Variations Demo 13 lodged or drafted · $354,921 unapproved
Accounting connected Thu 13 Aug 2026

Contracts

Variations

Scope added after award. Each variation carries its own priced lines, its approval status and the head contractor's reference, and joins the contract schedule of rates on approval.

Approved

$1.43M

30 variations, on the contract sums

Lodged, not approved

$355k

13 waiting on a head contractor

Already built, unapproved

$183k

8 with crews on them, cost with no revenue

Rejected

$18k

written off into the cost run

The exposure, in one place

$182,863.50 of work is physically on the ground against 8 variations that have not been approved. Each was instructed on site. Until they are approved, that value sits in cost with no revenue against it.

44 shown
Variation Job Head contractor Raised Their ref Value, ex GST Built Status
VAR-039-03 Purlin replacement, bays 15 to 26 QJ2039 Groote Eylandt Mining Company 9 Aug 2026 - $44,304.00 60% crew on it Submitted
VAR-046-03 Shed 2 sheet replacement, 40 sheets QJ2046 Downer Rail 5 Aug 2026 DWN-VO-0219 $17,120.00 0% Submitted
VAR-041-04 Lindum overpass: additional static line and anchor points QJ2041 Laing O'Rourke Australia 1 Aug 2026 LOR-VO-0182 $85,238.80 58% crew on it Submitted
VAR-045-02 Spider lift extended hire, 3 weeks QJ2045 M&A Developments 31 Jul 2026 MAA-VO-0038 $35,400.00 60% crew on it Submitted
VAR-047-02 Additional edge protection to the covered walkway QJ2047 Mountain Creek State High School, Dept of Education 29 Jul 2026 QED-VO-0117 $10,664.00 60% crew on it Submitted
VAR-006-03 Conveyor gallery access platform, additional static line QJ2006 Saipem Clough Joint Venture 29 Jul 2026 SCJV-VO-0271 $42,952.00 60% crew on it Submitted
VAR-042-01 Standing charge, material held at Landsborough QJ2042 Village Building Co. 28 Jul 2026 VIL-VO-0022 $4,992.00 0% Submitted
VAR-038-03 Membrane to the western gutter run QJ2038 Rio Tinto Aluminium 17 Jul 2026 RTA-VO-4451 $29,088.00 60% crew on it Submitted
VAR-044-03 Crane isolation standby, 4 shifts lost QJ2044 BHP Mitsubishi Alliance 2 Jul 2026 BMA-VO-2276 $46,944.00 60% crew on it Submitted
VAR-034-02 Defects attendance (parapet sealant and rainhead QJ1934 Department of Defence, Estate & Infrastructure 8 Aug 2026 - $4,867.20 0% Draft
VAR-041-05 Buranda: deletion of platform canopy roof lighting QJ2041 Laing O'Rourke Australia 7 Aug 2026 - -$12,672.00 0% Draft
VAR-006-04 Shed 2 south penetrations for the mechanical package QJ2006 Saipem Clough Joint Venture 7 Aug 2026 - $33,000.00 0% Draft
VAR-038-04 Additional shutdown attendance, July window QJ2038 Rio Tinto Aluminium 4 Aug 2026 - $13,023.00 60% crew on it Draft
VAR-049-01 Early works, conveyor permit and survey QJ2049 Bengalla Mining Company 5 Aug 2026 BGA-VO-0104 $10,168.00 86% Approved
VAR-044-04 Second personnel door, eastern elevation QJ2044 BHP Mitsubishi Alliance 24 Jul 2026 BMA-VO-2291 $1,840.00 12% Approved
VAR-047-01 Asbestos-containing sarking found, hold and dispose QJ2047 Mountain Creek State High School, Dept of Education 21 Jul 2026 QED-VO-0114 $21,512.00 86% Approved
VAR-039-02 Wash bay roof lighting replacement QJ2039 Groote Eylandt Mining Company 14 Jul 2026 GEM-VO-0124 $45,180.00 86% Approved
VAR-046-02 Shed 7 roof lighting replacement QJ2046 Downer Rail 7 Jul 2026 DWN-VO-0214 $16,632.00 86% Approved
VAR-045-01 Finesse set-out change to the northern elevation QJ2045 M&A Developments 25 Jun 2026 MAA-VO-0031 $27,228.00 86% Approved
VAR-039-01 Purlin replacement, bays 1 to 14 remeasured QJ2039 Groote Eylandt Mining Company 17 Jun 2026 GEM-VO-0117 $57,932.00 86% Approved
VAR-041-03 Architectural panel to Morningside entry, Finesse substitution QJ2041 Laing O'Rourke Australia 10 Jun 2026 LOR-VO-0168 $48,268.00 86% Approved
VAR-044-02 Additional louvre panels to the wash bay QJ2044 BHP Mitsubishi Alliance 5 Jun 2026 BMA-VO-2248 $24,336.00 86% Approved
VAR-006-02 Cyclone tie-down upgrade, both sheds QJ2006 Saipem Clough Joint Venture 3 Jun 2026 SCJV-VO-0246 $141,496.00 86% Approved
VAR-038-02 Rope access in lieu of EWP, southern elevation QJ2038 Rio Tinto Aluminium 27 May 2026 RTA-VO-4429 $18,280.00 86% Approved
VAR-046-01 Shed 4 leak rectification, additional 60 hours QJ2046 Downer Rail 14 May 2026 DWN-VO-0208 $18,550.00 86% Approved
VAR-036-03 Additional roof anchors to the crane runway QJ1936 Yancoal Australia 30 Apr 2026 YAN-VO-3371 $43,846.00 100% Approved
VAR-038-01 Acoustic enclosure extended to the second transfer point QJ2038 Rio Tinto Aluminium 28 Apr 2026 RTA-VO-4417 $90,444.00 86% Approved
VAR-044-01 Corroded purlin replacement, bays 4 to 9 QJ2044 BHP Mitsubishi Alliance 23 Apr 2026 BMA-VO-2211 $36,576.00 86% Approved
VAR-006-01 Additional roof lighting to Shed 1 QJ2006 Saipem Clough Joint Venture 22 Apr 2026 SCJV-VO-0218 $102,792.00 86% Approved
VAR-041-02 Extended possession, three additional night shutdowns QJ2041 Laing O'Rourke Australia 16 Apr 2026 LOR-VO-0141 $35,580.00 86% Approved
VAR-939-02 Additional insulated panel, office return wall QJ1939 McNab Constructions 9 Apr 2026 MCN-VO-0459 $51,708.00 100% Approved
VAR-036-02 Wet weather standby, February QJ1936 Yancoal Australia 12 Mar 2026 YAN-VO-3352 $49,812.00 100% Approved
VAR-939-01 Panel joint upgrade for cold-store certification QJ1939 McNab Constructions 21 Feb 2026 MCN-VO-0442 $33,216.00 100% Approved
VAR-041-01 Additional canopy sheeting, Banyo platform 2 QJ2041 Laing O'Rourke Australia 19 Feb 2026 LOR-VO-0113 $90,280.80 86% Approved
VAR-031-02 Security escort standby, 11 days QJ1931 Department of Defence, Estate & Infrastructure 2 Dec 2025 DEF-VO-1131 $68,904.00 100% Approved
VAR-036-01 Purlin renewal, northern bays QJ1936 Yancoal Australia 14 Nov 2025 YAN-VO-3318 $47,244.00 100% Approved
VAR-031-01 Additional flashing to the plant deck penetrations QJ1931 Department of Defence, Estate & Infrastructure 19 Sep 2025 DEF-VO-1104 $29,868.00 100% Approved
VAR-034-01 Panel colour change, full northern elevation QJ1934 Department of Defence, Estate & Infrastructure 27 Aug 2025 DEF-VO-0918 $202,492.00 100% Approved
VAR-028-01 Additional possession, Anzac weekend QJ1928 Queensland Rail 10 Apr 2025 QR-VO-0881 $23,720.00 100% Approved
VAR-028-02 Canopy gutter replacement QJ1928 Queensland Rail 19 Mar 2025 QR-VO-0872 $17,710.00 100% Approved
VAR-014-01 Additional safety mesh to the eastern bays QJ1814 MACH Energy, Mount Pleasant Operations 13 Mar 2024 MACH-VO-0210 $15,376.00 100% Approved
VAR-021-01 Conveyor cover extension, 40 lm QJ1821 BHP Mitsubishi Alliance 12 Dec 2023 BMA-VO-1802 $27,400.00 100% Approved
VAR-018-01 Heritage flashing detail to the pavilion parapet QJ1818 ADCO Constructions 24 Oct 2023 ADC-VO-1120 $31,848.00 100% Approved
VAR-044-05 Rejected (additional travel for the June roster change QJ2044 BHP Mitsubishi Alliance 10 Jul 2026 BMA-VO-2284 $18,480.00 60% crew on it Rejected