VAR-006-01 Demo Additional roof lighting to Shed 1
Accounting connected Thu 13 Aug 2026
VAR-006-01 Approved QJ2006

Variation 1, Additional roof lighting to Shed 1

PROJECT CERES - UREA SHEDS · Saipem Clough Joint Venture · their reference SCJV-VO-0218

Raised 22 Apr 2026 by Marcus Deng · approved 12 May 2026 by Dean Marchetti

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-ROF-SKY Fibreglass roof lighting, install $198.00/m² 380 $75,240.00 $64,330.20 14%
RS-WPF-PEN Roof penetration flashing, form & seal $684.00/ea 24 $16,416.00 $9,871.92 40%
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 320 $11,136.00 $8,841.60 21%
Total, ex GST $102,792.00 $83,043.72 19%
GST $10,279.20
Total, inc GST $113,071.20

Why it was raised

SCJV instruction after the lighting design was revised; the shed was too dark to work in with the original sheet layout.

Position

Value, ex GST
$102,792.00
Cost to deliver
$83,043.72
Margin
19.2%
Physically built
86%
Value already on the ground
$88,401.12
Work commenced
Yes, under site instruction

Contract

Contract no.
SCJV-CER-SC-1180
Head contractor
Saipem Clough Joint Venture
Approver
Dean Marchetti
Payment terms
45 days EOM
Open claim
PC-2026-0196

Trail

  1. Raised 22 Apr 2026 by Marcus DengPriced off the job's schedule of rates
  2. Lodged with Saipem Clough Joint VentureTheir reference SCJV-VO-0218
  3. Approved 12 May 2026Dean Marchetti · added to the contract sum and the open claim