Variation 1, Additional roof lighting to Shed 1
PROJECT CERES - UREA SHEDS · Saipem Clough Joint Venture · their reference SCJV-VO-0218
Raised 22 Apr 2026 by Marcus Deng · approved 12 May 2026 by Dean Marchetti
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-ROF-SKY Fibreglass roof lighting, install | $198.00/m² | 380 | $75,240.00 | $64,330.20 | 14% |
| RS-WPF-PEN Roof penetration flashing, form & seal | $684.00/ea | 24 | $16,416.00 | $9,871.92 | 40% |
| RS-WPF-SEA Sealant to laps, penetrations & flashings | $34.80/lm | 320 | $11,136.00 | $8,841.60 | 21% |
| Total, ex GST | $102,792.00 | $83,043.72 | 19% | ||
| GST | $10,279.20 | ||||
| Total, inc GST | $113,071.20 | ||||
Why it was raised
SCJV instruction after the lighting design was revised; the shed was too dark to work in with the original sheet layout.
Position
- Value, ex GST
- $102,792.00
- Cost to deliver
- $83,043.72
- Margin
- 19.2%
- Physically built
- 86%
- Value already on the ground
- $88,401.12
- Work commenced
- Yes, under site instruction
Contract
- Job
- QJ2006
- Contract no.
- SCJV-CER-SC-1180
- Head contractor
- Saipem Clough Joint Venture
- Approver
- Dean Marchetti
- Payment terms
- 45 days EOM
- Open claim
- PC-2026-0196
Trail
- Raised 22 Apr 2026 by Marcus DengPriced off the job's schedule of rates
- Lodged with Saipem Clough Joint VentureTheir reference SCJV-VO-0218
- Approved 12 May 2026Dean Marchetti · added to the contract sum and the open claim