VAR-046-01 Demo Shed 4 leak rectification, additional 60 hours
Accounting connected Thu 13 Aug 2026
VAR-046-01 Approved QJ2046

Variation 1, Shed 4 leak rectification, additional 60 hours

Downer Rail Maryborough: Periodic Roofing Works 2026 · Downer Rail · their reference DWN-VO-0208

Raised 14 May 2026 by Cameron Hale · approved 27 May 2026 by Paul Mistry

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-WPF-LEK Leak investigation & rectification $168.00/hr 60 $10,080.00 $8,280.00 18%
RS-ROF-GUT Box gutter, supply and install $385.00/lm 22 $8,470.00 $7,216.66 15%
Total, ex GST $18,550.00 $15,496.66 16%
GST $1,855.00
Total, inc GST $20,405.00

Why it was raised

Leak traced to a failed gutter joint rather than the sheet; scope grew on investigation.

Position

Value, ex GST
$18,550.00
Cost to deliver
$15,496.66
Margin
16.5%
Physically built
86%
Value already on the ground
$15,953.00
Work commenced
Yes, under site instruction

Contract

Contract no.
DWN-MBH-PER-2026
Head contractor
Downer Rail
Approver
Paul Mistry
Payment terms
30 days

Trail

  1. Raised 14 May 2026 by Cameron HalePriced off the job's schedule of rates
  2. Lodged with Downer RailTheir reference DWN-VO-0208
  3. Approved 27 May 2026Paul Mistry · added to the contract sum and the open claim