QClad
QClad
VAR-046-01 Demo Shed 4 leak rectification, additional 60 hours
Accounting connected Wed 5 Aug 2026
VAR-046-01 Approved PRJ-2026-046

Variation 1, Shed 4 leak rectification, additional 60 hours

Downer Rail Maryborough: Periodic Roofing Works 2026 · Downer Rail · their reference DWN-VO-0208

Raised 6 May 2026 by Cameron Doyle · approved 19 May 2026 by Paul Mistry

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-WPF-LEK Leak investigation & rectification $168.00/hr 60 $10,080.00 $8,280.00 18%
RS-ROF-GUT Box gutter, supply and install $385.00/lm 22 $8,470.00 $7,216.66 15%
Total, ex GST $18,550.00 $15,496.66 16%
GST $1,855.00
Total, inc GST $20,405.00

Why it was raised

Leak traced to a failed gutter joint rather than the sheet; scope grew on investigation.

Position

Value, ex GST
$18,550.00
Cost to deliver
$15,496.66
Margin
16.5%
Physically built
86%
Value already on the ground
$15,953.00
Work commenced
Yes, under site instruction

Contract

Contract no.
DWN-MBH-PER-2026
Head contractor
Downer Rail
Approver
Paul Mistry
Payment terms
30 days

Trail

  1. Raised 6 May 2026 by Cameron DoylePriced off the project schedule of rates
  2. Lodged with Downer RailTheir reference DWN-VO-0208
  3. Approved 19 May 2026Paul Mistry · added to the contract sum and the open claim