Variation 1, Shed 4 leak rectification, additional 60 hours
Downer Rail Maryborough: Periodic Roofing Works 2026 · Downer Rail · their reference DWN-VO-0208
Raised 6 May 2026 by Cameron Doyle · approved 19 May 2026 by Paul Mistry
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-WPF-LEK Leak investigation & rectification | $168.00/hr | 60 | $10,080.00 | $8,280.00 | 18% |
| RS-ROF-GUT Box gutter, supply and install | $385.00/lm | 22 | $8,470.00 | $7,216.66 | 15% |
| Total, ex GST | $18,550.00 | $15,496.66 | 16% | ||
| GST | $1,855.00 | ||||
| Total, inc GST | $20,405.00 | ||||
Why it was raised
Leak traced to a failed gutter joint rather than the sheet; scope grew on investigation.
Position
- Value, ex GST
- $18,550.00
- Cost to deliver
- $15,496.66
- Margin
- 16.5%
- Physically built
- 86%
- Value already on the ground
- $15,953.00
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2026-046
- Contract no.
- DWN-MBH-PER-2026
- Head contractor
- Downer Rail
- Approver
- Paul Mistry
- Payment terms
- 30 days
Trail
- Raised 6 May 2026 by Cameron DoylePriced off the project schedule of rates
- Lodged with Downer RailTheir reference DWN-VO-0208
- Approved 19 May 2026Paul Mistry · added to the contract sum and the open claim