QClad
QClad
VAR-039-01 Demo Purlin replacement, bays 1 to 14 remeasured
Accounting connected Thu 13 Aug 2026
VAR-039-01 Approved QJ2039

Variation 1, Purlin replacement, bays 1 to 14 remeasured

Groote Island: Mobile Plant Workshop Re-roof · Groote Eylandt Mining Company · their reference GEM-VO-0117

Raised 17 Jun 2026 by Cameron Hale · approved 4 Jul 2026 by Warrick Delaney

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-ROF-STR Strip existing roof sheeting & dispose $52.40/m² 640 $33,536.00 $30,995.20 8%
RS-CLD-FLA Custom flashings, supply and install $114.00/lm 214 $24,396.00 $19,795.00 19%
Total, ex GST $57,932.00 $50,790.20 12%
GST $5,793.20
Total, inc GST $63,725.20

Why it was raised

Provisional quantity at tender. With the sheeting off, 214 lm of purlin is corroded through rather than the 120 lm allowed.

Position

Value, ex GST
$57,932.00
Cost to deliver
$50,790.20
Margin
12.3%
Physically built
86%
Value already on the ground
$49,821.52
Work commenced
Yes, under site instruction

Contract

Contract no.
S32-GEM-2026-0918
Head contractor
Groote Eylandt Mining Company
Approver
Warrick Delaney
Payment terms
45 days EOM
Open claim
PC-2026-0197

Trail

  1. Raised 17 Jun 2026 by Cameron HalePriced off the job's schedule of rates
  2. Lodged with Groote Eylandt Mining CompanyTheir reference GEM-VO-0117
  3. Approved 4 Jul 2026Warrick Delaney · added to the contract sum and the open claim