QJ2047 Demo Mountain Creek SHS: Hall Re-roof & Cladding
Accounting connected Thu 13 Aug 2026
QJ2047 On site Commercial

Mountain Creek SHS: Hall Re-roof & Cladding

Mountain Creek State High School, Dept of Education · Mountain Creek, Sunshine Coast, QLD · contract QED-MCSHS-2026-0331

Cameron Hale · 7 Jul 2026 → 10 Oct 2026

Client view

School occupied, all noisy works outside class hours or in term break. Full perimeter edge protection required by the Department before any roof access.

The position

Every figure below is the sum of rows on this page.

Contract sum

$967,046

Tendered
$945,534
Approved variations
+$21,512
Lodged, not approved
$10,664

Work in place

$460,403

Complete
47.6%
Still to run
$506,643

Claimed & certified

$434,621

Certified
$252,301
Unclaimed WIP
$25,783
Retention held
$12,615

Margin

$79,281 17.2%

Cost of work in place
$381,122
Against the build-up
-$3,200
Committed, not received
$0

$6,398.40 of work is on the ground against variations nobody has approved.

VAR-047-02, Additional edge protection to the covered walkway. Until they are approved they sit in cost with no revenue against them.

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 6 tasks · General $183,878 $97,774 53% 998.4 495.1 $0 -$584 - -$1,420 19%
CC-02 Roofing 8 tasks · General $589,656 $272,957 46% 2,083.8 1,014.1 $77,071 $76,408 $22,176 -$1,363 16%
CC-03 Wall cladding 1 task · General $65,536 $19,005 29% 192 55.2 $7,693 $7,625 - -$116 18%
CC-05 Height access & safety systems 2 tasks · General $65,744 $51,060 78% 160.9 120.8 $3,408 $3,285 $3,408 -$186 18%
CC-06 Weatherproofing 2 tasks · General $62,232 $19,606 32% 302.2 95.6 $1,635 $1,611 - -$115 28%
Job total $967,046 $460,403 48% 3,737.3 1,780.8 $89,807 $88,345 $25,584 -$3,200 17%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $381,122, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$97,774 of $183,878 · 53%
TaskSub-jobContractDone%ValueEarnedHours
Site supervision, leading hand RS-PRE-SUP General 68 day 27.88 41% $84,864 $34,794 292.7 of 714
Scaffold: supply, erect, hire 8 weeks, dismantle RS-PRE-SCF General 640 m² 352 55% $60,480 $33,264 21.1 of 38.4
Mobilisation & site establishment RS-PRE-MOB General 1 item 1 100% $18,450 $18,450 96 of 96
Site supervision, leading hand RS-PRE-SUP · VAR-047-01 General 8 day 6.88 86% $9,984 $8,586 72.2 of 84
Demobilisation & make good RS-PRE-DEM General 1 item 0 0% $7,420 $0 0 of 44
SWMS, JSA & site-specific safety plan RS-PRE-SWM General 1 item 1 100% $2,680 $2,680 22 of 22
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$272,957 of $589,656 · 46%
TaskSub-jobContractDone%ValueEarnedHours
KLIP-LOK 406 roof sheeting, install RS-ROF-KL4 General 1,980 m² 871.2 44% $230,472 $101,408 287.5 of 653.4
Strip existing roof sheeting & dispose RS-ROF-STR General 1,980 m² 1,227.6 62% $103,752 $64,326 356 of 574.2
Roof insulation blanket 75mm R1.8, install RS-ROF-INS General 1,980 m² 871.2 44% $78,408 $34,500 122 of 277.2
Box gutter, supply and install RS-ROF-GUT General 168 lm 53.76 32% $64,680 $20,698 57 of 178.1
Safety mesh, install to purlins RS-ROF-SAF General 1,980 m² 990 50% $49,104 $24,552 94.1 of 188.1
Ridge capping & barge, supply and install RS-ROF-RDG General 224 lm 85.12 38% $32,704 $12,428 34 of 89.6
Downpipe & rainhead, supply and install RS-ROF-DWP General 22 ea 5.94 27% $19,008 $5,132 16 of 59.4
Strip existing roof sheeting & dispose RS-ROF-STR · VAR-047-01 General 220 m² 189.2 86% $11,528 $9,914 54.9 of 63.8
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$19,005 of $65,536 · 29%
TaskSub-jobContractDone%ValueEarnedHours
CUSTOM ORB wall cladding, install RS-CLD-CUS General 640 m² 185.6 29% $65,536 $19,005 55.7 of 192
CC-05 Height access & safety systems Anchor points, static lines, guardrail, rope access and elevated work platforms.
$51,060 of $65,744 · 78%
TaskSub-jobContractDone%ValueEarnedHours
Roof edge guardrail, install & hire RS-HGT-GRD General 386 lm 339.68 88% $47,864 $42,120 95.1 of 108.1
Roof anchor point: supply, install & certify RS-HGT-ANC General 24 ea 12 50% $17,880 $8,940 26.4 of 52.8
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$19,606 of $62,232 · 32%
TaskSub-jobContractDone%ValueEarnedHours
Sealant to laps, penetrations & flashings RS-WPF-SEA General 1,120 lm 369.6 33% $38,976 $12,862 73.9 of 224
Roof penetration flashing, form & seal RS-WPF-PEN General 34 ea 9.86 29% $23,256 $6,744 22.7 of 78.2

Correspondence

RFIs, material approvals and anything else sent about QJ2047, with the replies on the same thread.

Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.