Variation 2, Additional edge protection to the covered walkway
Mountain Creek SHS: Hall Re-roof & Cladding · Mountain Creek State High School, Dept of Education · their reference QED-VO-0117
Raised 29 Jul 2026 by Cameron Hale
Effect of approval
These lines join QJ2047's schedule of rates. With 60% of the work already in place, the value of work in place moves with the contract sum, the open progress claim measures the difference, the job's margin recalculates, and an acknowledgement is issued to the head contractor.
Contract sum
$967,046 → $977,710
Work in place
$460,403 → $466,802
Next claim
$0 → $6,398
Margin on QJ2047
17.2% → 17.2%
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-HGT-GRD Roof edge guardrail, install & hire | $124.00/lm | 86 | $10,664.00 | $8,778.88 | 18% |
| Total, ex GST | $10,664.00 | $8,778.88 | 18% | ||
| GST | $1,066.40 | ||||
| Total, inc GST | $11,730.40 | ||||
Why it was raised
Department required guardrail to the walkway roof before any access, not in scope.
Position
- Value, ex GST
- $10,664.00
- Cost to deliver
- $8,778.88
- Margin
- 17.7%
- Physically built
- 60%
- Value already on the ground
- $6,398.40
- Work commenced
- Yes, under site instruction
Contract
- Job
- QJ2047
- Contract no.
- QED-MCSHS-2026-0331
- Head contractor
- Mountain Creek State High School, Dept of Education
- Approver
- Ian Bardsley
- Payment terms
- 30 days
Trail
- Raised 29 Jul 2026 by Cameron HalePriced off the job's schedule of rates
- Lodged with Mountain Creek State High School, Dept of EducationTheir reference QED-VO-0117