Variation 1, Additional safety mesh to the eastern bays
Mount Pleasant Mine: Workshop Roofing · MACH Energy, Mount Pleasant Operations · their reference MACH-VO-0210
Raised 5 Mar 2024 by Cameron Doyle · approved 19 Mar 2024 by Terry Bligh
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-ROF-SAF Safety mesh, install to purlins | $24.80/m² | 620 | $15,376.00 | $12,437.20 | 19% |
| Total, ex GST | $15,376.00 | $12,437.20 | 19% | ||
| GST | $1,537.60 | ||||
| Total, inc GST | $16,913.60 | ||||
Why it was raised
Mine standard required mesh where the tender allowed harness only.
Position
- Value, ex GST
- $15,376.00
- Cost to deliver
- $12,437.20
- Margin
- 19.1%
- Physically built
- 100%
- Value already on the ground
- $15,376.00
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2024-014
- Contract no.
- MACH-MP-WS-2023-8890
- Head contractor
- MACH Energy, Mount Pleasant Operations
- Approver
- Terry Bligh
- Payment terms
- 45 days EOM
Trail
- Raised 5 Mar 2024 by Cameron DoylePriced off the project schedule of rates
- Lodged with MACH Energy, Mount Pleasant OperationsTheir reference MACH-VO-0210
- Approved 19 Mar 2024Terry Bligh · added to the contract sum and the open claim