VAR-014-01 Demo Additional safety mesh to the eastern bays
Accounting connected Thu 13 Aug 2026
VAR-014-01 Approved QJ1814

Variation 1, Additional safety mesh to the eastern bays

Mount Pleasant Mine: Workshop Roofing · MACH Energy, Mount Pleasant Operations · their reference MACH-VO-0210

Raised 13 Mar 2024 by Cameron Hale · approved 27 Mar 2024 by Terry Bligh

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-ROF-SAF Safety mesh, install to purlins $24.80/m² 620 $15,376.00 $12,437.20 19%
Total, ex GST $15,376.00 $12,437.20 19%
GST $1,537.60
Total, inc GST $16,913.60

Why it was raised

Mine standard required mesh where the tender allowed harness only.

Position

Value, ex GST
$15,376.00
Cost to deliver
$12,437.20
Margin
19.1%
Physically built
100%
Value already on the ground
$15,376.00
Work commenced
Yes, under site instruction

Contract

Contract no.
MACH-MP-WS-2023-8890
Head contractor
MACH Energy, Mount Pleasant Operations
Approver
Terry Bligh
Payment terms
45 days EOM

Trail

  1. Raised 13 Mar 2024 by Cameron HalePriced off the job's schedule of rates
  2. Lodged with MACH Energy, Mount Pleasant OperationsTheir reference MACH-VO-0210
  3. Approved 27 Mar 2024Terry Bligh · added to the contract sum and the open claim