VAR-014-01 Demo Additional safety mesh to the eastern bays
Accounting connected Wed 5 Aug 2026
VAR-014-01 Approved PRJ-2024-014

Variation 1, Additional safety mesh to the eastern bays

Mount Pleasant Mine: Workshop Roofing · MACH Energy, Mount Pleasant Operations · their reference MACH-VO-0210

Raised 5 Mar 2024 by Cameron Doyle · approved 19 Mar 2024 by Terry Bligh

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-ROF-SAF Safety mesh, install to purlins $24.80/m² 620 $15,376.00 $12,437.20 19%
Total, ex GST $15,376.00 $12,437.20 19%
GST $1,537.60
Total, inc GST $16,913.60

Why it was raised

Mine standard required mesh where the tender allowed harness only.

Position

Value, ex GST
$15,376.00
Cost to deliver
$12,437.20
Margin
19.1%
Physically built
100%
Value already on the ground
$15,376.00
Work commenced
Yes, under site instruction

Contract

Contract no.
MACH-MP-WS-2023-8890
Head contractor
MACH Energy, Mount Pleasant Operations
Approver
Terry Bligh
Payment terms
45 days EOM

Trail

  1. Raised 5 Mar 2024 by Cameron DoylePriced off the project schedule of rates
  2. Lodged with MACH Energy, Mount Pleasant OperationsTheir reference MACH-VO-0210
  3. Approved 19 Mar 2024Terry Bligh · added to the contract sum and the open claim