QRSAUP: Brisbane Rail Stations Roofing & Cladding
Laing O'Rourke Australia · Banyo, Buranda, Morningside & Lindum stations, QLD · contract LOR-QRSAUP-SC-0442
Marcus Deng · Crew 1, Rail · 16 Dec 2025 → 5 Dec 2026
Four stations, four accessible overpasses, platform canopies and station buildings. Large portions installable only inside rail possessions, night shutdowns priced separately. Limited laydown; most flashing prefabricated at Landsborough.
The position
Every figure below is the sum of rows on this page.
Contract sum
$4,093,279
- Tendered
- $3,919,150
- Approved variations
- +$174,129
- Lodged, not approved
- $72,567
Work in place
$2,499,553
- Complete
- 61.1%
- Still to run
- $1,593,726
Claimed & certified
$2,387,073
- Certified
- $2,384,573
- Unclaimed WIP
- $112,480
- Retention held
- $119,229
Margin
$456,408 18.3%
- Cost of work in place
- $2,043,145
- Against the build-up
- +$41,800
- Committed, not received
- $65,904
$49,438.50 of work is on the ground against variations nobody has approved.
VAR-041-04, Lindum overpass: additional static line and anchor points. Until they are approved they sit in cost with no revenue against them.
Cost centres
Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.
| Cost centre | Value | Earned | % | Budget hrs | Actual hrs | Budget material | Actual material | Committed | Run | Margin |
|---|---|---|---|---|---|---|---|---|---|---|
| CC-01 Preliminaries & establishment 8 tasks · General | $1,215,310 | $783,852 | 64% | 7,614.8 | 4,960.2 | $0 | $6,332 | - | +$23,409 | 18% |
| CC-02 Roofing 12 tasks · General | $1,459,321 | $922,423 | 63% | 4,542.3 | 2,960.4 | $326,379 | $331,532 | $31,872 | +$9,458 | 18% |
| CC-03 Wall cladding 6 tasks · General | $838,500 | $440,161 | 52% | 2,461.7 | 1,318 | $175,869 | $179,192 | $27,079 | +$5,710 | 17% |
| CC-05 Height access & safety systems 3 tasks · General | $395,000 | $255,804 | 65% | 1,695.2 | 1,086.8 | $51,706 | $52,632 | $26,560 | +$1,963 | 18% |
| CC-06 Weatherproofing 4 tasks · General | $185,148 | $97,313 | 53% | 923.8 | 508.2 | $7,520 | $7,768 | - | +$1,259 | 24% |
| Job total | $4,093,279 | $2,499,553 | 61% | 17,237.8 | 10,833.6 | $561,474 | $577,457 | $85,511 | +$41,800 | 18% |
The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $2,043,145, which is the job's actual cost.
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| Rail shutdown premium, night possession RS-PRE-SHT | General | 46 day | 27.14 | 59% | $545,560 | $321,880 | 2,388.3 of 4,048 |
| Site supervision, leading hand RS-PRE-SUP | General | 232 day | 143.84 | 62% | $289,536 | $179,512 | 1,510.3 of 2,436 |
| Scaffold: supply, erect, hire 8 weeks, dismantle RS-PRE-SCF | General | 2,180 m² | 1,547.8 | 71% | $217,564 | $154,470 | 92.9 of 130.8 |
| Mobilisation & site establishment RS-PRE-MOB | General | 4 item | 4 | 100% | $73,800 | $73,800 | 384 of 384 |
| Rail shutdown premium, night possession RS-PRE-SHT · VAR-041-02 | General | 3 day | 2.58 | 86% | $35,580 | $30,599 | 227 of 264 |
| Demobilisation & make good RS-PRE-DEM | General | 4 item | 0 | 0% | $29,680 | $0 | 0 of 176 |
| Site induction & verification of competency RS-PRE-IND | General | 22 ea | 22 | 100% | $12,870 | $12,870 | 88 of 88 |
| SWMS, JSA & site-specific safety plan RS-PRE-SWM | General | 4 item | 4 | 100% | $10,720 | $10,720 | 88 of 88 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| KLIP-LOK 700 HI-STRENGTH roof sheeting, install RS-ROF-KL7 | General | 4,820 m² | 3,084.8 | 64% | $638,168 | $408,428 | 1,110.5 of 1,735.2 |
| Roof insulation blanket 75mm R1.8, install RS-ROF-INS | General | 4,820 m² | 3,084.8 | 64% | $190,872 | $122,158 | 431.9 of 674.8 |
| Box gutter, supply and install RS-ROF-GUT | General | 388 lm | 201.76 | 52% | $149,380 | $77,678 | 213.9 of 411.3 |
| Safety mesh, install to purlins RS-ROF-SAF | General | 4,820 m² | 3,181.2 | 66% | $119,536 | $78,894 | 302.2 of 457.9 |
| Ridge capping & barge, supply and install RS-ROF-RDG | General | 612 lm | 354.96 | 58% | $89,352 | $51,824 | 142 of 244.8 |
| Strip existing roof sheeting & dispose RS-ROF-STR | General | 1,640 m² | 1,279.2 | 78% | $85,936 | $67,030 | 371 of 475.6 |
| Fibreglass roof lighting, install RS-ROF-SKY | General | 320 m² | 131.2 | 41% | $63,360 | $25,978 | 69.5 of 169.6 |
| KLIP-LOK 700 HI-STRENGTH roof sheeting, install RS-ROF-KL7 · VAR-041-01 | General | 386 m² | 331.96 | 86% | $51,106 | $43,952 | 119.5 of 139 |
| Downpipe & rainhead, supply and install RS-ROF-DWP | General | 46 ea | 22.08 | 48% | $39,744 | $19,077 | 59.6 of 124.2 |
| Roof insulation blanket 75mm R1.8, install RS-ROF-INS · VAR-041-01 | General | 386 m² | 331.96 | 86% | $15,286 | $13,146 | 46.5 of 54 |
| Safety mesh, install to purlins RS-ROF-SAF · VAR-041-01 | General | 386 m² | 331.96 | 86% | $9,573 | $8,233 | 31.5 of 36.7 |
| Ridge capping & barge, supply and install RS-ROF-RDG · VAR-041-01 | General | 48 lm | 41.28 | 86% | $7,008 | $6,027 | 16.5 of 19.2 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| CUSTOM ORB wall cladding, install RS-CLD-CUS | General | 2,940 m² | 1,675.8 | 57% | $301,056 | $171,602 | 502.7 of 882 |
| Custom flashings, supply and install RS-CLD-FLA | General | 1,860 lm | 1,023 | 55% | $212,040 | $116,622 | 347.8 of 632.4 |
| Fielders Finesse architectural cladding, install RS-CLD-FIN | General | 680 m² | 231.2 | 34% | $153,680 | $52,251 | 152.6 of 448.8 |
| Corner & parapet capping, supply and install RS-CLD-CAP | General | 940 lm | 460.6 | 49% | $129,720 | $63,563 | 184.2 of 376 |
| Fielders Finesse architectural cladding, install RS-CLD-FIN · VAR-041-03 | General | 148 m² | 127.28 | 86% | $33,448 | $28,765 | 84 of 97.7 |
| Corner & parapet capping, supply and install RS-CLD-CAP · VAR-041-03 | General | 62 lm | 53.32 | 86% | $8,556 | $7,358 | 21.3 of 24.8 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| EWP hire & operator, 45ft boom RS-HGT-EWP | General | 118 day | 71.98 | 61% | $210,040 | $128,124 | 719.8 of 1,180 |
| Static line system: supply, install & certify RS-HGT-STA | General | 480 lm | 326.4 | 68% | $137,280 | $93,350 | 254.6 of 374.4 |
| Roof anchor point: supply, install & certify RS-HGT-ANC | General | 64 ea | 46.08 | 72% | $47,680 | $34,330 | 101.4 of 140.8 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| Sealant to laps, penetrations & flashings RS-WPF-SEA | General | 3,240 lm | 1,717.2 | 53% | $112,752 | $59,759 | 343.4 of 648 |
| Roof penetration flashing, form & seal RS-WPF-PEN | General | 86 ea | 37.84 | 44% | $58,824 | $25,883 | 87 of 197.8 |
| Sealant to laps, penetrations & flashings RS-WPF-SEA · VAR-041-01 | General | 210 lm | 180.6 | 86% | $7,308 | $6,285 | 36.1 of 42 |
| Sealant to laps, penetrations & flashings RS-WPF-SEA · VAR-041-03 | General | 180 lm | 154.8 | 86% | $6,264 | $5,387 | 31 of 36 |
Schedule of rates
Contract quantity, measured to date, and what each line is worth. Lines added by a variation carry its number.
| Rate | Rate, ex GST | Qty | Measured | Contract value | In place | Cost of it | Margin |
|---|---|---|---|---|---|---|---|
| Preliminaries | |||||||
| RS-PRE-MOB Mobilisation & site establishment | $18,450.00/item | 4 | 4 100% | $73,800 | $73,800 | $60,896 | 17% |
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | $2,680.00/item | 4 | 4 100% | $10,720 | $10,720 | $9,152 | 15% |
| RS-PRE-IND Site induction & verification of competency | $585.00/ea | 22 | 22 100% | $12,870 | $12,870 | $10,362 | 19% |
| RS-PRE-SUP Site supervision, leading hand | $1,248.00/day | 232 | 143.84 62% | $289,536 | $179,512 | $148,874 | 17% |
| RS-PRE-SHT Rail shutdown premium, night possession | $11,860.00/day | 46 | 27.14 59% | $545,560 | $321,880 | $244,586 | 24% |
| RS-PRE-SCF Scaffold: supply, erect, hire 8 weeks, dismantle | $99.80/m² | 2,180 | 1,547.8 71% | $217,564 | $154,470 | $118,623 | 23% |
| RS-PRE-DEM Demobilisation & make good | $7,420.00/item | 4 | 0 0% | $29,680 | $0 | $0 | - |
| RS-PRE-SHT Rail shutdown premium, night possession · VAR-041-02 | $11,860.00/day | 3 | 2.58 86% | $35,580 | $30,599 | $23,251 | 24% |
| Roofing | |||||||
| RS-ROF-STR Strip existing roof sheeting & dispose | $52.40/m² | 1,640 | 1,279.2 78% | $85,936 | $67,030 | $61,952 | 8% |
| RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install | $132.40/m² | 4,820 | 3,084.8 64% | $638,168 | $408,428 | $322,115 | 21% |
| RS-ROF-INS Roof insulation blanket 75mm R1.8, install | $39.60/m² | 4,820 | 3,084.8 64% | $190,872 | $122,158 | $97,665 | 20% |
| RS-ROF-SAF Safety mesh, install to purlins | $24.80/m² | 4,820 | 3,181.2 66% | $119,536 | $78,894 | $63,815 | 19% |
| RS-ROF-RDG Ridge capping & barge, supply and install | $146.00/lm | 612 | 354.96 58% | $89,352 | $51,824 | $39,997 | 23% |
| RS-ROF-GUT Box gutter, supply and install | $385.00/lm | 388 | 201.76 52% | $149,380 | $77,678 | $66,183 | 15% |
| RS-ROF-DWP Downpipe & rainhead, supply and install | $864.00/ea | 46 | 22.08 48% | $39,744 | $19,077 | $15,903 | 17% |
| RS-ROF-SKY Fibreglass roof lighting, install | $198.00/m² | 320 | 131.2 41% | $63,360 | $25,978 | $22,211 | 14% |
| RS-ROF-KL7 KLIP-LOK 700 HI-STRENGTH roof sheeting, install · VAR-041-01 | $132.40/m² | 386 | 331.96 86% | $51,106 | $43,952 | $34,663 | 21% |
| RS-ROF-INS Roof insulation blanket 75mm R1.8, install · VAR-041-01 | $39.60/m² | 386 | 331.96 86% | $15,286 | $13,146 | $10,510 | 20% |
| RS-ROF-SAF Safety mesh, install to purlins · VAR-041-01 | $24.80/m² | 386 | 331.96 86% | $9,573 | $8,233 | $6,659 | 19% |
| RS-ROF-RDG Ridge capping & barge, supply and install · VAR-041-01 | $146.00/lm | 48 | 41.28 86% | $7,008 | $6,027 | $4,651 | 23% |
| Wall cladding | |||||||
| RS-CLD-CUS CUSTOM ORB wall cladding, install | $102.40/m² | 2,940 | 1,675.8 57% | $301,056 | $171,602 | $142,192 | 17% |
| RS-CLD-FIN Fielders Finesse architectural cladding, install | $226.00/m² | 680 | 231.2 34% | $153,680 | $52,251 | $43,144 | 17% |
| RS-CLD-FLA Custom flashings, supply and install | $114.00/lm | 1,860 | 1,023 55% | $212,040 | $116,622 | $94,628 | 19% |
| RS-CLD-CAP Corner & parapet capping, supply and install | $138.00/lm | 940 | 460.6 49% | $129,720 | $63,563 | $50,864 | 20% |
| RS-CLD-FIN Fielders Finesse architectural cladding, install · VAR-041-03 | $226.00/m² | 148 | 127.28 86% | $33,448 | $28,765 | $23,752 | 17% |
| RS-CLD-CAP Corner & parapet capping, supply and install · VAR-041-03 | $138.00/lm | 62 | 53.32 86% | $8,556 | $7,358 | $5,888 | 20% |
| Height access | |||||||
| RS-HGT-ANC Roof anchor point: supply, install & certify | $745.00/ea | 64 | 46.08 72% | $47,680 | $34,330 | $28,560 | 17% |
| RS-HGT-STA Static line system: supply, install & certify | $286.00/lm | 480 | 326.4 68% | $137,280 | $93,350 | $77,200 | 17% |
| RS-HGT-EWP EWP hire & operator, 45ft boom | $1,780.00/day | 118 | 71.98 61% | $210,040 | $128,124 | $100,772 | 21% |
| Weatherproofing | |||||||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | $34.80/lm | 3,240 | 1,717.2 53% | $112,752 | $59,759 | $47,446 | 21% |
| RS-WPF-PEN Roof penetration flashing, form & seal | $684.00/ea | 86 | 37.84 44% | $58,824 | $25,883 | $15,565 | 40% |
| RS-WPF-SEA Sealant to laps, penetrations & flashings · VAR-041-01 | $34.80/lm | 210 | 180.6 86% | $7,308 | $6,285 | $4,990 | 21% |
| RS-WPF-SEA Sealant to laps, penetrations & flashings · VAR-041-03 | $34.80/lm | 180 | 154.8 86% | $6,264 | $5,387 | $4,277 | 21% |
| Total | $4,093,279 | $2,499,553 | $2,001,345 | 20% | |||
Variations
An approved variation's lines join the schedule of rates above on approval.
| No. | Variation | Raised | Their ref | Value, ex GST | Built | Status |
|---|---|---|---|---|---|---|
| 5 | VAR-041-05 Buranda: deletion of platform canopy roof lighting | 7 Aug 2026 | - | -$12,672.00 | 0% | Draft |
| 4 | VAR-041-04 Lindum overpass: additional static line and anchor points | 1 Aug 2026 | LOR-VO-0182 | $85,238.80 | 58% | Submitted |
| 3 | VAR-041-03 Architectural panel to Morningside entry, Finesse substitution | 10 Jun 2026 | LOR-VO-0168 | $48,268.00 | 86% | Approved |
| 2 | VAR-041-02 Extended possession, three additional night shutdowns | 16 Apr 2026 | LOR-VO-0141 | $35,580.00 | 86% | Approved |
| 1 | VAR-041-01 Additional canopy sheeting, Banyo platform 2 | 19 Feb 2026 | LOR-VO-0113 | $90,280.80 | 86% | Approved |
Progress claims
Lodged under the QLD BIF Act: 15 business days to a payment schedule, 25 to payment. Retention at 5%.
| Claim | Period | This claim, ex GST | Retention | Inc GST | Lodged | Invoice | Status |
|---|---|---|---|---|---|---|---|
| PC-2026-0187No. 9 | Aug 2026 | $112,479.90 | $5,624.00 | $117,541.49 | - | - | Draft |
| PC-2026-0185No. 8 | Jul 2026 | $217,461.13 | $10,873.06 | $227,246.88 | 8 Aug 2026 | INV-26-0412 | Short certified |
| PC-2026-0181No. 7 | Jun 2026 | $344,938.36 | $17,246.92 | $360,460.58 | 8 Jul 2026 | INV-26-0398 | Paid |
| PC-2026-0176No. 6 | May 2026 | $369,933.89 | $18,496.69 | $386,580.92 | 6 Jun 2026 | INV-26-0384 | Paid |
| PC-2026-0170No. 5 | Apr 2026 | $354,936.56 | $17,746.83 | $370,908.70 | 8 May 2026 | INV-26-0369 | Paid |
| PC-2026-0163No. 4 | Mar 2026 | $324,941.93 | $16,247.10 | $339,564.31 | 8 Apr 2026 | INV-26-0351 | Paid |
| PC-2026-0156No. 3 | Feb 2026 | $302,445.95 | $15,122.30 | $316,056.02 | 7 Mar 2026 | INV-26-0334 | Paid |
| PC-2026-0149No. 2 | Jan 2026 | $267,452.20 | $13,372.61 | $279,487.55 | 7 Feb 2026 | INV-26-0318 | Paid |
| PC-2026-0142No. 1 | Dec 2025 | $204,963.37 | $10,248.17 | $214,186.72 | 6 Jan 2026 | INV-26-0301 | Paid |
Invoices
| Invoice | Issued | Due | Inc GST | Ledger | Status |
|---|---|---|---|---|---|
| INV-26-0412 | 12 Aug 2026 | 11 Sep 2026 | $224,634.38 | XRO-4114 | Sent |
| INV-26-0398 | 29 Jul 2026 | 12 Aug 2026 | $360,460.58 | XRO-4113 | Paid |
| INV-26-0384 | 27 Jun 2026 | 10 Jul 2026 | $386,580.92 | XRO-4112 | Paid |
| INV-26-0369 | 29 May 2026 | 12 Jun 2026 | $370,908.70 | XRO-4111 | Paid |
| INV-26-0351 | 29 Apr 2026 | 13 May 2026 | $339,564.31 | XRO-4110 | Paid |
| INV-26-0334 | 27 Mar 2026 | 10 Apr 2026 | $316,056.02 | XRO-4109 | Paid |
| INV-26-0318 | 26 Feb 2026 | 13 Mar 2026 | $279,487.55 | XRO-4108 | Paid |
| INV-26-0301 | 24 Jan 2026 | 10 Feb 2026 | $214,186.72 | XRO-4107 | Paid |
Labour booked this week
1100 hours, $65,720.00 of cost, off the crew app. 9,842 hours on this job to date.
| Day card | Person | Date | Task | Rate | Hours | Cost | Status |
|---|---|---|---|---|---|---|---|
| TS-20260803-0001 | Blake TuialaLeading Hand | Mon 3 Aug | Rail: supervision, crew of 12 | RS-PRE-SUP | 10 +2 | $832.00 | Approved |
| TS-20260803-0002 | Ryan PetrieRoof Plumber | Mon 3 Aug | Lindum overpass, static line install (VAR-041-04) | RS-HGT-STA | 10 +2 | $754.00 | Approved |
| TS-20260803-0003 | Josh MardinRoof Plumber | Mon 3 Aug | Morningside, flashing to the canopy fascia | RS-CLD-FLA | 10 +2 | $754.00 | Approved |
| TS-20260803-0004 | Dane KelsoCladding Installer | Mon 3 Aug | Banyo: canopy sheeting, bays 6 to 11 | RS-ROF-KL7 | 10 +2 | $702.00 | Approved |
| TS-20260803-0005 | Tyrone BakerCladding Installer | Mon 3 Aug | Buranda, sealant to laps and penetrations | RS-WPF-SEA | 10 +2 | $702.00 | Approved |
| TS-20260803-0006 | Isaac VellaRope Access Tech | Mon 3 Aug | Lindum, anchor point install and certification | RS-HGT-ANC | 10 +2 | $897.00 | Approved |
| TS-20260803-0007 | Nick HarrowCladding Installer | Mon 3 Aug | Morningside entry, Finesse panel set-out | RS-CLD-FIN | 10 +2 | $702.00 | Approved |
| TS-20260803-0008 | Kade WhitmoreCladding Installer | Mon 3 Aug | Lindum overpass, sheeting to the eastern deck | RS-ROF-KL7 | 10 +2 | $702.00 | Approved |
| TS-20260803-0009 | Shaun FerrisEWP Operator | Mon 3 Aug | Lindum overpass, static line install (VAR-041-04) | RS-HGT-STA | 10 +2 | $767.00 | Approved |
| TS-20260803-0010 | Beau LansdownLabourer | Mon 3 Aug | Morningside, flashing to the canopy fascia | RS-CLD-FLA | 10 +2 | $546.00 | Approved |
| TS-20260803-0011 | Corey IonaCladding Installer | Mon 3 Aug | Banyo: canopy sheeting, bays 6 to 11 | RS-ROF-KL7 | 10 +2 | $702.00 | Approved |
| TS-20260804-0012 | Blake TuialaLeading Hand | Tue 4 Aug | Rail: supervision, crew of 12 | RS-PRE-SUP | 10 +2 | $832.00 | Approved |
| TS-20260804-0013 | Ryan PetrieRoof Plumber | Tue 4 Aug | Morningside, flashing to the canopy fascia | RS-CLD-FLA | 10 +2 | $754.00 | Approved |
| TS-20260804-0014 | Josh MardinRoof Plumber | Tue 4 Aug | Banyo: canopy sheeting, bays 6 to 11 | RS-ROF-KL7 | 10 +2 | $754.00 | Approved |
| TS-20260804-0015 | Dane KelsoCladding Installer | Tue 4 Aug | Buranda, sealant to laps and penetrations | RS-WPF-SEA | 7 | $378.00 | Approved |
| TS-20260804-0016 | Dane KelsoCladding Installer | Tue 4 Aug | Lindum, anchor point install and certification | RS-HGT-ANC | 3 +2 | $324.00 | Approved |
| TS-20260804-0017 | Tyrone BakerCladding Installer | Tue 4 Aug | Lindum, anchor point install and certification | RS-HGT-ANC | 10 +2 | $702.00 | Approved |
| TS-20260804-0018 | Isaac VellaRope Access Tech | Tue 4 Aug | Morningside entry, Finesse panel set-out | RS-CLD-FIN | 10 +2 | $897.00 | Approved |
| TS-20260804-0019 | Nick HarrowCladding Installer | Tue 4 Aug | Supervision and possession co-ordination | RS-PRE-SUP | 10 +2 | $702.00 | Approved |
| TS-20260804-0020 | Kade WhitmoreCladding Installer | Tue 4 Aug | Lindum overpass, static line install (VAR-041-04) | RS-HGT-STA | 10 +2 | $702.00 | Approved |
| TS-20260804-0021 | Shaun FerrisEWP Operator | Tue 4 Aug | Morningside, flashing to the canopy fascia | RS-CLD-FLA | 10 +2 | $767.00 | Approved |
| TS-20260804-0022 | Beau LansdownLabourer | Tue 4 Aug | Banyo: canopy sheeting, bays 6 to 11 | RS-ROF-KL7 | 10 +2 | $546.00 | Approved |
| TS-20260804-0023 | Corey IonaCladding Installer | Tue 4 Aug | Buranda, sealant to laps and penetrations | RS-WPF-SEA | 10 +2 | $702.00 | Approved |
| TS-20260805-0024 | Blake TuialaLeading Hand | Wed 5 Aug | Rail: supervision, crew of 12 | RS-PRE-SUP | 10 | $640.00 | Approved |
| TS-20260805-0025 | Ryan PetrieRoof Plumber | Wed 5 Aug | Banyo: canopy sheeting, bays 6 to 11 | RS-ROF-KL7 | 10 | $580.00 | Approved |
| TS-20260805-0026 | Josh MardinRoof Plumber | Wed 5 Aug | Buranda, sealant to laps and penetrations | RS-WPF-SEA | 10 | $580.00 | Approved |
| TS-20260805-0027 | Dane KelsoCladding Installer | Wed 5 Aug | Lindum, anchor point install and certification | RS-HGT-ANC | 10 | $540.00 | Approved |
| TS-20260805-0028 | Tyrone BakerCladding Installer | Wed 5 Aug | Morningside entry, Finesse panel set-out | RS-CLD-FIN | 10 | $540.00 | Approved |
| TS-20260805-0029 | Isaac VellaRope Access Tech | Wed 5 Aug | Supervision and possession co-ordination | RS-PRE-SUP | 10 | $690.00 | Approved |
| TS-20260805-0030 | Nick HarrowCladding Installer | Wed 5 Aug | Lindum overpass, sheeting to the eastern deck | RS-ROF-KL7 | 10 | $540.00 | Approved |
| TS-20260805-0031 | Kade WhitmoreCladding Installer | Wed 5 Aug | Morningside, flashing to the canopy fascia | RS-CLD-FLA | 10 | $540.00 | Approved |
| TS-20260805-0032 | Shaun FerrisEWP Operator | Wed 5 Aug | Banyo: canopy sheeting, bays 6 to 11 | RS-ROF-KL7 | 10 | $590.00 | Approved |
| TS-20260805-0033 | Beau LansdownLabourer | Wed 5 Aug | Buranda, sealant to laps and penetrations | RS-WPF-SEA | 10 | $420.00 | Approved |
| TS-20260805-0034 | Corey IonaCladding Installer | Wed 5 Aug | Lindum, anchor point install and certification | RS-HGT-ANC | 10 | $540.00 | Approved |
| TS-20260806-0035 | Blake TuialaLeading Hand | Thu 6 Aug | Rail: supervision, crew of 12 | RS-PRE-SUP | 10 +2 | $832.00 | Approved |
| TS-20260806-0036 | Ryan PetrieRoof Plumber | Thu 6 Aug | Buranda, sealant to laps and penetrations | RS-WPF-SEA | 10 +2 | $754.00 | Approved |
| TS-20260806-0037 | Josh MardinRoof Plumber | Thu 6 Aug | Lindum, anchor point install and certification | RS-HGT-ANC | 10 +2 | $754.00 | Approved |
| TS-20260806-0038 | Dane KelsoCladding Installer | Thu 6 Aug | Morningside entry, Finesse panel set-out | RS-CLD-FIN | 10 +2 | $702.00 | Approved |
| TS-20260806-0039 | Tyrone BakerCladding Installer | Thu 6 Aug | Supervision and possession co-ordination | RS-PRE-SUP | 10 +2 | $702.00 | Approved |
| TS-20260806-0040 | Isaac VellaRope Access Tech | Thu 6 Aug | Lindum overpass, sheeting to the eastern deck | RS-ROF-KL7 | 10 +2 | $897.00 | Approved |
| TS-20260806-0041 | Nick HarrowCladding Installer | Thu 6 Aug | Lindum overpass, static line install (VAR-041-04) | RS-HGT-STA | 10 +2 | $702.00 | Approved |
| TS-20260806-0042 | Kade WhitmoreCladding Installer | Thu 6 Aug | Banyo: canopy sheeting, bays 6 to 11 | RS-ROF-KL7 | 10 +2 | $702.00 | Approved |
| TS-20260806-0043 | Shaun FerrisEWP Operator | Thu 6 Aug | Buranda, sealant to laps and penetrations | RS-WPF-SEA | 10 +2 | $767.00 | Approved |
| TS-20260806-0044 | Beau LansdownLabourer | Thu 6 Aug | Lindum, anchor point install and certification | RS-HGT-ANC | 10 +2 | $546.00 | Approved |
| TS-20260806-0045 | Corey IonaCladding Installer | Thu 6 Aug | Morningside entry, Finesse panel set-out | RS-CLD-FIN | 10 +2 | $702.00 | Approved |
| TS-20260807-0046 | Blake TuialaLeading Hand | Fri 7 Aug | Rail: supervision, crew of 12 | RS-PRE-SUP | 8 | $512.00 | Approved |
| TS-20260807-0047 | Ryan PetrieRoof Plumber | Fri 7 Aug | Lindum, anchor point install and certification | RS-HGT-ANC | 8 | $464.00 | Approved |
| TS-20260807-0048 | Josh MardinRoof Plumber | Fri 7 Aug | Morningside entry, Finesse panel set-out | RS-CLD-FIN | 8 | $464.00 | Approved |
| TS-20260807-0049 | Dane KelsoCladding Installer | Fri 7 Aug | Supervision and possession co-ordination | RS-PRE-SUP | 5 | $270.00 | Approved |
| TS-20260807-0050 | Dane KelsoCladding Installer | Fri 7 Aug | Lindum, anchor point install and certification | RS-HGT-ANC | 3 | $162.00 | Approved |
| TS-20260807-0051 | Tyrone BakerCladding Installer | Fri 7 Aug | Lindum overpass, sheeting to the eastern deck | RS-ROF-KL7 | 8 | $432.00 | Approved |
| TS-20260807-0052 | Isaac VellaRope Access Tech | Fri 7 Aug | Lindum overpass, static line install (VAR-041-04) | RS-HGT-STA | 8 | $552.00 | Approved |
| TS-20260807-0053 | Nick HarrowCladding Installer | Fri 7 Aug | Morningside, flashing to the canopy fascia | RS-CLD-FLA | 8 | $432.00 | Approved |
| TS-20260807-0054 | Kade WhitmoreCladding Installer | Fri 7 Aug | Buranda, sealant to laps and penetrations | RS-WPF-SEA | 8 | $432.00 | Approved |
| TS-20260807-0055 | Shaun FerrisEWP Operator | Fri 7 Aug | Lindum, anchor point install and certification | RS-HGT-ANC | 8 | $472.00 | Approved |
| TS-20260807-0056 | Beau LansdownLabourer | Fri 7 Aug | Morningside entry, Finesse panel set-out | RS-CLD-FIN | 8 | $336.00 | Approved |
| TS-20260807-0057 | Corey IonaCladding Installer | Fri 7 Aug | Supervision and possession co-ordination | RS-PRE-SUP | 8 | $432.00 | Approved |
| TS-20260810-0058 | Blake TuialaLeading Hand | Mon 10 Aug | Rail: supervision, crew of 12 | RS-PRE-SUP | 10 +2 | $832.00 | Approved |
| TS-20260810-0059 | Ryan PetrieRoof Plumber | Mon 10 Aug | Lindum overpass, static line install (VAR-041-04) | RS-HGT-STA | 10 +2 | $754.00 | Approved |
| TS-20260810-0060 | Josh MardinRoof Plumber | Mon 10 Aug | Morningside, flashing to the canopy fascia | RS-CLD-FLA | 10 +2 | $754.00 | Approved |
Purchase orders
$65,904.00 committed and not yet received.
| PO | Supplier | Deliver to | Raised | Expected | Ex GST | Status |
|---|---|---|---|---|---|---|
| PO-2026-0341 | Lysaght (BlueScope) | Landsborough store (prefab | 5 Aug 2026 | 19 Aug 2026 | $39,344.00 | Sent |
| PO-2026-0340 | Safetylink | Lindum station site | 4 Aug 2026 | 15 Aug 2026 | $26,560.00 | Sent |
| PO-2026-0339 | Buckby Metals | Landsborough store (prefab) | 1 Aug 2026 | 8 Aug 2026 | $27,079.20 | Received |
| PO-2026-0338 | Coates Hire | Morningside station site | 30 Jul 2026 | 4 Aug 2026 | $7,440.00 | Invoiced |
Subcontractor claims
| Claim | Subcontractor | Trade | Period | Ex GST | Status |
|---|---|---|---|---|---|
| SCC-2026-0212 | Sunshine Coast Scaffolding | Scaffold erect & dismantle | Jul 2026 | $86,400.00 | Approved |
| SCC-2026-0211 | Apex Trades Roofing | Roof sheeting & flashings | Jul 2026 | $124,800.00 | Approved |
| SCC-2026-0210 | Highgate Access Solutions | Rope access & height safety | Jul 2026 | $30,600.00 | Query Claiming 5 days where the docket book shows 4. Held pending the site diary. |
Inspection & test plans
Hold and witness points for the handover pack.
AS 1562.1 / SA HB 39
- Hold 1.1 Purlin set-out and level survey before sheeting Signed 12 Mar 2026 · Steve Bracken
- Record 1.2 Sheet profile, BMT and colour verified against approved sample Signed 14 Mar 2026 · P-101
- Witness 1.3 Fastener type, pattern and torque (first bay Signed 19 Mar 2026 · Steve Bracken
- Surveillance 1.4 Safety mesh continuity and lap Signed 26 Mar 2026 · P-009
- Hold 1.5 Completed roof) water test to valleys and penetrations Open
AS/NZS 1891.2
- Hold 2.1 Structural adequacy of the anchor substrate confirmed by the engineer Signed 5 Aug 2026 · Steve Bracken
- Record 2.2 Anchor installation torque record, each point Signed 11 Aug 2026 · P-101
- Hold 2.3 Proof load test 15 kN, each anchor Open
- Hold 2.4 System certification and tagging by a competent person Open
- Record 2.5 As-installed drawing and certificate to the handover pack Open
AS 1562.1 / manufacturer's specification
- Hold 3.1 Shop drawing and set-out approved before cutting Signed 2 Jul 2026 · Steve Bracken
- Witness 3.2 Substrate flatness within 3 mm in 3 m Signed 16 Jul 2026 · P-101
- Hold 3.3 Panel alignment and joint width, first elevation Open
- Witness 3.4 Sealant adhesion test to the cladding junction Open
Site diary
The daily site record supporting delay and disruption claims.
Static line install continued on the Lindum deck under VAR-041-04. Anchors set to bay 14. Laing O'Rourke walked the deck at 1030 and signed the ITP hold point for anchor pull-testing. Possession confirmed for Thursday night.
Delay, Rain: sheeting stopped 1400, crew redeployed to prefab flashing under cover · 2.5 h lost
Morningside canopy fascia flashing continued to 1400. Rain stopped roof works; crew moved to the ground-level prefab bay. 2.5 hours lost across 12. Notified LOR by email at 1420.
Banyo canopy sheeting bays 6 to 11 complete. Highgate on the eastern face by rope access. Offcut sweep at every break per the actions from INC-2026-018: checked and signed at 1000, 1230 and 1500.
Drawings and documents
At their current revision. Superseded revisions stay on the register, because after an incident the question is which revision the crew were working to that day.
| Document | Kind | Rev | Owner | Updated | Size | Status |
|---|---|---|---|---|---|---|
| QJ2041 Rail possession plan, August DOC-4376 · SharePoint / QClad / Jobs / QJ2041 / 04 Programme | Report | F | Marcus Deng | 7 Aug 2026 | 1.3 MB | Current |
Correspondence
RFIs, material approvals and anything else sent about QJ2041, with the replies on the same thread.
Possession window clash, Banyo platform 2
The possession window issued for Banyo platform 2 on the night of 12 August overlaps the signalling works already programmed for the same window. Our crew cannot access the canopy while that is live. Can the possession be moved to 13 August, or should we stand the crew down and reprogramme?
Possession moved to the night of 13 August, confirmed with the signalling contractor. Revised possession notice to follow. Please confirm your crew and the flagging arrangements for the new date.
Confirmed for 13 August. Crew 1 with the same flagging arrangements as the 5 August possession.