QClad
QClad
QJ2041 Demo QRSAUP: Brisbane Rail Stations Roofing & Cladding
Accounting connected Thu 13 Aug 2026
QJ2041 On site Transport P6 QRSAUP.RC.4400

QRSAUP: Brisbane Rail Stations Roofing & Cladding

Laing O'Rourke Australia · Banyo, Buranda, Morningside & Lindum stations, QLD · contract LOR-QRSAUP-SC-0442

Marcus Deng · Crew 1, Rail · 16 Dec 2025 → 5 Dec 2026

Claim PC-2026-0187 Client view

Four stations, four accessible overpasses, platform canopies and station buildings. Large portions installable only inside rail possessions, night shutdowns priced separately. Limited laydown; most flashing prefabricated at Landsborough.

The position

Every figure below is the sum of rows on this page.

Contract sum

$4,093,279

Tendered
$3,919,150
Approved variations
+$174,129
Lodged, not approved
$72,567

Work in place

$2,499,553

Complete
61.1%
Still to run
$1,593,726

Claimed & certified

$2,387,073

Certified
$2,384,573
Unclaimed WIP
$112,480
Retention held
$119,229

Margin

$456,408 18.3%

Cost of work in place
$2,043,145
Against the build-up
+$41,800
Committed, not received
$65,904

$49,438.50 of work is on the ground against variations nobody has approved.

VAR-041-04, Lindum overpass: additional static line and anchor points. Until they are approved they sit in cost with no revenue against them.

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 8 tasks · General $1,215,310 $783,852 64% 7,614.8 4,960.2 $0 $6,332 - +$23,409 18%
CC-02 Roofing 12 tasks · General $1,459,321 $922,423 63% 4,542.3 2,960.4 $326,379 $331,532 $31,872 +$9,458 18%
CC-03 Wall cladding 6 tasks · General $838,500 $440,161 52% 2,461.7 1,318 $175,869 $179,192 $27,079 +$5,710 17%
CC-05 Height access & safety systems 3 tasks · General $395,000 $255,804 65% 1,695.2 1,086.8 $51,706 $52,632 $26,560 +$1,963 18%
CC-06 Weatherproofing 4 tasks · General $185,148 $97,313 53% 923.8 508.2 $7,520 $7,768 - +$1,259 24%
Job total $4,093,279 $2,499,553 61% 17,237.8 10,833.6 $561,474 $577,457 $85,511 +$41,800 18%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $2,043,145, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$783,852 of $1,215,310 · 64%
TaskSub-jobContractDone%ValueEarnedHours
Rail shutdown premium, night possession RS-PRE-SHT General 46 day 27.14 59% $545,560 $321,880 2,388.3 of 4,048
Site supervision, leading hand RS-PRE-SUP General 232 day 143.84 62% $289,536 $179,512 1,510.3 of 2,436
Scaffold: supply, erect, hire 8 weeks, dismantle RS-PRE-SCF General 2,180 m² 1,547.8 71% $217,564 $154,470 92.9 of 130.8
Mobilisation & site establishment RS-PRE-MOB General 4 item 4 100% $73,800 $73,800 384 of 384
Rail shutdown premium, night possession RS-PRE-SHT · VAR-041-02 General 3 day 2.58 86% $35,580 $30,599 227 of 264
Demobilisation & make good RS-PRE-DEM General 4 item 0 0% $29,680 $0 0 of 176
Site induction & verification of competency RS-PRE-IND General 22 ea 22 100% $12,870 $12,870 88 of 88
SWMS, JSA & site-specific safety plan RS-PRE-SWM General 4 item 4 100% $10,720 $10,720 88 of 88
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$922,423 of $1,459,321 · 63%
TaskSub-jobContractDone%ValueEarnedHours
KLIP-LOK 700 HI-STRENGTH roof sheeting, install RS-ROF-KL7 General 4,820 m² 3,084.8 64% $638,168 $408,428 1,110.5 of 1,735.2
Roof insulation blanket 75mm R1.8, install RS-ROF-INS General 4,820 m² 3,084.8 64% $190,872 $122,158 431.9 of 674.8
Box gutter, supply and install RS-ROF-GUT General 388 lm 201.76 52% $149,380 $77,678 213.9 of 411.3
Safety mesh, install to purlins RS-ROF-SAF General 4,820 m² 3,181.2 66% $119,536 $78,894 302.2 of 457.9
Ridge capping & barge, supply and install RS-ROF-RDG General 612 lm 354.96 58% $89,352 $51,824 142 of 244.8
Strip existing roof sheeting & dispose RS-ROF-STR General 1,640 m² 1,279.2 78% $85,936 $67,030 371 of 475.6
Fibreglass roof lighting, install RS-ROF-SKY General 320 m² 131.2 41% $63,360 $25,978 69.5 of 169.6
KLIP-LOK 700 HI-STRENGTH roof sheeting, install RS-ROF-KL7 · VAR-041-01 General 386 m² 331.96 86% $51,106 $43,952 119.5 of 139
Downpipe & rainhead, supply and install RS-ROF-DWP General 46 ea 22.08 48% $39,744 $19,077 59.6 of 124.2
Roof insulation blanket 75mm R1.8, install RS-ROF-INS · VAR-041-01 General 386 m² 331.96 86% $15,286 $13,146 46.5 of 54
Safety mesh, install to purlins RS-ROF-SAF · VAR-041-01 General 386 m² 331.96 86% $9,573 $8,233 31.5 of 36.7
Ridge capping & barge, supply and install RS-ROF-RDG · VAR-041-01 General 48 lm 41.28 86% $7,008 $6,027 16.5 of 19.2
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$440,161 of $838,500 · 52%
TaskSub-jobContractDone%ValueEarnedHours
CUSTOM ORB wall cladding, install RS-CLD-CUS General 2,940 m² 1,675.8 57% $301,056 $171,602 502.7 of 882
Custom flashings, supply and install RS-CLD-FLA General 1,860 lm 1,023 55% $212,040 $116,622 347.8 of 632.4
Fielders Finesse architectural cladding, install RS-CLD-FIN General 680 m² 231.2 34% $153,680 $52,251 152.6 of 448.8
Corner & parapet capping, supply and install RS-CLD-CAP General 940 lm 460.6 49% $129,720 $63,563 184.2 of 376
Fielders Finesse architectural cladding, install RS-CLD-FIN · VAR-041-03 General 148 m² 127.28 86% $33,448 $28,765 84 of 97.7
Corner & parapet capping, supply and install RS-CLD-CAP · VAR-041-03 General 62 lm 53.32 86% $8,556 $7,358 21.3 of 24.8
CC-05 Height access & safety systems Anchor points, static lines, guardrail, rope access and elevated work platforms.
$255,804 of $395,000 · 65%
TaskSub-jobContractDone%ValueEarnedHours
EWP hire & operator, 45ft boom RS-HGT-EWP General 118 day 71.98 61% $210,040 $128,124 719.8 of 1,180
Static line system: supply, install & certify RS-HGT-STA General 480 lm 326.4 68% $137,280 $93,350 254.6 of 374.4
Roof anchor point: supply, install & certify RS-HGT-ANC General 64 ea 46.08 72% $47,680 $34,330 101.4 of 140.8
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$97,313 of $185,148 · 53%
TaskSub-jobContractDone%ValueEarnedHours
Sealant to laps, penetrations & flashings RS-WPF-SEA General 3,240 lm 1,717.2 53% $112,752 $59,759 343.4 of 648
Roof penetration flashing, form & seal RS-WPF-PEN General 86 ea 37.84 44% $58,824 $25,883 87 of 197.8
Sealant to laps, penetrations & flashings RS-WPF-SEA · VAR-041-01 General 210 lm 180.6 86% $7,308 $6,285 36.1 of 42
Sealant to laps, penetrations & flashings RS-WPF-SEA · VAR-041-03 General 180 lm 154.8 86% $6,264 $5,387 31 of 36

Drawings and documents

At their current revision. Superseded revisions stay on the register, because after an incident the question is which revision the crew were working to that day.

All documents
DocumentKindRevOwnerUpdatedSizeStatus
QJ2041 Rail possession plan, August DOC-4376 · SharePoint / QClad / Jobs / QJ2041 / 04 Programme Report F Marcus Deng 7 Aug 2026 1.3 MB Current

Correspondence

RFIs, material approvals and anything else sent about QJ2041, with the replies on the same thread.

RFI-016 RFI Answered Denise Kerrigan, Lor Projects 3 messages

Possession window clash, Banyo platform 2

Jared Ruska QClad 2026-08-06 13:05

The possession window issued for Banyo platform 2 on the night of 12 August overlaps the signalling works already programmed for the same window. Our crew cannot access the canopy while that is live. Can the possession be moved to 13 August, or should we stand the crew down and reprogramme?

Denise Kerrigan replied 2026-08-08 10:18

Possession moved to the night of 13 August, confirmed with the signalling contractor. Revised possession notice to follow. Please confirm your crew and the flagging arrangements for the new date.

Jared Ruska QClad 2026-08-08 11:02

Confirmed for 13 August. Crew 1 with the same flagging arrangements as the 5 August possession.