VAR-006-04 Demo Shed 2 south penetrations for the mechanical package
Accounting connected Thu 13 Aug 2026
VAR-006-04 Draft QJ2006

Variation 4, Shed 2 south penetrations for the mechanical package

PROJECT CERES - UREA SHEDS · Saipem Clough Joint Venture

Raised 7 Aug 2026 by Marcus Deng

Effect of approval

These lines join QJ2006's schedule of rates. With no work yet started, the value of work in place moves with the contract sum, the open progress claim measures the difference, the job's margin recalculates, and an acknowledgement is issued to the head contractor.

Contract sum

$7,497,478 → $7,530,478

Work in place

$3,367,317 → $3,367,317

PC-2026-0196 (Aug 2026)

$343,466 → $343,466

Margin on QJ2006

17.8% → 17.8%

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-WPF-PEN Roof penetration flashing, form & seal $684.00/ea 34 $23,256.00 $13,985.22 40%
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 280 $9,744.00 $7,736.40 21%
Total, ex GST $33,000.00 $21,721.62 34%
GST $3,300.00
Total, inc GST $36,300.00

Why it was raised

Mechanical contractor issued 34 penetrations after the sheeting was set out. Each one has to be formed, flashed and sealed.

Position

Value, ex GST
$33,000.00
Cost to deliver
$21,721.62
Margin
34.2%
Physically built
0%
Value already on the ground
$0.00
Work commenced
No

Contract

Contract no.
SCJV-CER-SC-1180
Head contractor
Saipem Clough Joint Venture
Approver
Dean Marchetti
Payment terms
45 days EOM
Open claim
PC-2026-0196

Trail

  1. Raised 7 Aug 2026 by Marcus DengPriced off the job's schedule of rates