Variation 2, Canopy gutter replacement
Coomera Station Re-roof · Queensland Rail · their reference QR-VO-0872
Raised 11 Mar 2025 by Marcus Deng · approved 24 Mar 2025 by Melissa Trang
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-ROF-GUT Box gutter, supply and install | $385.00/lm | 46 | $17,710.00 | $15,089.38 | 15% |
| Total, ex GST | $17,710.00 | $15,089.38 | 15% | ||
| GST | $1,771.00 | ||||
| Total, inc GST | $19,481.00 | ||||
Why it was raised
Existing gutter found unserviceable on strip.
Position
- Value, ex GST
- $17,710.00
- Cost to deliver
- $15,089.38
- Margin
- 14.8%
- Physically built
- 100%
- Value already on the ground
- $17,710.00
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2025-028
- Contract no.
- QR-COO-RR-2024-7712
- Head contractor
- Queensland Rail
- Approver
- Melissa Trang
- Payment terms
- 30 days
Trail
- Raised 11 Mar 2025 by Marcus DengPriced off the project schedule of rates
- Lodged with Queensland RailTheir reference QR-VO-0872
- Approved 24 Mar 2025Melissa Trang · added to the contract sum and the open claim