QJ2049 Demo Bengalla VDC Re-roof Stage 2
Accounting connected Thu 13 Aug 2026
QJ2049 Awarded Mining & Resources P6 BGA.VDC.S2.1100

Bengalla VDC Re-roof Stage 2

Bengalla Mining Company · Bengalla Mine, Muswellbrook, NSW · contract BGA-VDC-S2-40118

Marcus Deng · 1 Sep 2026 → 6 Feb 2027

Claim PC-2026-0194 Client view

Stage 2 follows the 2023 VDC re-roof. Live conveyor beneath the whole footprint: permit to work every shift, no exceptions. NSW crews via Hunter Valley Cladding.

The position

Every figure below is the sum of rows on this page.

Contract sum

$1,775,394

Tendered
$1,765,226
Approved variations
+$10,168

Work in place

$22,515

Complete
1.3%
Still to run
$1,752,879

Claimed & certified

$0

Certified
$0
Unclaimed WIP
$22,515
Retention held
$0

Margin

$3,860 17.1%

Cost of work in place
$18,655
Against the build-up
$0
Committed, not received
$64,104

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 7 tasks · General $179,040 $22,515 13% 1,411 160.4 $0 $0 - $0 17%
CC-02 Roofing 6 tasks · General $983,248 $0 0% 3,418 0 $0 $0 - $0 0%
CC-03 Wall cladding 1 task · General $172,212 $0 0% 497.2 0 $0 $0 - $0 0%
CC-05 Height access & safety systems 2 tasks · General $154,390 $0 0% 428.8 0 $0 $0 $64,104 $0 0%
CC-06 Weatherproofing 1 task · General $86,304 $0 0% 496 0 $0 $0 - $0 0%
CC-08 Direct labour & plant 1 task · General $200,200 $0 0% 0 0 $0 $0 - $0 0%
Job total $1,775,394 $22,515 1% 6,251 160.4 $0 $0 $64,104 $0 17%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $18,655, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$22,515 of $179,040 · 13%
TaskSub-jobContractDone%ValueEarnedHours
Site supervision, leading hand RS-PRE-SUP General 104 day 0 0% $129,792 $0 0 of 1,092
Mobilisation & site establishment RS-PRE-MOB General 1 item 0.35 35% $18,450 $6,458 33.6 of 96
Site induction & verification of competency RS-PRE-IND General 18 ea 7.92 44% $10,530 $4,633 31.7 of 72
Site supervision, leading hand RS-PRE-SUP · VAR-049-01 General 6 day 5.16 86% $7,488 $6,440 54.2 of 63
Demobilisation & make good RS-PRE-DEM General 1 item 0 0% $7,420 $0 0 of 44
SWMS, JSA & site-specific safety plan RS-PRE-SWM General 1 item 1 100% $2,680 $2,680 22 of 22
SWMS, JSA & site-specific safety plan RS-PRE-SWM · VAR-049-01 General 1 item 0.86 86% $2,680 $2,305 18.9 of 22
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$0 of $983,248 · 0%
TaskSub-jobContractDone%ValueEarnedHours
Stramit Speed Deck Ultra, install RS-ROF-SPD General 3,420 m² 0 0% $416,556 $0 0 of 1,162.8
Strip existing roof sheeting & dispose RS-ROF-STR General 3,420 m² 0 0% $179,208 $0 0 of 991.8
Roof insulation blanket 75mm R1.8, install RS-ROF-INS General 3,420 m² 0 0% $135,432 $0 0 of 478.8
Box gutter, supply and install RS-ROF-GUT General 288 lm 0 0% $110,880 $0 0 of 305.3
Safety mesh, install to purlins RS-ROF-SAF General 3,420 m² 0 0% $84,816 $0 0 of 324.9
Ridge capping & barge, supply and install RS-ROF-RDG General 386 lm 0 0% $56,356 $0 0 of 154.4
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$0 of $172,212 · 0%
TaskSub-jobContractDone%ValueEarnedHours
Purlin & girt, supply and install RS-CLD-PUR General 22.6 t 0 0% $172,212 $0 0 of 497.2
CC-05 Height access & safety systems Anchor points, static lines, guardrail, rope access and elevated work platforms.
$0 of $154,390 · 0%
TaskSub-jobContractDone%ValueEarnedHours
Static line system: supply, install & certify RS-HGT-STA General 420 lm 0 0% $120,120 $0 0 of 327.6
Roof anchor point: supply, install & certify RS-HGT-ANC General 46 ea 0 0% $34,270 $0 0 of 101.2
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$0 of $86,304 · 0%
TaskSub-jobContractDone%ValueEarnedHours
Sealant to laps, penetrations & flashings RS-WPF-SEA General 2,480 lm 0 0% $86,304 $0 0 of 496
CC-08 Direct labour & plant Dayworks, overtime and travel time charged at the labour rate.
$0 of $200,200 · 0%
TaskSub-jobContractDone%ValueEarnedHours
Travel & living away: per person, per day RS-LAB-TRV General 520 day 0 0% $200,200 $0 0 of 0

Correspondence

RFIs, material approvals and anything else sent about QJ2049, with the replies on the same thread.

Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.