Variation 5, Rejected (additional travel for the June roster change
BMA Saraji Workshop Upgrade: Cladding · BHP Mitsubishi Alliance · their reference BMA-VO-2284
Raised 2 Jul 2026 by Cameron Doyle
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-LAB-TRV Travel & living away: per person, per day | $385.00/day | 48 | $18,480.00 | $15,264.00 | 17% |
| Total, ex GST | $18,480.00 | $15,264.00 | 17% | ||
| GST | $1,848.00 | ||||
| Total, inc GST | $20,328.00 | ||||
Why it was raised
Roster changed from 2:1 to 3:1 for two swings, adding travel and LAFHA.
Rejected: BMA hold that the roster is a QClad resourcing decision. $18.4k written off) it is in the cost run on this job.
Position
- Value, ex GST
- $18,480.00
- Cost to deliver
- $15,264.00
- Margin
- 17.4%
- Physically built
- 60%
- Value already on the ground
- $11,088.00
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2026-044
- Contract no.
- BMA-SAR-2026-1187
- Head contractor
- BHP Mitsubishi Alliance
- Approver
- Warren Idle
- Payment terms
- 45 days EOM
Trail
- Raised 2 Jul 2026 by Cameron DoylePriced off the project schedule of rates
- Lodged with BHP Mitsubishi AllianceTheir reference BMA-VO-2284
- Rejected$18,480.00 written off into the cost run on PRJ-2026-044