BMA Saraji Workshop Upgrade: Cladding · BHP Mitsubishi Alliance · their reference BMA-VO-2284
Raised 10 Jul 2026 by Cameron Hale
Priced off the pricing schedule the contract is measured against.
Roster changed from 2:1 to 3:1 for two swings, adding travel and LAFHA.
Rejected: BMA hold that the roster is a QClad resourcing decision. $18.4k written off) it is in the cost run on this job.