Site
Timesheets
Day cards filed from the crew app, booked against the project on receipt and approved by the project manager. Approved cards feed the weekly payroll extract.
Hours this pay period
4,468
501 h overtime
416 day cards, fortnightly cycle
Labour cost
$264k
fully loaded, booked to project
Charged to contracts
$502k
47% recovery
Awaiting approval
90
1 queried
Off the crew app
96%
398 of 416 cards, 58 people on the system
Hours by job, week beginning 10 Aug 2026
Cost is fully loaded: wage plus superannuation, workers' compensation, leave and allowances. Overtime at time and a half.
| Job | Mon | Tue | Wed | Thu• | Fri | Hours | Cost |
|---|---|---|---|---|---|---|---|
| QJ2006 PROJECT CERES - UREA SHEDS | 128 | 128 | 128 | 133.25 | - | 1,157.25 | $70,185 |
| QJ2041 QRSAUP: Brisbane Rail Stations Roofing & Cladding | 132 | 132 | 110 | 132 | - | 1,100 | $65,720 |
| QJ2044 BMA Saraji Workshop Upgrade: Cladding | 118 | 118 | 118 | 98 | - | 1,011 | $59,929 |
| QJ2045 M&A Apartments Stage 3: Facade Cladding | 36 | 30 | 36 | 20 | - | 268 | $16,368 |
| QJ2039 Groote Island: Mobile Plant Workshop Re-roof | 108 | 90 | 96 | 90 | - | 876 | $47,916 |
| QJ2046 Downer Rail Maryborough: Periodic Roofing Works 2026 | - | - | 12 | 10 | - | 56 | $4,071 |
| Total | 522 | 498 | 500 | 483.25 | 0 | 4,468 | $264,189 |
Crew 1, Rail
11/12- BT Blake Tuiala Leading Hand
- RP Ryan Petrie Roof Plumber
- JM Josh Mardin Roof Plumber
- DK Dane Kelso Cladding Installer
- TB Tyrone Baker Cladding Installer
- IV Isaac Vella Rope Access Tech
- NH Nick Harrow Cladding Installer
- KW Kade Whitmore Cladding Installer
- SF Shaun Ferris EWP Operator
- BL Beau Lansdown Labourer
- CI Corey Iona Cladding Installer
- LO Liam O'Shea Annual leave, back 18 Aug 2026
Crew 2, Bowen Basin
9/11- MR Mitch Ravenscroft Leading Hand
- TO Trent Osborne Roof Plumber
- DY Damien Yorke Cladding Installer
- BC Brody Chan Cladding Installer
- AP Angus Petersen Rope Access Tech
- JM Jesse Mallard Cladding Installer
- AR Ashton Reilly Apprentice, 2nd yr
- NP Nathan Prowse Labourer
- RC Rhys Callaghan Cladding Installer
- WT Wade Tolhurst Off swing, 2:1 roster
- KD Kirk Danaher EWP ticket expires 4 Sep 2026, off plant until it is renewed
Crew 3, FIFO West
10/11- ZM Zeb Marchetti Leading Hand
- CB Callum Byrne Roof Plumber
- DW Deacon Whitely Acoustic Installer
- HN Hamish Ngata Acoustic Installer
- LS Levi Sandford Cladding Installer
- BH Brett Hallam Rope Access Tech
- FD Fletcher Doig Cladding Installer
- SF Sione Fatu Labourer
- KA Kyle Anderton Apprentice, 1st yr
- BR Bailey Rutherford Cladding Installer
- OK Owen Krasnov Personal leave
Crew 4, FIFO North
12/12- DF Dom Falzon Leading Hand
- JW Jarrah Winton Roof Plumber
- EB Ellis Braithwaite Cladding Installer
- TG Tom Gillard Cladding Installer
- RS Reece Salvatore Sheeting Hand
- MD Marlon Deverell EWP Operator
- XP Xavier Pauling Cladding Installer
- HC Heath Corrigan Labourer
- JS Jai Sutherland Apprentice, 3rd yr
- LF Lachlan Ferreira Cladding Installer
- RC Riley Cusack Roof Plumber
- NB Ned Blackwood Rope Access Tech
416 shown
| Day card | Person | Date | Job | Task | Cost centre | Rate | Hours | Cost | Source | Status | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| TS-20260813-9005 | Zeb Marchetti Leading Hand | Thu 13 Aug | QJ2006 | FIFO West: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 5.25 | $336.00 | Crew app | Submitted | |
| TS-20260803-0001 | Blake Tuiala Leading Hand | Mon 3 Aug | QJ2041 | Rail: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260803-0002 | Ryan Petrie Roof Plumber | Mon 3 Aug | QJ2041 | Lindum overpass, static line install (VAR-041-04) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260803-0003 | Josh Mardin Roof Plumber | Mon 3 Aug | QJ2041 | Morningside, flashing to the canopy fascia | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260803-0004 | Dane Kelso Cladding Installer | Mon 3 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260803-0005 | Tyrone Baker Cladding Installer | Mon 3 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260803-0006 | Isaac Vella Rope Access Tech | Mon 3 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260803-0007 | Nick Harrow Cladding Installer | Mon 3 Aug | QJ2041 | Morningside entry, Finesse panel set-out | CC-03 Wall cladding | RS-CLD-FIN | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260803-0008 | Kade Whitmore Cladding Installer | Mon 3 Aug | QJ2041 | Lindum overpass, sheeting to the eastern deck | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260803-0009 | Shaun Ferris EWP Operator | Mon 3 Aug | QJ2041 | Lindum overpass, static line install (VAR-041-04) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $767.00 | Crew app | Approved | |
| TS-20260803-0010 | Beau Lansdown Labourer | Mon 3 Aug | QJ2041 | Morningside, flashing to the canopy fascia | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260803-0011 | Corey Iona Cladding Installer | Mon 3 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260804-0012 | Blake Tuiala Leading Hand | Tue 4 Aug | QJ2041 | Rail: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260804-0013 | Ryan Petrie Roof Plumber | Tue 4 Aug | QJ2041 | Morningside, flashing to the canopy fascia | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260804-0014 | Josh Mardin Roof Plumber | Tue 4 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260804-0015 | Dane Kelso Cladding Installer | Tue 4 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 7 | $378.00 | Crew app | Approved | |
| TS-20260804-0016 | Dane Kelso Cladding Installer | Tue 4 Aug | QJ2041 | Lindum, anchor point install and certification Changed cost centre part way through the shift. | CC-05 Height access & safety systems | RS-HGT-ANC | 3 +2 | $324.00 | Crew app | Approved | |
| TS-20260804-0017 | Tyrone Baker Cladding Installer | Tue 4 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260804-0018 | Isaac Vella Rope Access Tech | Tue 4 Aug | QJ2041 | Morningside entry, Finesse panel set-out | CC-03 Wall cladding | RS-CLD-FIN | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260804-0019 | Nick Harrow Cladding Installer | Tue 4 Aug | QJ2041 | Supervision and possession co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260804-0020 | Kade Whitmore Cladding Installer | Tue 4 Aug | QJ2041 | Lindum overpass, static line install (VAR-041-04) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260804-0021 | Shaun Ferris EWP Operator | Tue 4 Aug | QJ2041 | Morningside, flashing to the canopy fascia | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $767.00 | Crew app | Approved | |
| TS-20260804-0022 | Beau Lansdown Labourer | Tue 4 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260804-0023 | Corey Iona Cladding Installer | Tue 4 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260805-0024 | Blake Tuiala Leading Hand | Wed 5 Aug | QJ2041 | Rail: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $640.00 | Crew app | Approved | |
| TS-20260805-0025 | Ryan Petrie Roof Plumber | Wed 5 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 | $580.00 | Crew app | Approved | |
| TS-20260805-0026 | Josh Mardin Roof Plumber | Wed 5 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 10 | $580.00 | Crew app | Approved | |
| TS-20260805-0027 | Dane Kelso Cladding Installer | Wed 5 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 10 | $540.00 | Crew app | Approved | |
| TS-20260805-0028 | Tyrone Baker Cladding Installer | Wed 5 Aug | QJ2041 | Morningside entry, Finesse panel set-out | CC-03 Wall cladding | RS-CLD-FIN | 10 | $540.00 | Crew app | Approved | |
| TS-20260805-0029 | Isaac Vella Rope Access Tech | Wed 5 Aug | QJ2041 | Supervision and possession co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $690.00 | Crew app | Approved | |
| TS-20260805-0030 | Nick Harrow Cladding Installer | Wed 5 Aug | QJ2041 | Lindum overpass, sheeting to the eastern deck | CC-02 Roofing | RS-ROF-KL7 | 10 | $540.00 | Crew app | Approved | |
| TS-20260805-0031 | Kade Whitmore Cladding Installer | Wed 5 Aug | QJ2041 | Morningside, flashing to the canopy fascia | CC-03 Wall cladding | RS-CLD-FLA | 10 | $540.00 | Crew app | Approved | |
| TS-20260805-0032 | Shaun Ferris EWP Operator | Wed 5 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 | $590.00 | Crew app | Approved | |
| TS-20260805-0033 | Beau Lansdown Labourer | Wed 5 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 10 | $420.00 | Crew app | Approved | |
| TS-20260805-0034 | Corey Iona Cladding Installer | Wed 5 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 10 | $540.00 | Crew app | Approved | |
| TS-20260806-0035 | Blake Tuiala Leading Hand | Thu 6 Aug | QJ2041 | Rail: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260806-0036 | Ryan Petrie Roof Plumber | Thu 6 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260806-0037 | Josh Mardin Roof Plumber | Thu 6 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260806-0038 | Dane Kelso Cladding Installer | Thu 6 Aug | QJ2041 | Morningside entry, Finesse panel set-out | CC-03 Wall cladding | RS-CLD-FIN | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260806-0039 | Tyrone Baker Cladding Installer | Thu 6 Aug | QJ2041 | Supervision and possession co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260806-0040 | Isaac Vella Rope Access Tech | Thu 6 Aug | QJ2041 | Lindum overpass, sheeting to the eastern deck | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260806-0041 | Nick Harrow Cladding Installer | Thu 6 Aug | QJ2041 | Lindum overpass, static line install (VAR-041-04) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260806-0042 | Kade Whitmore Cladding Installer | Thu 6 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260806-0043 | Shaun Ferris EWP Operator | Thu 6 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $767.00 | Crew app | Approved | |
| TS-20260806-0044 | Beau Lansdown Labourer | Thu 6 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260806-0045 | Corey Iona Cladding Installer | Thu 6 Aug | QJ2041 | Morningside entry, Finesse panel set-out | CC-03 Wall cladding | RS-CLD-FIN | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260807-0046 | Blake Tuiala Leading Hand | Fri 7 Aug | QJ2041 | Rail: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $512.00 | Crew app | Approved | |
| TS-20260807-0047 | Ryan Petrie Roof Plumber | Fri 7 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 8 | $464.00 | Crew app | Approved | |
| TS-20260807-0048 | Josh Mardin Roof Plumber | Fri 7 Aug | QJ2041 | Morningside entry, Finesse panel set-out | CC-03 Wall cladding | RS-CLD-FIN | 8 | $464.00 | Crew app | Approved | |
| TS-20260807-0049 | Dane Kelso Cladding Installer | Fri 7 Aug | QJ2041 | Supervision and possession co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 5 | $270.00 | Crew app | Approved | |
| TS-20260807-0050 | Dane Kelso Cladding Installer | Fri 7 Aug | QJ2041 | Lindum, anchor point install and certification Changed cost centre part way through the shift. | CC-05 Height access & safety systems | RS-HGT-ANC | 3 | $162.00 | Crew app | Approved | |
| TS-20260807-0051 | Tyrone Baker Cladding Installer | Fri 7 Aug | QJ2041 | Lindum overpass, sheeting to the eastern deck | CC-02 Roofing | RS-ROF-KL7 | 8 | $432.00 | Crew app | Approved | |
| TS-20260807-0052 | Isaac Vella Rope Access Tech | Fri 7 Aug | QJ2041 | Lindum overpass, static line install (VAR-041-04) | CC-05 Height access & safety systems | RS-HGT-STA | 8 | $552.00 | Crew app | Approved | |
| TS-20260807-0053 | Nick Harrow Cladding Installer | Fri 7 Aug | QJ2041 | Morningside, flashing to the canopy fascia | CC-03 Wall cladding | RS-CLD-FLA | 8 | $432.00 | Crew app | Approved | |
| TS-20260807-0054 | Kade Whitmore Cladding Installer | Fri 7 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 8 | $432.00 | Crew app | Approved | |
| TS-20260807-0055 | Shaun Ferris EWP Operator | Fri 7 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 8 | $472.00 | Crew app | Approved | |
| TS-20260807-0056 | Beau Lansdown Labourer | Fri 7 Aug | QJ2041 | Morningside entry, Finesse panel set-out | CC-03 Wall cladding | RS-CLD-FIN | 8 | $336.00 | Crew app | Approved | |
| TS-20260807-0057 | Corey Iona Cladding Installer | Fri 7 Aug | QJ2041 | Supervision and possession co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $432.00 | Crew app | Approved | |
| TS-20260810-0058 | Blake Tuiala Leading Hand | Mon 10 Aug | QJ2041 | Rail: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260810-0059 | Ryan Petrie Roof Plumber | Mon 10 Aug | QJ2041 | Lindum overpass, static line install (VAR-041-04) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260810-0060 | Josh Mardin Roof Plumber | Mon 10 Aug | QJ2041 | Morningside, flashing to the canopy fascia | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260810-0061 | Dane Kelso Cladding Installer | Mon 10 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260810-0062 | Tyrone Baker Cladding Installer | Mon 10 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260810-0063 | Isaac Vella Rope Access Tech | Mon 10 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260810-0064 | Nick Harrow Cladding Installer | Mon 10 Aug | QJ2041 | Morningside entry, Finesse panel set-out | CC-03 Wall cladding | RS-CLD-FIN | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260810-0065 | Kade Whitmore Cladding Installer | Mon 10 Aug | QJ2041 | Lindum overpass, sheeting to the eastern deck | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260810-0066 | Shaun Ferris EWP Operator | Mon 10 Aug | QJ2041 | Lindum overpass, static line install (VAR-041-04) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $767.00 | Crew app | Approved | |
| TS-20260810-0067 | Beau Lansdown Labourer | Mon 10 Aug | QJ2041 | Morningside, flashing to the canopy fascia | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260810-0068 | Corey Iona Cladding Installer | Mon 10 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260811-0069 | Blake Tuiala Leading Hand | Tue 11 Aug | QJ2041 | Rail: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260811-0070 | Ryan Petrie Roof Plumber | Tue 11 Aug | QJ2041 | Morningside, flashing to the canopy fascia | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260811-0071 | Josh Mardin Roof Plumber | Tue 11 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260811-0072 | Dane Kelso Cladding Installer | Tue 11 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 7 | $378.00 | Crew app | Approved | |
| TS-20260811-0073 | Dane Kelso Cladding Installer | Tue 11 Aug | QJ2041 | Lindum, anchor point install and certification Changed cost centre part way through the shift. | CC-05 Height access & safety systems | RS-HGT-ANC | 3 +2 | $324.00 | Crew app | Approved | |
| TS-20260811-0074 | Tyrone Baker Cladding Installer | Tue 11 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260811-0075 | Isaac Vella Rope Access Tech | Tue 11 Aug | QJ2041 | Morningside entry, Finesse panel set-out | CC-03 Wall cladding | RS-CLD-FIN | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260811-0076 | Nick Harrow Cladding Installer | Tue 11 Aug | QJ2041 | Supervision and possession co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260811-0077 | Kade Whitmore Cladding Installer | Tue 11 Aug | QJ2041 | Lindum overpass, static line install (VAR-041-04) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260811-0078 | Shaun Ferris EWP Operator | Tue 11 Aug | QJ2041 | Morningside, flashing to the canopy fascia | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $767.00 | Crew app | Approved | |
| TS-20260811-0079 | Beau Lansdown Labourer | Tue 11 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260811-0080 | Corey Iona Cladding Installer | Tue 11 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260812-0081 | Blake Tuiala Leading Hand | Wed 12 Aug | QJ2041 | Rail: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $640.00 | Crew app | Submitted | |
| TS-20260812-0082 | Ryan Petrie Roof Plumber | Wed 12 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 | $580.00 | Crew app | Submitted | |
| TS-20260812-0083 | Josh Mardin Roof Plumber | Wed 12 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 10 | $580.00 | Crew app | Submitted | |
| TS-20260812-0084 | Dane Kelso Cladding Installer | Wed 12 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 10 | $540.00 | Crew app | Submitted | |
| TS-20260812-0085 | Tyrone Baker Cladding Installer | Wed 12 Aug | QJ2041 | Morningside entry, Finesse panel set-out | CC-03 Wall cladding | RS-CLD-FIN | 10 | $540.00 | Crew app | Submitted | |
| TS-20260812-0086 | Isaac Vella Rope Access Tech | Wed 12 Aug | QJ2041 | Supervision and possession co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $690.00 | Crew app | Submitted | |
| TS-20260812-0087 | Nick Harrow Cladding Installer | Wed 12 Aug | QJ2041 | Lindum overpass, sheeting to the eastern deck | CC-02 Roofing | RS-ROF-KL7 | 10 | $540.00 | Crew app | Submitted | |
| TS-20260812-0088 | Kade Whitmore Cladding Installer | Wed 12 Aug | QJ2041 | Morningside, flashing to the canopy fascia | CC-03 Wall cladding | RS-CLD-FLA | 10 | $540.00 | Crew app | Submitted | |
| TS-20260812-0089 | Shaun Ferris EWP Operator | Wed 12 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 | $590.00 | Crew app | Submitted | |
| TS-20260812-0090 | Beau Lansdown Labourer | Wed 12 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 10 | $420.00 | Crew app | Submitted | |
| TS-20260812-0091 | Corey Iona Cladding Installer | Wed 12 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 10 | $540.00 | Crew app | Submitted | |
| TS-20260813-0092 | Blake Tuiala Leading Hand | Thu 13 Aug | QJ2041 | Rail: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Submitted | |
| TS-20260813-0093 | Ryan Petrie Roof Plumber | Thu 13 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $754.00 | Crew app | Submitted | |
| TS-20260813-0094 | Josh Mardin Roof Plumber | Thu 13 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 10 +2 | $754.00 | Crew app | Submitted | |
| TS-20260813-0095 | Dane Kelso Cladding Installer | Thu 13 Aug | QJ2041 | Morningside entry, Finesse panel set-out | CC-03 Wall cladding | RS-CLD-FIN | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260813-0096 | Tyrone Baker Cladding Installer | Thu 13 Aug | QJ2041 | Supervision and possession co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260813-0097 | Isaac Vella Rope Access Tech | Thu 13 Aug | QJ2041 | Lindum overpass, sheeting to the eastern deck | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $897.00 | Crew app | Submitted | |
| TS-20260813-0098 | Nick Harrow Cladding Installer | Thu 13 Aug | QJ2041 | Lindum overpass, static line install (VAR-041-04) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260813-0099 | Kade Whitmore Cladding Installer | Thu 13 Aug | QJ2041 | Banyo: canopy sheeting, bays 6 to 11 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260813-0100 | Shaun Ferris EWP Operator | Thu 13 Aug | QJ2041 | Buranda, sealant to laps and penetrations | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $767.00 | Crew app | Submitted | |
| TS-20260813-0101 | Beau Lansdown Labourer | Thu 13 Aug | QJ2041 | Lindum, anchor point install and certification | CC-05 Height access & safety systems | RS-HGT-ANC | 10 +2 | $546.00 | Crew app | Submitted | |
| TS-20260813-0102 | Corey Iona Cladding Installer | Thu 13 Aug | QJ2041 | Morningside entry, Finesse panel set-out | CC-03 Wall cladding | RS-CLD-FIN | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260803-0103 | Mitch Ravenscroft Leading Hand | Mon 3 Aug | QJ2044 | Bowen Basin: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $736.00 | Crew app | Approved | |
| TS-20260803-0104 | Trent Osborne Roof Plumber | Mon 3 Aug | QJ2044 | Saraji workshop, roof sheeting bays 12 to 16 | CC-02 Roofing | RS-ROF-KL7 | 10 +1 | $667.00 | Crew app | Approved | |
| TS-20260803-0105 | Damien Yorke Cladding Installer | Mon 3 Aug | QJ2044 | Purlin replacement, bays 7 to 9 (VAR-044-01) | CC-03 Wall cladding | RS-CLD-PUR | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260803-0106 | Brody Chan Cladding Installer | Mon 3 Aug | QJ2044 | Wash bay louvre install (VAR-044-02) | CC-03 Wall cladding | RS-CLD-LOU | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260803-0107 | Angus Petersen Rope Access Tech | Mon 3 Aug | QJ2044 | Safety mesh to the northern bays | CC-02 Roofing | RS-ROF-SAF | 10 +1 | $793.50 | Crew app | Approved | |
| TS-20260803-0108 | Wade Tolhurst Sheeting Hand | Mon 3 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 +1 | $586.50 | Crew app | Approved | |
| TS-20260803-0109 | Jesse Mallard Cladding Installer | Mon 3 Aug | QJ2044 | Supervision and crane isolation co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260803-0110 | Ashton Reilly Apprentice, 2nd yr | Mon 3 Aug | QJ2044 | Saraji workshop: wall cladding, eastern elevation | CC-03 Wall cladding | RS-CLD-KL7 | 10 +1 | $345.00 | Crew app | Approved | |
| TS-20260803-0111 | Kirk Danaher EWP Operator | Mon 3 Aug | QJ2044 | Saraji workshop, roof sheeting bays 12 to 16 | CC-02 Roofing | RS-ROF-KL7 | 10 +1 | $678.50 | Crew app | Approved | |
| TS-20260803-0112 | Rhys Callaghan Cladding Installer | Mon 3 Aug | QJ2044 | Wash bay louvre install (VAR-044-02) | CC-03 Wall cladding | RS-CLD-LOU | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260804-0113 | Mitch Ravenscroft Leading Hand | Tue 4 Aug | QJ2044 | Bowen Basin: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $736.00 | Crew app | Approved | |
| TS-20260804-0114 | Trent Osborne Roof Plumber | Tue 4 Aug | QJ2044 | Purlin replacement, bays 7 to 9 (VAR-044-01) | CC-03 Wall cladding | RS-CLD-PUR | 10 +1 | $667.00 | Crew app | Approved | |
| TS-20260804-0115 | Damien Yorke Cladding Installer | Tue 4 Aug | QJ2044 | Wash bay louvre install (VAR-044-02) | CC-03 Wall cladding | RS-CLD-LOU | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260804-0116 | Brody Chan Cladding Installer | Tue 4 Aug | QJ2044 | Safety mesh to the northern bays | CC-02 Roofing | RS-ROF-SAF | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260804-0117 | Angus Petersen Rope Access Tech | Tue 4 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 +1 | $793.50 | Crew app | Approved | |
| TS-20260804-0118 | Wade Tolhurst Sheeting Hand | Tue 4 Aug | QJ2044 | Supervision and crane isolation co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $586.50 | Crew app | Approved | |
| TS-20260804-0119 | Jesse Mallard Cladding Installer | Tue 4 Aug | QJ2044 | Saraji workshop: wall cladding, eastern elevation | CC-03 Wall cladding | RS-CLD-KL7 | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260804-0120 | Ashton Reilly Apprentice, 2nd yr | Tue 4 Aug | QJ2044 | Saraji workshop, roof sheeting bays 12 to 16 | CC-02 Roofing | RS-ROF-KL7 | 10 +1 | $345.00 | Crew app | Approved | |
| TS-20260804-0121 | Kirk Danaher EWP Operator | Tue 4 Aug | QJ2044 | Purlin replacement, bays 7 to 9 (VAR-044-01) | CC-03 Wall cladding | RS-CLD-PUR | 10 +1 | $678.50 | Crew app | Approved | |
| TS-20260804-0122 | Rhys Callaghan Cladding Installer | Tue 4 Aug | QJ2044 | Safety mesh to the northern bays | CC-02 Roofing | RS-ROF-SAF | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260805-0123 | Mitch Ravenscroft Leading Hand | Wed 5 Aug | QJ2044 | Bowen Basin: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $736.00 | Crew app | Approved | |
| TS-20260805-0124 | Trent Osborne Roof Plumber | Wed 5 Aug | QJ2044 | Wash bay louvre install (VAR-044-02) | CC-03 Wall cladding | RS-CLD-LOU | 10 +1 | $667.00 | Crew app | Approved | |
| TS-20260805-0125 | Damien Yorke Cladding Installer | Wed 5 Aug | QJ2044 | Safety mesh to the northern bays | CC-02 Roofing | RS-ROF-SAF | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260805-0126 | Brody Chan Cladding Installer | Wed 5 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260805-0127 | Angus Petersen Rope Access Tech | Wed 5 Aug | QJ2044 | Supervision and crane isolation co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $793.50 | Crew app | Approved | |
| TS-20260805-0128 | Wade Tolhurst Sheeting Hand | Wed 5 Aug | QJ2044 | Saraji workshop: wall cladding, eastern elevation | CC-03 Wall cladding | RS-CLD-KL7 | 10 +1 | $586.50 | Crew app | Approved | |
| TS-20260805-0129 | Jesse Mallard Cladding Installer | Wed 5 Aug | QJ2044 | Saraji workshop, roof sheeting bays 12 to 16 | CC-02 Roofing | RS-ROF-KL7 | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260805-0130 | Ashton Reilly Apprentice, 2nd yr | Wed 5 Aug | QJ2044 | Purlin replacement, bays 7 to 9 (VAR-044-01) | CC-03 Wall cladding | RS-CLD-PUR | 10 +1 | $345.00 | Crew app | Approved | |
| TS-20260805-0131 | Nathan Prowse Labourer | Wed 5 Aug | QJ2044 | Safety mesh to the northern bays | CC-02 Roofing | RS-ROF-SAF | 10 +1 | $483.00 | Crew app | Approved | |
| TS-20260805-0132 | Rhys Callaghan Cladding Installer | Wed 5 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260806-0133 | Mitch Ravenscroft Leading Hand | Thu 6 Aug | QJ2044 | Bowen Basin: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $640.00 | Crew app | Approved | |
| TS-20260806-0134 | Trent Osborne Roof Plumber | Thu 6 Aug | QJ2044 | Safety mesh to the northern bays | CC-02 Roofing | RS-ROF-SAF | 10 | $580.00 | Crew app | Approved | |
| TS-20260806-0135 | Damien Yorke Cladding Installer | Thu 6 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 | $540.00 | Crew app | Approved | |
| TS-20260806-0136 | Brody Chan Cladding Installer | Thu 6 Aug | QJ2044 | Supervision and crane isolation co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $540.00 | Crew app | Approved | |
| TS-20260806-0137 | Angus Petersen Rope Access Tech | Thu 6 Aug | QJ2044 | Saraji workshop: wall cladding, eastern elevation | CC-03 Wall cladding | RS-CLD-KL7 | 10 | $690.00 | Crew app | Approved | |
| TS-20260806-0138 | Jesse Mallard Cladding Installer | Thu 6 Aug | QJ2044 | Purlin replacement, bays 7 to 9 (VAR-044-01) | CC-03 Wall cladding | RS-CLD-PUR | 10 | $540.00 | Crew app | Approved | |
| TS-20260806-0139 | Ashton Reilly Apprentice, 2nd yr | Thu 6 Aug | QJ2044 | Wash bay louvre install (VAR-044-02) | CC-03 Wall cladding | RS-CLD-LOU | 10 | $300.00 | Crew app | Approved | |
| TS-20260806-0140 | Nathan Prowse Labourer | Thu 6 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 | $420.00 | Crew app | Approved | |
| TS-20260806-0141 | Rhys Callaghan Cladding Installer | Thu 6 Aug | QJ2044 | Supervision and crane isolation co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $540.00 | Crew app | Approved | |
| TS-20260807-0142 | Mitch Ravenscroft Leading Hand | Fri 7 Aug | QJ2044 | Bowen Basin: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $736.00 | Crew app | Approved | |
| TS-20260807-0143 | Trent Osborne Roof Plumber | Fri 7 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 +1 | $667.00 | Crew app | Approved | |
| TS-20260807-0144 | Damien Yorke Cladding Installer | Fri 7 Aug | QJ2044 | Supervision and crane isolation co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260807-0145 | Brody Chan Cladding Installer | Fri 7 Aug | QJ2044 | Saraji workshop: wall cladding, eastern elevation | CC-03 Wall cladding | RS-CLD-KL7 | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260807-0146 | Angus Petersen Rope Access Tech | Fri 7 Aug | QJ2044 | Saraji workshop, roof sheeting bays 12 to 16 | CC-02 Roofing | RS-ROF-KL7 | 10 +1 | $793.50 | Crew app | Approved | |
| TS-20260807-0147 | Jesse Mallard Cladding Installer | Fri 7 Aug | QJ2044 | Wash bay louvre install (VAR-044-02) | CC-03 Wall cladding | RS-CLD-LOU | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260807-0148 | Ashton Reilly Apprentice, 2nd yr | Fri 7 Aug | QJ2044 | Safety mesh to the northern bays | CC-02 Roofing | RS-ROF-SAF | 10 +1 | $345.00 | Crew app | Approved | |
| TS-20260807-0149 | Nathan Prowse Labourer | Fri 7 Aug | QJ2044 | Supervision and crane isolation co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $483.00 | Crew app | Approved | |
| TS-20260807-0150 | Rhys Callaghan Cladding Installer | Fri 7 Aug | QJ2044 | Saraji workshop: wall cladding, eastern elevation | CC-03 Wall cladding | RS-CLD-KL7 | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260810-0151 | Mitch Ravenscroft Leading Hand | Mon 10 Aug | QJ2044 | Bowen Basin: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $736.00 | Crew app | Approved | |
| TS-20260810-0152 | Trent Osborne Roof Plumber | Mon 10 Aug | QJ2044 | Saraji workshop, roof sheeting bays 12 to 16 | CC-02 Roofing | RS-ROF-KL7 | 10 +1 | $667.00 | Crew app | Approved | |
| TS-20260810-0153 | Damien Yorke Cladding Installer | Mon 10 Aug | QJ2044 | Purlin replacement, bays 7 to 9 (VAR-044-01) | CC-03 Wall cladding | RS-CLD-PUR | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260810-0154 | Brody Chan Cladding Installer | Mon 10 Aug | QJ2044 | Wash bay louvre install (VAR-044-02) | CC-03 Wall cladding | RS-CLD-LOU | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260810-0155 | Angus Petersen Rope Access Tech | Mon 10 Aug | QJ2044 | Safety mesh to the northern bays | CC-02 Roofing | RS-ROF-SAF | 10 +1 | $793.50 | Crew app | Approved | |
| TS-20260810-0156 | Wade Tolhurst Sheeting Hand | Mon 10 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 +1 | $586.50 | Crew app | Approved | |
| TS-20260810-0157 | Jesse Mallard Cladding Installer | Mon 10 Aug | QJ2044 | Supervision and crane isolation co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260810-0158 | Ashton Reilly Apprentice, 2nd yr | Mon 10 Aug | QJ2044 | Saraji workshop: wall cladding, eastern elevation | CC-03 Wall cladding | RS-CLD-KL7 | 10 +1 | $345.00 | Crew app | Approved | |
| TS-20260810-0159 | Kirk Danaher EWP Operator | Mon 10 Aug | QJ2044 | Saraji workshop, roof sheeting bays 12 to 16 | CC-02 Roofing | RS-ROF-KL7 | 10 +1 | $678.50 | Crew app | Approved | |
| TS-20260810-0160 | Rhys Callaghan Cladding Installer | Mon 10 Aug | QJ2044 | Wash bay louvre install (VAR-044-02) | CC-03 Wall cladding | RS-CLD-LOU | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260811-0161 | Mitch Ravenscroft Leading Hand | Tue 11 Aug | QJ2044 | Bowen Basin: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $736.00 | Crew app | Approved | |
| TS-20260811-0162 | Trent Osborne Roof Plumber | Tue 11 Aug | QJ2044 | Purlin replacement, bays 7 to 9 (VAR-044-01) | CC-03 Wall cladding | RS-CLD-PUR | 10 +1 | $667.00 | Crew app | Approved | |
| TS-20260811-0163 | Damien Yorke Cladding Installer | Tue 11 Aug | QJ2044 | Wash bay louvre install (VAR-044-02) | CC-03 Wall cladding | RS-CLD-LOU | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260811-0164 | Brody Chan Cladding Installer | Tue 11 Aug | QJ2044 | Safety mesh to the northern bays | CC-02 Roofing | RS-ROF-SAF | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260811-0165 | Angus Petersen Rope Access Tech | Tue 11 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 +1 | $793.50 | Crew app | Approved | |
| TS-20260811-0166 | Wade Tolhurst Sheeting Hand | Tue 11 Aug | QJ2044 | Supervision and crane isolation co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $586.50 | Crew app | Approved | |
| TS-20260811-0167 | Jesse Mallard Cladding Installer | Tue 11 Aug | QJ2044 | Saraji workshop: wall cladding, eastern elevation | CC-03 Wall cladding | RS-CLD-KL7 | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260811-0168 | Ashton Reilly Apprentice, 2nd yr | Tue 11 Aug | QJ2044 | Saraji workshop, roof sheeting bays 12 to 16 | CC-02 Roofing | RS-ROF-KL7 | 10 +1 | $345.00 | Crew app | Approved | |
| TS-20260811-0169 | Kirk Danaher EWP Operator | Tue 11 Aug | QJ2044 | Purlin replacement, bays 7 to 9 (VAR-044-01) | CC-03 Wall cladding | RS-CLD-PUR | 10 +1 | $678.50 | Crew app | Approved | |
| TS-20260811-0170 | Rhys Callaghan Cladding Installer | Tue 11 Aug | QJ2044 | Safety mesh to the northern bays | CC-02 Roofing | RS-ROF-SAF | 10 +1 | $621.00 | Crew app | Approved | |
| TS-20260812-0171 | Mitch Ravenscroft Leading Hand | Wed 12 Aug | QJ2044 | Bowen Basin: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $736.00 | Crew app | Submitted | |
| TS-20260812-0172 | Trent Osborne Roof Plumber | Wed 12 Aug | QJ2044 | Wash bay louvre install (VAR-044-02) | CC-03 Wall cladding | RS-CLD-LOU | 10 +1 | $667.00 | Crew app | Submitted | |
| TS-20260812-0173 | Damien Yorke Cladding Installer | Wed 12 Aug | QJ2044 | Safety mesh to the northern bays | CC-02 Roofing | RS-ROF-SAF | 10 +1 | $621.00 | Crew app | Submitted | |
| TS-20260812-0174 | Brody Chan Cladding Installer | Wed 12 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 +1 | $621.00 | Crew app | Submitted | |
| TS-20260812-0175 | Angus Petersen Rope Access Tech | Wed 12 Aug | QJ2044 | Supervision and crane isolation co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +1 | $793.50 | Crew app | Submitted | |
| TS-20260812-0176 | Wade Tolhurst Sheeting Hand | Wed 12 Aug | QJ2044 | Saraji workshop: wall cladding, eastern elevation | CC-03 Wall cladding | RS-CLD-KL7 | 10 +1 | $586.50 | Crew app | Submitted | |
| TS-20260812-0177 | Jesse Mallard Cladding Installer | Wed 12 Aug | QJ2044 | Saraji workshop, roof sheeting bays 12 to 16 | CC-02 Roofing | RS-ROF-KL7 | 10 +1 | $621.00 | Crew app | Submitted | |
| TS-20260812-0178 | Ashton Reilly Apprentice, 2nd yr | Wed 12 Aug | QJ2044 | Purlin replacement, bays 7 to 9 (VAR-044-01) | CC-03 Wall cladding | RS-CLD-PUR | 10 +1 | $345.00 | Crew app | Submitted | |
| TS-20260812-0179 | Nathan Prowse Labourer | Wed 12 Aug | QJ2044 | Safety mesh to the northern bays | CC-02 Roofing | RS-ROF-SAF | 10 +1 | $483.00 | Crew app | Submitted | |
| TS-20260812-0180 | Rhys Callaghan Cladding Installer | Wed 12 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 +1 | $621.00 | Crew app | Submitted | |
| TS-20260813-0181 | Mitch Ravenscroft Leading Hand | Thu 13 Aug | QJ2044 | Bowen Basin: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $640.00 | Crew app | Submitted | |
| TS-20260813-0182 | Trent Osborne Roof Plumber | Thu 13 Aug | QJ2044 | Safety mesh to the northern bays Twelve hours booked against a ten-hour shift with no overtime approval on file. Cameron has asked Mitch for the docket. | CC-02 Roofing | RS-ROF-SAF | 10 | $580.00 | Crew app | Queried | |
| TS-20260813-0183 | Damien Yorke Cladding Installer | Thu 13 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 | $540.00 | Crew app | Submitted | |
| TS-20260813-0184 | Brody Chan Cladding Installer | Thu 13 Aug | QJ2044 | Supervision and crane isolation co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $540.00 | Crew app | Submitted | |
| TS-20260813-0185 | Angus Petersen Rope Access Tech | Thu 13 Aug | QJ2044 | Saraji workshop: wall cladding, eastern elevation | CC-03 Wall cladding | RS-CLD-KL7 | 10 | $690.00 | Crew app | Submitted | |
| TS-20260813-0186 | Jesse Mallard Cladding Installer | Thu 13 Aug | QJ2044 | Purlin replacement, bays 7 to 9 (VAR-044-01) | CC-03 Wall cladding | RS-CLD-PUR | 10 | $540.00 | Crew app | Submitted | |
| TS-20260813-0187 | Ashton Reilly Apprentice, 2nd yr | Thu 13 Aug | QJ2044 | Wash bay louvre install (VAR-044-02) | CC-03 Wall cladding | RS-CLD-LOU | 10 | $300.00 | Crew app | Submitted | |
| TS-20260813-0188 | Nathan Prowse Labourer | Thu 13 Aug | QJ2044 | Flashing to the crane runway penetrations | CC-03 Wall cladding | RS-CLD-FLA | 10 | $420.00 | Crew app | Submitted | |
| TS-20260813-0189 | Rhys Callaghan Cladding Installer | Thu 13 Aug | QJ2044 | Supervision and crane isolation co-ordination | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $540.00 | Crew app | Submitted | |
| TS-20260803-0190 | Zeb Marchetti Leading Hand | Mon 3 Aug | QJ2006 | FIFO West: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260803-0191 | Callum Byrne Roof Plumber | Mon 3 Aug | QJ2006 | Shed 1 south, blanket insulation and safety mesh | CC-02 Roofing | RS-ROF-INS | 6 | $348.00 | Crew app | Approved | |
| TS-20260803-0192 | Callum Byrne Roof Plumber | Mon 3 Aug | QJ2006 | Conveyor gallery, static line (VAR-006-03) Changed cost centre part way through the shift. | CC-05 Height access & safety systems | RS-HGT-STA | 4 +2 | $406.00 | Crew app | Approved | |
| TS-20260803-0193 | Deacon Whitely Acoustic Installer | Mon 3 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $728.00 | Crew app | Approved | |
| TS-20260803-0194 | Hamish Ngata Acoustic Installer | Mon 3 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $728.00 | Crew app | Approved | |
| TS-20260803-0195 | Levi Sandford Cladding Installer | Mon 3 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260803-0196 | Brett Hallam Rope Access Tech | Mon 3 Aug | QJ2006 | Sealant to laps and penetrations, Shed 1 | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260803-0197 | Fletcher Doig Cladding Installer | Mon 3 Aug | QJ2006 | Supervision and JV clock-on reconciliation | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260803-0198 | Sione Fatu Labourer | Mon 3 Aug | QJ2006 | Shed 1 north: KLIP-LOK 700, bays 14 to 19 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260803-0199 | Kyle Anderton Apprentice, 1st yr | Mon 3 Aug | QJ2006 | Shed 1 south, blanket insulation and safety mesh | CC-02 Roofing | RS-ROF-INS | 10 +2 | $338.00 | Crew app | Approved | |
| TS-20260803-0200 | Bailey Rutherford Cladding Installer | Mon 3 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260804-0201 | Zeb Marchetti Leading Hand | Tue 4 Aug | QJ2006 | FIFO West: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260804-0202 | Callum Byrne Roof Plumber | Tue 4 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260804-0203 | Deacon Whitely Acoustic Installer | Tue 4 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $728.00 | Crew app | Approved | |
| TS-20260804-0204 | Hamish Ngata Acoustic Installer | Tue 4 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 7 | $392.00 | Crew app | Approved | |
| TS-20260804-0205 | Hamish Ngata Acoustic Installer | Tue 4 Aug | QJ2006 | Shed 1 north, sealant to laps after the sheeting crew Changed cost centre part way through the shift. | CC-06 Weatherproofing | RS-WPF-SEA | 3 +2 | $336.00 | Crew app | Approved | |
| TS-20260804-0206 | Levi Sandford Cladding Installer | Tue 4 Aug | QJ2006 | Shed 2 north, box gutter to the eastern valley | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260804-0207 | Brett Hallam Rope Access Tech | Tue 4 Aug | QJ2006 | Supervision and JV clock-on reconciliation | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260804-0208 | Fletcher Doig Cladding Installer | Tue 4 Aug | QJ2006 | Shed 1 north: KLIP-LOK 700, bays 14 to 19 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260804-0209 | Sione Fatu Labourer | Tue 4 Aug | QJ2006 | Shed 1 south, blanket insulation and safety mesh | CC-02 Roofing | RS-ROF-INS | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260804-0210 | Kyle Anderton Apprentice, 1st yr | Tue 4 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $338.00 | Crew app | Approved | |
| TS-20260804-0211 | Bailey Rutherford Cladding Installer | Tue 4 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260805-0212 | Zeb Marchetti Leading Hand | Wed 5 Aug | QJ2006 | FIFO West: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260805-0213 | Callum Byrne Roof Plumber | Wed 5 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 6 | $348.00 | Crew app | Approved | |
| TS-20260805-0214 | Callum Byrne Roof Plumber | Wed 5 Aug | QJ2006 | Conveyor gallery, static line (VAR-006-03) Changed cost centre part way through the shift. | CC-05 Height access & safety systems | RS-HGT-STA | 4 +2 | $406.00 | Crew app | Approved | |
| TS-20260805-0215 | Deacon Whitely Acoustic Installer | Wed 5 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $728.00 | Crew app | Approved | |
| TS-20260805-0216 | Hamish Ngata Acoustic Installer | Wed 5 Aug | QJ2006 | Shed 2 north, box gutter to the eastern valley | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $728.00 | Crew app | Approved | |
| TS-20260805-0217 | Levi Sandford Cladding Installer | Wed 5 Aug | QJ2006 | Sealant to laps and penetrations, Shed 1 | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260805-0218 | Brett Hallam Rope Access Tech | Wed 5 Aug | QJ2006 | Shed 1 north: KLIP-LOK 700, bays 14 to 19 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260805-0219 | Fletcher Doig Cladding Installer | Wed 5 Aug | QJ2006 | Shed 1 south, blanket insulation and safety mesh | CC-02 Roofing | RS-ROF-INS | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260805-0220 | Sione Fatu Labourer | Wed 5 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260805-0221 | Kyle Anderton Apprentice, 1st yr | Wed 5 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $338.00 | Crew app | Approved | |
| TS-20260805-0222 | Bailey Rutherford Cladding Installer | Wed 5 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260806-0223 | Zeb Marchetti Leading Hand | Thu 6 Aug | QJ2006 | FIFO West: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260806-0224 | Callum Byrne Roof Plumber | Thu 6 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 6 | $348.00 | Crew app | Approved | |
| TS-20260806-0225 | Callum Byrne Roof Plumber | Thu 6 Aug | QJ2006 | Conveyor gallery, static line (VAR-006-03) Changed cost centre part way through the shift. | CC-05 Height access & safety systems | RS-HGT-STA | 4 +2 | $406.00 | Crew app | Approved | |
| TS-20260806-0226 | Deacon Whitely Acoustic Installer | Thu 6 Aug | QJ2006 | Shed 2 north, box gutter to the eastern valley | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $728.00 | Crew app | Approved | |
| TS-20260806-0227 | Hamish Ngata Acoustic Installer | Thu 6 Aug | QJ2006 | Sealant to laps and penetrations, Shed 1 | CC-06 Weatherproofing | RS-WPF-SEA | 7 | $392.00 | Crew app | Approved | |
| TS-20260806-0228 | Hamish Ngata Acoustic Installer | Thu 6 Aug | QJ2006 | Shed 1 north, sealant to laps after the sheeting crew Changed cost centre part way through the shift. | CC-06 Weatherproofing | RS-WPF-SEA | 3 +2 | $336.00 | Crew app | Approved | |
| TS-20260806-0229 | Levi Sandford Cladding Installer | Thu 6 Aug | QJ2006 | Supervision and JV clock-on reconciliation | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260806-0230 | Brett Hallam Rope Access Tech | Thu 6 Aug | QJ2006 | Shed 1 south, blanket insulation and safety mesh | CC-02 Roofing | RS-ROF-INS | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260806-0231 | Fletcher Doig Cladding Installer | Thu 6 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260806-0232 | Sione Fatu Labourer | Thu 6 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260806-0233 | Kyle Anderton Apprentice, 1st yr | Thu 6 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $338.00 | Crew app | Approved | |
| TS-20260806-0234 | Bailey Rutherford Cladding Installer | Thu 6 Aug | QJ2006 | Shed 2 north, box gutter to the eastern valley | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260807-0235 | Zeb Marchetti Leading Hand | Fri 7 Aug | QJ2006 | FIFO West: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260807-0236 | Callum Byrne Roof Plumber | Fri 7 Aug | QJ2006 | Shed 2 north, box gutter to the eastern valley | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260807-0237 | Deacon Whitely Acoustic Installer | Fri 7 Aug | QJ2006 | Sealant to laps and penetrations, Shed 1 | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $728.00 | Crew app | Approved | |
| TS-20260807-0238 | Hamish Ngata Acoustic Installer | Fri 7 Aug | QJ2006 | Supervision and JV clock-on reconciliation | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $728.00 | Crew app | Approved | |
| TS-20260807-0239 | Levi Sandford Cladding Installer | Fri 7 Aug | QJ2006 | Shed 1 north: KLIP-LOK 700, bays 14 to 19 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260807-0240 | Brett Hallam Rope Access Tech | Fri 7 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260807-0241 | Fletcher Doig Cladding Installer | Fri 7 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260807-0242 | Sione Fatu Labourer | Fri 7 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260807-0243 | Kyle Anderton Apprentice, 1st yr | Fri 7 Aug | QJ2006 | Shed 2 north, box gutter to the eastern valley | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $338.00 | Crew app | Approved | |
| TS-20260807-0244 | Bailey Rutherford Cladding Installer | Fri 7 Aug | QJ2006 | Sealant to laps and penetrations, Shed 1 | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260810-0245 | Zeb Marchetti Leading Hand | Mon 10 Aug | QJ2006 | FIFO West: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260810-0246 | Callum Byrne Roof Plumber | Mon 10 Aug | QJ2006 | Shed 1 south, blanket insulation and safety mesh | CC-02 Roofing | RS-ROF-INS | 6 | $348.00 | Crew app | Approved | |
| TS-20260810-0247 | Callum Byrne Roof Plumber | Mon 10 Aug | QJ2006 | Conveyor gallery, static line (VAR-006-03) Changed cost centre part way through the shift. | CC-05 Height access & safety systems | RS-HGT-STA | 4 +2 | $406.00 | Crew app | Approved | |
| TS-20260810-0248 | Deacon Whitely Acoustic Installer | Mon 10 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $728.00 | Crew app | Approved | |
| TS-20260810-0249 | Hamish Ngata Acoustic Installer | Mon 10 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $728.00 | Crew app | Approved | |
| TS-20260810-0250 | Levi Sandford Cladding Installer | Mon 10 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260810-0251 | Brett Hallam Rope Access Tech | Mon 10 Aug | QJ2006 | Sealant to laps and penetrations, Shed 1 | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260810-0252 | Fletcher Doig Cladding Installer | Mon 10 Aug | QJ2006 | Supervision and JV clock-on reconciliation | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260810-0253 | Sione Fatu Labourer | Mon 10 Aug | QJ2006 | Shed 1 north: KLIP-LOK 700, bays 14 to 19 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260810-0254 | Kyle Anderton Apprentice, 1st yr | Mon 10 Aug | QJ2006 | Shed 1 south, blanket insulation and safety mesh | CC-02 Roofing | RS-ROF-INS | 10 +2 | $338.00 | Crew app | Approved | |
| TS-20260810-0255 | Bailey Rutherford Cladding Installer | Mon 10 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260811-0256 | Zeb Marchetti Leading Hand | Tue 11 Aug | QJ2006 | FIFO West: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260811-0257 | Callum Byrne Roof Plumber | Tue 11 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260811-0258 | Deacon Whitely Acoustic Installer | Tue 11 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $728.00 | Crew app | Approved | |
| TS-20260811-0259 | Hamish Ngata Acoustic Installer | Tue 11 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 7 | $392.00 | Crew app | Approved | |
| TS-20260811-0260 | Hamish Ngata Acoustic Installer | Tue 11 Aug | QJ2006 | Shed 1 north, sealant to laps after the sheeting crew Changed cost centre part way through the shift. | CC-06 Weatherproofing | RS-WPF-SEA | 3 +2 | $336.00 | Crew app | Approved | |
| TS-20260811-0261 | Levi Sandford Cladding Installer | Tue 11 Aug | QJ2006 | Shed 2 north, box gutter to the eastern valley | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260811-0262 | Brett Hallam Rope Access Tech | Tue 11 Aug | QJ2006 | Supervision and JV clock-on reconciliation | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260811-0263 | Fletcher Doig Cladding Installer | Tue 11 Aug | QJ2006 | Shed 1 north: KLIP-LOK 700, bays 14 to 19 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260811-0264 | Sione Fatu Labourer | Tue 11 Aug | QJ2006 | Shed 1 south, blanket insulation and safety mesh | CC-02 Roofing | RS-ROF-INS | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260811-0265 | Kyle Anderton Apprentice, 1st yr | Tue 11 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $338.00 | Crew app | Approved | |
| TS-20260811-0266 | Bailey Rutherford Cladding Installer | Tue 11 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260812-0267 | Zeb Marchetti Leading Hand | Wed 12 Aug | QJ2006 | FIFO West: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Submitted | |
| TS-20260812-0268 | Callum Byrne Roof Plumber | Wed 12 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 6 | $348.00 | Crew app | Submitted | |
| TS-20260812-0269 | Callum Byrne Roof Plumber | Wed 12 Aug | QJ2006 | Conveyor gallery, static line (VAR-006-03) Changed cost centre part way through the shift. | CC-05 Height access & safety systems | RS-HGT-STA | 4 +2 | $406.00 | Crew app | Submitted | |
| TS-20260812-0270 | Deacon Whitely Acoustic Installer | Wed 12 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $728.00 | Crew app | Submitted | |
| TS-20260812-0271 | Hamish Ngata Acoustic Installer | Wed 12 Aug | QJ2006 | Shed 2 north, box gutter to the eastern valley | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $728.00 | Crew app | Submitted | |
| TS-20260812-0272 | Levi Sandford Cladding Installer | Wed 12 Aug | QJ2006 | Sealant to laps and penetrations, Shed 1 | CC-06 Weatherproofing | RS-WPF-SEA | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260812-0273 | Brett Hallam Rope Access Tech | Wed 12 Aug | QJ2006 | Shed 1 north: KLIP-LOK 700, bays 14 to 19 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $897.00 | Crew app | Submitted | |
| TS-20260812-0274 | Fletcher Doig Cladding Installer | Wed 12 Aug | QJ2006 | Shed 1 south, blanket insulation and safety mesh | CC-02 Roofing | RS-ROF-INS | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260812-0275 | Sione Fatu Labourer | Wed 12 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $546.00 | Crew app | Submitted | |
| TS-20260812-0276 | Kyle Anderton Apprentice, 1st yr | Wed 12 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $338.00 | Crew app | Submitted | |
| TS-20260812-0277 | Bailey Rutherford Cladding Installer | Wed 12 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260813-0278 | Zeb Marchetti Leading Hand | Thu 13 Aug | QJ2006 | FIFO West: supervision, crew of 11 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Submitted | |
| TS-20260813-0279 | Callum Byrne Roof Plumber | Thu 13 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 6 | $348.00 | Crew app | Submitted | |
| TS-20260813-0280 | Callum Byrne Roof Plumber | Thu 13 Aug | QJ2006 | Conveyor gallery, static line (VAR-006-03) Changed cost centre part way through the shift. | CC-05 Height access & safety systems | RS-HGT-STA | 4 +2 | $406.00 | Crew app | Submitted | |
| TS-20260813-0281 | Deacon Whitely Acoustic Installer | Thu 13 Aug | QJ2006 | Shed 2 north, box gutter to the eastern valley | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $728.00 | Crew app | Submitted | |
| TS-20260813-0282 | Hamish Ngata Acoustic Installer | Thu 13 Aug | QJ2006 | Sealant to laps and penetrations, Shed 1 | CC-06 Weatherproofing | RS-WPF-SEA | 7 | $392.00 | Crew app | Submitted | |
| TS-20260813-0283 | Hamish Ngata Acoustic Installer | Thu 13 Aug | QJ2006 | Shed 1 north, sealant to laps after the sheeting crew Changed cost centre part way through the shift. | CC-06 Weatherproofing | RS-WPF-SEA | 3 +2 | $336.00 | Crew app | Submitted | |
| TS-20260813-0284 | Levi Sandford Cladding Installer | Thu 13 Aug | QJ2006 | Supervision and JV clock-on reconciliation | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260813-0285 | Brett Hallam Rope Access Tech | Thu 13 Aug | QJ2006 | Shed 1 south, blanket insulation and safety mesh | CC-02 Roofing | RS-ROF-INS | 10 +2 | $897.00 | Crew app | Submitted | |
| TS-20260813-0286 | Fletcher Doig Cladding Installer | Thu 13 Aug | QJ2006 | Shed 1 north, Kingspan panel to the eastern elevation | CC-03 Wall cladding | RS-CLD-KSP | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260813-0287 | Sione Fatu Labourer | Thu 13 Aug | QJ2006 | Shed 1 south, flashing to the ridge and barge | CC-03 Wall cladding | RS-CLD-FLA | 10 +2 | $546.00 | Crew app | Submitted | |
| TS-20260813-0288 | Kyle Anderton Apprentice, 1st yr | Thu 13 Aug | QJ2006 | Conveyor gallery, static line install (VAR-006-03) | CC-05 Height access & safety systems | RS-HGT-STA | 10 +2 | $338.00 | Crew app | Submitted | |
| TS-20260813-0289 | Bailey Rutherford Cladding Installer | Thu 13 Aug | QJ2006 | Shed 2 north, box gutter to the eastern valley | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260803-0290 | Dom Falzon Leading Hand | Mon 3 Aug | QJ2045 | FIFO North: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260803-0291 | Jarrah Winton Roof Plumber | Mon 3 Aug | QJ2045 | M&A Stage 3, KingKlip to the return walls | CC-03 Wall cladding | RS-CLD-KKP | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260803-0292 | Ellis Braithwaite Cladding Installer | Mon 3 Aug | QJ2045 | M&A Stage 3, capping to the parapet | CC-03 Wall cladding | RS-CLD-CAP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260803-0293 | Tom Gillard Cladding Installer | Mon 3 Aug | QJ2039 | Wash bay, roof lighting replacement (VAR-039-02) | CC-02 Roofing | RS-ROF-SKY | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260803-0294 | Reece Salvatore Sheeting Hand | Mon 3 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 +2 | $663.00 | Crew app | Approved | |
| TS-20260803-0295 | Marlon Deverell EWP Operator | Mon 3 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $767.00 | Crew app | Approved | |
| TS-20260803-0296 | Xavier Pauling Cladding Installer | Mon 3 Aug | QJ2039 | Supervision and permit to work over live plant | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260803-0297 | Heath Corrigan Labourer | Mon 3 Aug | QJ2039 | Workshop main span: strip sheeting, bays 15 to 20 | CC-02 Roofing | RS-ROF-STR | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260803-0298 | Jai Sutherland Apprentice, 3rd yr | Mon 3 Aug | QJ2039 | Workshop main span, KLIP-LOK 700 to bays 9 to 14 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $442.00 | Crew app | Approved | |
| TS-20260803-0299 | Lachlan Ferreira Cladding Installer | Mon 3 Aug | QJ2039 | Blanket insulation and safety mesh, main span | CC-02 Roofing | RS-ROF-INS | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260803-0300 | Riley Cusack Roof Plumber | Mon 3 Aug | QJ2039 | Wash bay, roof lighting replacement (VAR-039-02) | CC-02 Roofing | RS-ROF-SKY | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260803-0301 | Ned Blackwood Rope Access Tech | Mon 3 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260804-0302 | Dom Falzon Leading Hand | Tue 4 Aug | QJ2045 | FIFO North: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $640.00 | Crew app | Approved | |
| TS-20260804-0303 | Jarrah Winton Roof Plumber | Tue 4 Aug | QJ2045 | M&A Stage 3, KingKlip to the return walls | CC-03 Wall cladding | RS-CLD-KKP | 10 | $580.00 | Crew app | Approved | |
| TS-20260804-0304 | Ellis Braithwaite Cladding Installer | Tue 4 Aug | QJ2045 | M&A Stage 3, capping to the parapet | CC-03 Wall cladding | RS-CLD-CAP | 10 | $540.00 | Crew app | Approved | |
| TS-20260804-0305 | Tom Gillard Cladding Installer | Tue 4 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 | $540.00 | Crew app | Approved | |
| TS-20260804-0306 | Reece Salvatore Sheeting Hand | Tue 4 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 | $510.00 | Crew app | Approved | |
| TS-20260804-0307 | Marlon Deverell EWP Operator | Tue 4 Aug | QJ2039 | Supervision and permit to work over live plant | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $590.00 | Crew app | Approved | |
| TS-20260804-0308 | Xavier Pauling Cladding Installer | Tue 4 Aug | QJ2039 | Workshop main span: strip sheeting, bays 15 to 20 | CC-02 Roofing | RS-ROF-STR | 10 | $540.00 | Crew app | Approved | |
| TS-20260804-0309 | Heath Corrigan Labourer | Tue 4 Aug | QJ2039 | Workshop main span, KLIP-LOK 700 to bays 9 to 14 | CC-02 Roofing | RS-ROF-KL7 | 10 | $420.00 | Crew app | Approved | |
| TS-20260804-0310 | Jai Sutherland Apprentice, 3rd yr | Tue 4 Aug | QJ2039 | Blanket insulation and safety mesh, main span | CC-02 Roofing | RS-ROF-INS | 10 | $340.00 | Crew app | Approved | |
| TS-20260804-0311 | Lachlan Ferreira Cladding Installer | Tue 4 Aug | QJ2039 | Wash bay, roof lighting replacement (VAR-039-02) | CC-02 Roofing | RS-ROF-SKY | 10 | $540.00 | Crew app | Approved | |
| TS-20260804-0312 | Riley Cusack Roof Plumber | Tue 4 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 | $580.00 | Crew app | Approved | |
| TS-20260804-0313 | Ned Blackwood Rope Access Tech | Tue 4 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 | $690.00 | Crew app | Approved | |
| TS-20260805-0314 | Dom Falzon Leading Hand | Wed 5 Aug | QJ2045 | FIFO North: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260805-0315 | Jarrah Winton Roof Plumber | Wed 5 Aug | QJ2045 | M&A Stage 3, KingKlip to the return walls | CC-03 Wall cladding | RS-CLD-KKP | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260805-0316 | Ellis Braithwaite Cladding Installer | Wed 5 Aug | QJ2045 | M&A Stage 3, capping to the parapet | CC-03 Wall cladding | RS-CLD-CAP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260805-0317 | Tom Gillard Cladding Installer | Wed 5 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260805-0318 | Reece Salvatore Sheeting Hand | Wed 5 Aug | QJ2039 | Supervision and permit to work over live plant | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $663.00 | Crew app | Approved | |
| TS-20260805-0319 | Marlon Deverell EWP Operator | Wed 5 Aug | QJ2039 | Workshop main span: strip sheeting, bays 15 to 20 | CC-02 Roofing | RS-ROF-STR | 10 +2 | $767.00 | Crew app | Approved | |
| TS-20260805-0320 | Xavier Pauling Cladding Installer | Wed 5 Aug | QJ2039 | Workshop main span, KLIP-LOK 700 to bays 9 to 14 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260805-0321 | Heath Corrigan Labourer | Wed 5 Aug | QJ2039 | Blanket insulation and safety mesh, main span | CC-02 Roofing | RS-ROF-INS | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260805-0322 | Jai Sutherland Apprentice, 3rd yr | Wed 5 Aug | QJ2039 | Wash bay, roof lighting replacement (VAR-039-02) | CC-02 Roofing | RS-ROF-SKY | 10 +2 | $442.00 | Crew app | Approved | |
| TS-20260805-0323 | Lachlan Ferreira Cladding Installer | Wed 5 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260805-0324 | Riley Cusack Roof Plumber | Wed 5 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260805-0325 | Ned Blackwood Rope Access Tech | Wed 5 Aug | QJ2046 | Downer Maryborough, shed 4 leak investigation | CC-06 Weatherproofing | RS-WPF-LEK | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260806-0326 | Dom Falzon Leading Hand | Thu 6 Aug | QJ2039 | FIFO North: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $640.00 | Crew app | Approved | |
| TS-20260806-0327 | Jarrah Winton Roof Plumber | Thu 6 Aug | QJ2045 | M&A Stage 3, KingKlip to the return walls | CC-03 Wall cladding | RS-CLD-KKP | 10 | $580.00 | Crew app | Approved | |
| TS-20260806-0328 | Ellis Braithwaite Cladding Installer | Thu 6 Aug | QJ2045 | M&A Stage 3, capping to the parapet | CC-03 Wall cladding | RS-CLD-CAP | 10 | $540.00 | Crew app | Approved | |
| TS-20260806-0329 | Tom Gillard Cladding Installer | Thu 6 Aug | QJ2039 | Supervision and permit to work over live plant | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $540.00 | Crew app | Approved | |
| TS-20260806-0330 | Reece Salvatore Sheeting Hand | Thu 6 Aug | QJ2039 | Workshop main span: strip sheeting, bays 15 to 20 | CC-02 Roofing | RS-ROF-STR | 10 | $510.00 | Crew app | Approved | |
| TS-20260806-0331 | Marlon Deverell EWP Operator | Thu 6 Aug | QJ2039 | Workshop main span, KLIP-LOK 700 to bays 9 to 14 | CC-02 Roofing | RS-ROF-KL7 | 10 | $590.00 | Crew app | Approved | |
| TS-20260806-0332 | Xavier Pauling Cladding Installer | Thu 6 Aug | QJ2039 | Blanket insulation and safety mesh, main span | CC-02 Roofing | RS-ROF-INS | 10 | $540.00 | Crew app | Approved | |
| TS-20260806-0333 | Heath Corrigan Labourer | Thu 6 Aug | QJ2039 | Wash bay, roof lighting replacement (VAR-039-02) | CC-02 Roofing | RS-ROF-SKY | 10 | $420.00 | Crew app | Approved | |
| TS-20260806-0334 | Jai Sutherland Apprentice, 3rd yr | Thu 6 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 | $340.00 | Crew app | Approved | |
| TS-20260806-0335 | Lachlan Ferreira Cladding Installer | Thu 6 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 | $540.00 | Crew app | Approved | |
| TS-20260806-0336 | Riley Cusack Roof Plumber | Thu 6 Aug | QJ2039 | Supervision and permit to work over live plant | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $580.00 | Crew app | Approved | |
| TS-20260806-0337 | Ned Blackwood Rope Access Tech | Thu 6 Aug | QJ2046 | Downer Maryborough, shed 4 leak investigation | CC-06 Weatherproofing | RS-WPF-LEK | 10 | $690.00 | Crew app | Approved | |
| TS-20260807-0338 | Dom Falzon Leading Hand | Fri 7 Aug | QJ2039 | FIFO North: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260807-0339 | Jarrah Winton Roof Plumber | Fri 7 Aug | QJ2045 | M&A Stage 3, KingKlip to the return walls | CC-03 Wall cladding | RS-CLD-KKP | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260807-0340 | Ellis Braithwaite Cladding Installer | Fri 7 Aug | QJ2045 | M&A Stage 3, capping to the parapet | CC-03 Wall cladding | RS-CLD-CAP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260807-0341 | Tom Gillard Cladding Installer | Fri 7 Aug | QJ2039 | Workshop main span: strip sheeting, bays 15 to 20 | CC-02 Roofing | RS-ROF-STR | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260807-0342 | Reece Salvatore Sheeting Hand | Fri 7 Aug | QJ2039 | Workshop main span, KLIP-LOK 700 to bays 9 to 14 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $663.00 | Crew app | Approved | |
| TS-20260807-0343 | Marlon Deverell EWP Operator | Fri 7 Aug | QJ2039 | Blanket insulation and safety mesh, main span | CC-02 Roofing | RS-ROF-INS | 10 +2 | $767.00 | Crew app | Approved | |
| TS-20260807-0344 | Xavier Pauling Cladding Installer | Fri 7 Aug | QJ2039 | Wash bay, roof lighting replacement (VAR-039-02) | CC-02 Roofing | RS-ROF-SKY | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260807-0345 | Heath Corrigan Labourer | Fri 7 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260807-0346 | Jai Sutherland Apprentice, 3rd yr | Fri 7 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $442.00 | Crew app | Approved | |
| TS-20260807-0347 | Lachlan Ferreira Cladding Installer | Fri 7 Aug | QJ2039 | Supervision and permit to work over live plant | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260807-0348 | Riley Cusack Roof Plumber | Fri 7 Aug | QJ2039 | Workshop main span: strip sheeting, bays 15 to 20 | CC-02 Roofing | RS-ROF-STR | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260807-0349 | Ned Blackwood Rope Access Tech | Fri 7 Aug | QJ2046 | Downer Maryborough, shed 4 leak investigation | CC-06 Weatherproofing | RS-WPF-LEK | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260810-0350 | Dom Falzon Leading Hand | Mon 10 Aug | QJ2045 | FIFO North: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Approved | |
| TS-20260810-0351 | Jarrah Winton Roof Plumber | Mon 10 Aug | QJ2045 | M&A Stage 3, KingKlip to the return walls | CC-03 Wall cladding | RS-CLD-KKP | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260810-0352 | Ellis Braithwaite Cladding Installer | Mon 10 Aug | QJ2045 | M&A Stage 3, capping to the parapet | CC-03 Wall cladding | RS-CLD-CAP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260810-0353 | Tom Gillard Cladding Installer | Mon 10 Aug | QJ2039 | Wash bay, roof lighting replacement (VAR-039-02) | CC-02 Roofing | RS-ROF-SKY | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260810-0354 | Reece Salvatore Sheeting Hand | Mon 10 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 +2 | $663.00 | Crew app | Approved | |
| TS-20260810-0355 | Marlon Deverell EWP Operator | Mon 10 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $767.00 | Crew app | Approved | |
| TS-20260810-0356 | Xavier Pauling Cladding Installer | Mon 10 Aug | QJ2039 | Supervision and permit to work over live plant | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260810-0357 | Heath Corrigan Labourer | Mon 10 Aug | QJ2039 | Workshop main span: strip sheeting, bays 15 to 20 | CC-02 Roofing | RS-ROF-STR | 10 +2 | $546.00 | Crew app | Approved | |
| TS-20260810-0358 | Jai Sutherland Apprentice, 3rd yr | Mon 10 Aug | QJ2039 | Workshop main span, KLIP-LOK 700 to bays 9 to 14 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $442.00 | Crew app | Approved | |
| TS-20260810-0359 | Lachlan Ferreira Cladding Installer | Mon 10 Aug | QJ2039 | Blanket insulation and safety mesh, main span | CC-02 Roofing | RS-ROF-INS | 10 +2 | $702.00 | Crew app | Approved | |
| TS-20260810-0360 | Riley Cusack Roof Plumber | Mon 10 Aug | QJ2039 | Wash bay, roof lighting replacement (VAR-039-02) | CC-02 Roofing | RS-ROF-SKY | 10 +2 | $754.00 | Crew app | Approved | |
| TS-20260810-0361 | Ned Blackwood Rope Access Tech | Mon 10 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 +2 | $897.00 | Crew app | Approved | |
| TS-20260811-0362 | Dom Falzon Leading Hand | Tue 11 Aug | QJ2045 | FIFO North: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $640.00 | Crew app | Approved | |
| TS-20260811-0363 | Jarrah Winton Roof Plumber | Tue 11 Aug | QJ2045 | M&A Stage 3, KingKlip to the return walls | CC-03 Wall cladding | RS-CLD-KKP | 10 | $580.00 | Crew app | Approved | |
| TS-20260811-0364 | Ellis Braithwaite Cladding Installer | Tue 11 Aug | QJ2045 | M&A Stage 3, capping to the parapet | CC-03 Wall cladding | RS-CLD-CAP | 10 | $540.00 | Crew app | Approved | |
| TS-20260811-0365 | Tom Gillard Cladding Installer | Tue 11 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 | $540.00 | Crew app | Approved | |
| TS-20260811-0366 | Reece Salvatore Sheeting Hand | Tue 11 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 | $510.00 | Crew app | Approved | |
| TS-20260811-0367 | Marlon Deverell EWP Operator | Tue 11 Aug | QJ2039 | Supervision and permit to work over live plant | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $590.00 | Crew app | Approved | |
| TS-20260811-0368 | Xavier Pauling Cladding Installer | Tue 11 Aug | QJ2039 | Workshop main span: strip sheeting, bays 15 to 20 | CC-02 Roofing | RS-ROF-STR | 10 | $540.00 | Crew app | Approved | |
| TS-20260811-0369 | Heath Corrigan Labourer | Tue 11 Aug | QJ2039 | Workshop main span, KLIP-LOK 700 to bays 9 to 14 | CC-02 Roofing | RS-ROF-KL7 | 10 | $420.00 | Crew app | Approved | |
| TS-20260811-0370 | Jai Sutherland Apprentice, 3rd yr | Tue 11 Aug | QJ2039 | Blanket insulation and safety mesh, main span | CC-02 Roofing | RS-ROF-INS | 10 | $340.00 | Crew app | Approved | |
| TS-20260811-0371 | Lachlan Ferreira Cladding Installer | Tue 11 Aug | QJ2039 | Wash bay, roof lighting replacement (VAR-039-02) | CC-02 Roofing | RS-ROF-SKY | 10 | $540.00 | Crew app | Approved | |
| TS-20260811-0372 | Riley Cusack Roof Plumber | Tue 11 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 | $580.00 | Crew app | Approved | |
| TS-20260811-0373 | Ned Blackwood Rope Access Tech | Tue 11 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 | $690.00 | Crew app | Approved | |
| TS-20260812-0374 | Dom Falzon Leading Hand | Wed 12 Aug | QJ2045 | FIFO North: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $832.00 | Crew app | Submitted | |
| TS-20260812-0375 | Jarrah Winton Roof Plumber | Wed 12 Aug | QJ2045 | M&A Stage 3, KingKlip to the return walls | CC-03 Wall cladding | RS-CLD-KKP | 10 +2 | $754.00 | Crew app | Submitted | |
| TS-20260812-0376 | Ellis Braithwaite Cladding Installer | Wed 12 Aug | QJ2045 | M&A Stage 3, capping to the parapet | CC-03 Wall cladding | RS-CLD-CAP | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260812-0377 | Tom Gillard Cladding Installer | Wed 12 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260812-0378 | Reece Salvatore Sheeting Hand | Wed 12 Aug | QJ2039 | Supervision and permit to work over live plant | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 +2 | $663.00 | Crew app | Submitted | |
| TS-20260812-0379 | Marlon Deverell EWP Operator | Wed 12 Aug | QJ2039 | Workshop main span: strip sheeting, bays 15 to 20 | CC-02 Roofing | RS-ROF-STR | 10 +2 | $767.00 | Crew app | Submitted | |
| TS-20260812-0380 | Xavier Pauling Cladding Installer | Wed 12 Aug | QJ2039 | Workshop main span, KLIP-LOK 700 to bays 9 to 14 | CC-02 Roofing | RS-ROF-KL7 | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260812-0381 | Heath Corrigan Labourer | Wed 12 Aug | QJ2039 | Blanket insulation and safety mesh, main span | CC-02 Roofing | RS-ROF-INS | 10 +2 | $546.00 | Crew app | Submitted | |
| TS-20260812-0382 | Jai Sutherland Apprentice, 3rd yr | Wed 12 Aug | QJ2039 | Wash bay, roof lighting replacement (VAR-039-02) | CC-02 Roofing | RS-ROF-SKY | 10 +2 | $442.00 | Crew app | Submitted | |
| TS-20260812-0383 | Lachlan Ferreira Cladding Installer | Wed 12 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 +2 | $702.00 | Crew app | Submitted | |
| TS-20260812-0384 | Riley Cusack Roof Plumber | Wed 12 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 +2 | $754.00 | Crew app | Submitted | |
| TS-20260812-0385 | Ned Blackwood Rope Access Tech | Wed 12 Aug | QJ2046 | Downer Maryborough, shed 4 leak investigation | CC-06 Weatherproofing | RS-WPF-LEK | 10 +2 | $897.00 | Crew app | Submitted | |
| TS-20260813-0386 | Dom Falzon Leading Hand | Thu 13 Aug | QJ2039 | FIFO North: supervision, crew of 12 | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $640.00 | Crew app | Submitted | |
| TS-20260813-0387 | Jarrah Winton Roof Plumber | Thu 13 Aug | QJ2045 | M&A Stage 3, KingKlip to the return walls | CC-03 Wall cladding | RS-CLD-KKP | 10 | $580.00 | Crew app | Submitted | |
| TS-20260813-0388 | Ellis Braithwaite Cladding Installer | Thu 13 Aug | QJ2045 | M&A Stage 3, capping to the parapet | CC-03 Wall cladding | RS-CLD-CAP | 10 | $540.00 | Crew app | Submitted | |
| TS-20260813-0389 | Tom Gillard Cladding Installer | Thu 13 Aug | QJ2039 | Supervision and permit to work over live plant | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $540.00 | Crew app | Submitted | |
| TS-20260813-0390 | Reece Salvatore Sheeting Hand | Thu 13 Aug | QJ2039 | Workshop main span: strip sheeting, bays 15 to 20 | CC-02 Roofing | RS-ROF-STR | 10 | $510.00 | Crew app | Submitted | |
| TS-20260813-0391 | Marlon Deverell EWP Operator | Thu 13 Aug | QJ2039 | Workshop main span, KLIP-LOK 700 to bays 9 to 14 | CC-02 Roofing | RS-ROF-KL7 | 10 | $590.00 | Crew app | Submitted | |
| TS-20260813-0392 | Xavier Pauling Cladding Installer | Thu 13 Aug | QJ2039 | Blanket insulation and safety mesh, main span | CC-02 Roofing | RS-ROF-INS | 10 | $540.00 | Crew app | Submitted | |
| TS-20260813-0393 | Heath Corrigan Labourer | Thu 13 Aug | QJ2039 | Wash bay, roof lighting replacement (VAR-039-02) | CC-02 Roofing | RS-ROF-SKY | 10 | $420.00 | Crew app | Submitted | |
| TS-20260813-0394 | Jai Sutherland Apprentice, 3rd yr | Thu 13 Aug | QJ2039 | Store annexe, CUSTOM ORB to the western wall | CC-03 Wall cladding | RS-CLD-CUS | 10 | $340.00 | Crew app | Submitted | |
| TS-20260813-0395 | Lachlan Ferreira Cladding Installer | Thu 13 Aug | QJ2039 | Store annexe, box gutter and downpipes | CC-02 Roofing | RS-ROF-GUT | 10 | $540.00 | Crew app | Submitted | |
| TS-20260813-0396 | Riley Cusack Roof Plumber | Thu 13 Aug | QJ2039 | Supervision and permit to work over live plant | CC-01 Preliminaries & establishment | RS-PRE-SUP | 10 | $580.00 | Crew app | Submitted | |
| TS-20260813-0397 | Ned Blackwood Rope Access Tech | Thu 13 Aug | QJ2046 | Downer Maryborough, shed 4 leak investigation | CC-06 Weatherproofing | RS-WPF-LEK | 10 | $690.00 | Crew app | Submitted | |
| TS-20260803-0398 | Marcus Deng Project Manager | Mon 3 Aug | QJ2006 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260804-0399 | Marcus Deng Project Manager | Tue 4 Aug | QJ2006 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260805-0400 | Marcus Deng Project Manager | Wed 5 Aug | QJ2006 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260806-0401 | Marcus Deng Project Manager | Thu 6 Aug | QJ2006 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260807-0402 | Marcus Deng Project Manager | Fri 7 Aug | QJ2006 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260810-0403 | Marcus Deng Project Manager | Mon 10 Aug | QJ2006 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260811-0404 | Marcus Deng Project Manager | Tue 11 Aug | QJ2006 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260812-0405 | Marcus Deng Project Manager | Wed 12 Aug | QJ2006 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260813-0406 | Marcus Deng Project Manager | Thu 13 Aug | QJ2006 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Submitted | |
| TS-20260803-0407 | Cameron Hale Project Manager | Mon 3 Aug | QJ2044 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260804-0408 | Cameron Hale Project Manager | Tue 4 Aug | QJ2044 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260805-0409 | Cameron Hale Project Manager | Wed 5 Aug | QJ2044 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260806-0410 | Cameron Hale Project Manager | Thu 6 Aug | QJ2044 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260807-0411 | Cameron Hale Project Manager | Fri 7 Aug | QJ2044 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260810-0412 | Cameron Hale Project Manager | Mon 10 Aug | QJ2044 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260811-0413 | Cameron Hale Project Manager | Tue 11 Aug | QJ2044 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260812-0414 | Cameron Hale Project Manager | Wed 12 Aug | QJ2044 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Approved | |
| TS-20260813-0415 | Cameron Hale Project Manager | Thu 13 Aug | QJ2044 | Project management: client meetings, programme and claims | CC-01 Preliminaries & establishment | RS-PRE-SUP | 8 | $832.00 | Office | Submitted |