Variation 1, Heritage flashing detail to the pavilion parapet
RNA Showgrounds: Pavilion Roof Renewal Stage 4 · ADCO Constructions · their reference ADC-VO-1120
Raised 16 Oct 2023 by Cameron Doyle · approved 2 Nov 2023 by Nadia Petkovic
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-CLD-FLA Custom flashings, supply and install | $114.00/lm | 168 | $19,152.00 | $15,540.00 | 19% |
| RS-CLD-CAP Corner & parapet capping, supply and install | $138.00/lm | 92 | $12,696.00 | $10,159.56 | 20% |
| Total, ex GST | $31,848.00 | $25,699.56 | 19% | ||
| GST | $3,184.80 | ||||
| Total, inc GST | $35,032.80 | ||||
Why it was raised
Heritage architect required a bespoke folded detail.
Position
- Value, ex GST
- $31,848.00
- Cost to deliver
- $25,699.56
- Margin
- 19.3%
- Physically built
- 100%
- Value already on the ground
- $31,848.00
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2024-018
- Contract no.
- ADC-RNA-S4-2023-4419
- Head contractor
- ADCO Constructions
- Approver
- Nadia Petkovic
- Payment terms
- BIF 15/25
Trail
- Raised 16 Oct 2023 by Cameron DoylePriced off the project schedule of rates
- Lodged with ADCO ConstructionsTheir reference ADC-VO-1120
- Approved 2 Nov 2023Nadia Petkovic · added to the contract sum and the open claim