Clermont Coal: CHPP Conveyor Sheeting
BHP Mitsubishi Alliance · Clermont, QLD · contract BMA-CLM-CHPP-2023-6602
Marcus Deng · 10 Oct 2023 → 24 Feb 2024 · PC 8 Mar 2024 · DLP ends 8 Mar 2025
The position
Every figure below is the sum of rows on this page.
Contract sum
$794,942
- Tendered
- $767,542
- Approved variations
- +$27,400
Work in place
$794,942
- Complete
- 100.0%
- Still to run
- $0
Claimed & certified
$794,942
- Certified
- $75,519
- Unclaimed WIP
- $0
- Retention held
- $0
Margin
$150,709 19.0%
- Cost of work in place
- $644,233
- Against the build-up
- -$10,600
- Committed, not received
- $0
Cost centres
Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.
| Cost centre | Value | Earned | % | Budget hrs | Actual hrs | Budget material | Actual material | Committed | Run | Margin |
|---|---|---|---|---|---|---|---|---|---|---|
| CC-01 Preliminaries & establishment 4 tasks · General | $117,754 | $117,754 | 100% | 902 | 874.3 | $0 | -$393 | - | -$3,002 | 20% |
| CC-02 Roofing 1 task · General | $144,744 | $144,744 | 100% | 444 | 438.4 | $58,120 | $57,403 | - | -$1,247 | 17% |
| CC-03 Wall cladding 2 tasks · General | $245,760 | $245,760 | 100% | 720 | 708.6 | $99,480 | $97,945 | - | -$2,610 | 18% |
| CC-05 Height access & safety systems 1 task · General | $76,960 | $76,960 | 100% | 520 | 516 | $0 | -$88 | - | -$464 | 22% |
| CC-06 Weatherproofing 2 tasks · General | $48,024 | $48,024 | 100% | 276 | 271.2 | $2,705 | $2,621 | - | -$538 | 22% |
| CC-08 Direct labour & plant 1 task · General | $161,700 | $161,700 | 100% | 0 | 0 | $0 | -$2,739 | - | -$2,739 | 19% |
| Job total | $794,942 | $794,942 | 100% | 2,862 | 2,808.5 | $160,304 | $154,749 | $0 | -$10,600 | 19% |
The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $644,233, which is the job's actual cost.
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| Site supervision, leading hand RS-PRE-SUP | General | 68 day | 68 | 100% | $84,864 | $84,864 | 714 of 714 |
| Mobilisation & site establishment RS-PRE-MOB | General | 1 item | 1 | 100% | $18,450 | $18,450 | 96 of 96 |
| Demobilisation & make good RS-PRE-DEM | General | 1 item | 1 | 100% | $7,420 | $7,420 | 44 of 44 |
| Site induction & verification of competency RS-PRE-IND | General | 12 ea | 12 | 100% | $7,020 | $7,020 | 48 of 48 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| TRIMDEK roof sheeting, install RS-ROF-TRM | General | 1,480 m² | 1,480 | 100% | $144,744 | $144,744 | 444 of 444 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| CUSTOM ORB wall cladding, install RS-CLD-CUS | General | 2,180 m² | 2,180 | 100% | $223,232 | $223,232 | 654 of 654 |
| CUSTOM ORB wall cladding, install RS-CLD-CUS · VAR-021-01 | General | 220 m² | 220 | 100% | $22,528 | $22,528 | 66 of 66 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| Rope access technician, IRATA RS-HGT-ROP | General | 52 day | 52 | 100% | $76,960 | $76,960 | 520 of 520 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| Sealant to laps, penetrations & flashings RS-WPF-SEA | General | 1,240 lm | 1,240 | 100% | $43,152 | $43,152 | 248 of 248 |
| Sealant to laps, penetrations & flashings RS-WPF-SEA · VAR-021-01 | General | 140 lm | 140 | 100% | $4,872 | $4,872 | 28 of 28 |
| Task | Sub-job | Contract | Done | % | Value | Earned | Hours |
|---|---|---|---|---|---|---|---|
| Travel & living away: per person, per day RS-LAB-TRV | General | 420 day | 420 | 100% | $161,700 | $161,700 | 0 of 0 |
Schedule of rates
Contract quantity, measured to date, and what each line is worth. Lines added by a variation carry its number.
| Rate | Rate, ex GST | Qty | Measured | Contract value | In place | Cost of it | Margin |
|---|---|---|---|---|---|---|---|
| Preliminaries | |||||||
| RS-PRE-MOB Mobilisation & site establishment | $18,450.00/item | 1 | 1 100% | $18,450 | $18,450 | $15,224 | 17% |
| RS-PRE-IND Site induction & verification of competency | $585.00/ea | 12 | 12 100% | $7,020 | $7,020 | $5,652 | 19% |
| RS-PRE-SUP Site supervision, leading hand | $1,248.00/day | 68 | 68 100% | $84,864 | $84,864 | $70,380 | 17% |
| RS-PRE-DEM Demobilisation & make good | $7,420.00/item | 1 | 1 100% | $7,420 | $7,420 | $6,316 | 15% |
| Labour & plant | |||||||
| RS-LAB-TRV Travel & living away: per person, per day | $385.00/day | 420 | 420 100% | $161,700 | $161,700 | $133,560 | 17% |
| Wall cladding | |||||||
| RS-CLD-CUS CUSTOM ORB wall cladding, install | $102.40/m² | 2,180 | 2,180 100% | $223,232 | $223,232 | $184,973 | 17% |
| RS-CLD-CUS CUSTOM ORB wall cladding, install · VAR-021-01 | $102.40/m² | 220 | 220 100% | $22,528 | $22,528 | $18,667 | 17% |
| Roofing | |||||||
| RS-ROF-TRM TRIMDEK roof sheeting, install | $97.80/m² | 1,480 | 1,480 100% | $144,744 | $144,744 | $121,612 | 16% |
| Height access | |||||||
| RS-HGT-ROP Rope access technician, IRATA | $1,480.00/day | 52 | 52 100% | $76,960 | $76,960 | $60,320 | 22% |
| Weatherproofing | |||||||
| RS-WPF-SEA Sealant to laps, penetrations & flashings | $34.80/lm | 1,240 | 1,240 100% | $43,152 | $43,152 | $34,261 | 21% |
| RS-WPF-SEA Sealant to laps, penetrations & flashings · VAR-021-01 | $34.80/lm | 140 | 140 100% | $4,872 | $4,872 | $3,868 | 21% |
| Total | $794,942 | $794,942 | $654,833 | 18% | |||
Variations
An approved variation's lines join the schedule of rates above on approval.
| No. | Variation | Raised | Their ref | Value, ex GST | Built | Status |
|---|---|---|---|---|---|---|
| 1 | VAR-021-01 Conveyor cover extension, 40 lm | 12 Dec 2023 | BMA-VO-1802 | $27,400.00 | 100% | Approved |
Progress claims
Lodged under the QLD BIF Act: 15 business days to a payment schedule, 25 to payment. Retention at 5%.
| Claim | Period | This claim, ex GST | Retention | Inc GST | Lodged | Invoice | Status |
|---|---|---|---|---|---|---|---|
| PC-2024-0074No. 1 | Apr 2024 | $75,519.49 | $3,775.97 | $78,917.87 | 17 Mar 2024 | INV-24-0201 | Paid |
Invoices
| Invoice | Issued | Due | Inc GST | Ledger | Status |
|---|---|---|---|---|---|
| INV-24-0201 | 2 Apr 2024 | 19 Apr 2024 | $78,917.87 | XRO-4141 | Paid |
Labour booked this week
0 hours, $0.00 of cost, off the crew app. 2,940 hours on this job to date.
| Day card | Person | Date | Task | Rate | Hours | Cost | Status |
|---|---|---|---|---|---|---|---|
| No hours booked to this job this week. | |||||||
Purchase orders
$0.00 committed and not yet received.
| PO | Supplier | Deliver to | Raised | Expected | Ex GST | Status |
|---|---|---|---|---|---|---|
| Nothing ordered against this job. | ||||||
Nothing recorded against this job yet.
Correspondence
RFIs, material approvals and anything else sent about QJ1821, with the replies on the same thread.
Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.