QJ1821 Demo Clermont Coal: CHPP Conveyor Sheeting
Accounting connected Thu 13 Aug 2026
QJ1821 Complete Mining & Resources

Clermont Coal: CHPP Conveyor Sheeting

BHP Mitsubishi Alliance · Clermont, QLD · contract BMA-CLM-CHPP-2023-6602

Marcus Deng · 10 Oct 2023 → 24 Feb 2024 · PC 8 Mar 2024 · DLP ends 8 Mar 2025

Client view

The position

Every figure below is the sum of rows on this page.

Contract sum

$794,942

Tendered
$767,542
Approved variations
+$27,400

Work in place

$794,942

Complete
100.0%
Still to run
$0

Claimed & certified

$794,942

Certified
$75,519
Unclaimed WIP
$0
Retention held
$0

Margin

$150,709 19.0%

Cost of work in place
$644,233
Against the build-up
-$10,600
Committed, not received
$0

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 4 tasks · General $117,754 $117,754 100% 902 874.3 $0 -$393 - -$3,002 20%
CC-02 Roofing 1 task · General $144,744 $144,744 100% 444 438.4 $58,120 $57,403 - -$1,247 17%
CC-03 Wall cladding 2 tasks · General $245,760 $245,760 100% 720 708.6 $99,480 $97,945 - -$2,610 18%
CC-05 Height access & safety systems 1 task · General $76,960 $76,960 100% 520 516 $0 -$88 - -$464 22%
CC-06 Weatherproofing 2 tasks · General $48,024 $48,024 100% 276 271.2 $2,705 $2,621 - -$538 22%
CC-08 Direct labour & plant 1 task · General $161,700 $161,700 100% 0 0 $0 -$2,739 - -$2,739 19%
Job total $794,942 $794,942 100% 2,862 2,808.5 $160,304 $154,749 $0 -$10,600 19%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $644,233, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$117,754 of $117,754 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Site supervision, leading hand RS-PRE-SUP General 68 day 68 100% $84,864 $84,864 714 of 714
Mobilisation & site establishment RS-PRE-MOB General 1 item 1 100% $18,450 $18,450 96 of 96
Demobilisation & make good RS-PRE-DEM General 1 item 1 100% $7,420 $7,420 44 of 44
Site induction & verification of competency RS-PRE-IND General 12 ea 12 100% $7,020 $7,020 48 of 48
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$144,744 of $144,744 · 100%
TaskSub-jobContractDone%ValueEarnedHours
TRIMDEK roof sheeting, install RS-ROF-TRM General 1,480 m² 1,480 100% $144,744 $144,744 444 of 444
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$245,760 of $245,760 · 100%
TaskSub-jobContractDone%ValueEarnedHours
CUSTOM ORB wall cladding, install RS-CLD-CUS General 2,180 m² 2,180 100% $223,232 $223,232 654 of 654
CUSTOM ORB wall cladding, install RS-CLD-CUS · VAR-021-01 General 220 m² 220 100% $22,528 $22,528 66 of 66
CC-05 Height access & safety systems Anchor points, static lines, guardrail, rope access and elevated work platforms.
$76,960 of $76,960 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Rope access technician, IRATA RS-HGT-ROP General 52 day 52 100% $76,960 $76,960 520 of 520
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$48,024 of $48,024 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Sealant to laps, penetrations & flashings RS-WPF-SEA General 1,240 lm 1,240 100% $43,152 $43,152 248 of 248
Sealant to laps, penetrations & flashings RS-WPF-SEA · VAR-021-01 General 140 lm 140 100% $4,872 $4,872 28 of 28
CC-08 Direct labour & plant Dayworks, overtime and travel time charged at the labour rate.
$161,700 of $161,700 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Travel & living away: per person, per day RS-LAB-TRV General 420 day 420 100% $161,700 $161,700 0 of 0

Correspondence

RFIs, material approvals and anything else sent about QJ1821, with the replies on the same thread.

Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.