QJ1939 Demo McNab: Yatala Cold Store Insulated Panel
Accounting connected Thu 13 Aug 2026
QJ1939 Practical completion Industrial

McNab: Yatala Cold Store Insulated Panel

McNab Constructions · Yatala, QLD · contract MCN-YAT-CS-2025-2214

Cameron Hale · 11 Nov 2025 → 6 Jun 2026 · PC 20 Jun 2026 · DLP ends 20 Jun 2027

Client view

The position

Every figure below is the sum of rows on this page.

Contract sum

$1,993,066

Tendered
$1,908,142
Approved variations
+$84,924

Work in place

$1,993,066

Complete
100.0%
Still to run
$0

Claimed & certified

$1,993,066

Certified
$175,390
Unclaimed WIP
$0
Retention held
$4,385

Margin

$419,150 21.0%

Cost of work in place
$1,573,916
Against the build-up
-$14,200
Committed, not received
$0

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 3 tasks · General $145,678 $145,678 100% 1,148 1,124.2 $0 -$270 - -$2,509 19%
CC-02 Roofing 1 task · General $536,280 $536,280 100% 1,351.6 1,340 $224,911 $223,084 - -$2,917 22%
CC-03 Wall cladding 5 tasks · General $1,079,812 $1,079,812 100% 2,785.2 2,755.3 $455,153 $450,518 - -$7,441 21%
CC-05 Height access & safety systems 1 task · General $122,720 $122,720 100% 520 517.3 $0 -$259 - -$513 20%
CC-06 Weatherproofing 2 tasks · General $108,576 $108,576 100% 624 616.6 $6,115 $5,987 - -$820 21%
Job total $1,993,066 $1,993,066 100% 6,428.8 6,353.4 $686,178 $679,060 $0 -$14,200 21%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $1,573,916, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$145,678 of $145,678 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Site supervision, leading hand RS-PRE-SUP General 96 day 96 100% $119,808 $119,808 1,008 of 1,008
Mobilisation & site establishment RS-PRE-MOB General 1 item 1 100% $18,450 $18,450 96 of 96
Demobilisation & make good RS-PRE-DEM General 1 item 1 100% $7,420 $7,420 44 of 44
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$536,280 of $536,280 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Bondor EquiDeck insulated roof panel, install RS-ROF-EQD General 2,180 m² 2,180 100% $536,280 $536,280 1,351.6 of 1,351.6
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$1,079,812 of $1,079,812 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Kingspan KS1000 RW insulated panel, install RS-CLD-KSP General 3,240 m² 3,240 100% $900,720 $900,720 2,268 of 2,268
Custom flashings, supply and install RS-CLD-FLA General 860 lm 860 100% $98,040 $98,040 292.4 of 292.4
Kingspan KS1000 RW insulated panel, install RS-CLD-KSP · VAR-939-02 General 186 m² 186 100% $51,708 $51,708 130.2 of 130.2
Personnel access door in cladding, form and trim RS-CLD-DOR General 10 ea 10 100% $18,400 $18,400 62 of 62
Custom flashings, supply and install RS-CLD-FLA · VAR-939-01 General 96 lm 96 100% $10,944 $10,944 32.6 of 32.6
CC-05 Height access & safety systems Anchor points, static lines, guardrail, rope access and elevated work platforms.
$122,720 of $122,720 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Spider lift hire & operator, 28m RS-HGT-SPI General 52 day 52 100% $122,720 $122,720 520 of 520
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$108,576 of $108,576 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Sealant to laps, penetrations & flashings RS-WPF-SEA General 2,480 lm 2,480 100% $86,304 $86,304 496 of 496
Sealant to laps, penetrations & flashings RS-WPF-SEA · VAR-939-01 General 640 lm 640 100% $22,272 $22,272 128 of 128

Correspondence

RFIs, material approvals and anything else sent about QJ1939, with the replies on the same thread.

Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.