Variation 1, Finesse set-out change to the northern elevation
M&A Apartments Stage 3: Facade Cladding · M&A Developments · their reference MAA-VO-0031
Raised 17 Jun 2026 by Cameron Doyle · approved 1 Jul 2026 by Jordan Ellul
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-CLD-FIN Fielders Finesse architectural cladding, install | $229.00/m² | 96 | $21,984.00 | $17,914.56 | 19% |
| RS-CLD-CAP Corner & parapet capping, supply and install | $138.00/lm | 38 | $5,244.00 | $4,196.34 | 20% |
| Total, ex GST | $27,228.00 | $22,110.90 | 19% | ||
| GST | $2,722.80 | ||||
| Total, inc GST | $29,950.80 | ||||
Why it was raised
Architect revised the panel module after the shop drawings were approved; sheets recut.
The recut is why this job is running $26k over, the original sheets could not be reused.
Position
- Value, ex GST
- $27,228.00
- Cost to deliver
- $22,110.90
- Margin
- 18.8%
- Physically built
- 86%
- Value already on the ground
- $23,416.08
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2026-045
- Contract no.
- MAA-S3-CL-2026-0088
- Head contractor
- M&A Developments
- Approver
- Jordan Ellul
- Payment terms
- 30 days
Trail
- Raised 17 Jun 2026 by Cameron DoylePriced off the project schedule of rates
- Lodged with M&A DevelopmentsTheir reference MAA-VO-0031
- Approved 1 Jul 2026Jordan Ellul · added to the contract sum and the open claim