QJ2006 Demo PROJECT CERES - UREA SHEDS
Accounting connected Thu 13 Aug 2026
QJ2006 On site Energy P6 CER-ST-4400 21/7 · 14 crew · 96 flights from Q31904

PROJECT CERES - UREA SHEDS

Saipem Clough Joint Venture · Ceres urea plant, Karratha, WA · contract SCJV-CER-SC-1180

Marcus Deng · Crew 3, FIFO West · 24 Feb 2026 → 3 Apr 2027

Claim PC-2026-0196 Client view

Two urea storage sheds and the linking conveyor gallery. Fly-in fly-out through Karratha on a 21 and 7. The joint venture run their own clock-on system and QClad hours are reconciled to it weekly, which is why every day card on this job carries a cost centre.

The position

Every figure below is the sum of rows on this page.

Contract sum

$7,497,478

Tendered
$7,253,190
Approved variations
+$244,288
Lodged, not approved
$75,952

Work in place

$3,367,317

Complete
44.9%
Still to run
$4,130,161

Claimed & certified

$3,023,851

Certified
$3,023,851
Unclaimed WIP
$343,466
Retention held
$151,193

Margin

$598,868 17.8%

Cost of work in place
$2,768,450
Against the build-up
+$96,400
Committed, not received
$317,032

$25,771.20 of work is on the ground against variations nobody has approved.

VAR-006-03, Conveyor gallery access platform, additional static line. Until they are approved they sit in cost with no revenue against them.

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 6 tasks · General $1,045,810 $548,840 52% 5,395.4 2,953 $0 $13,636 $7,080 +$32,994 14%
CC-02 Roofing 13 tasks · Shed 1 north, Shed 2 north, Shed 2 south, General $2,741,012 $1,278,900 47% 8,294.9 4,099.8 $450,894 $464,849 $261,886 +$25,537 18%
CC-03 Wall cladding 5 tasks · Shed 1 south, Shed 2 south, General $2,331,456 $898,795 39% 5,919.6 2,369.1 $366,125 $379,597 $204,820 +$21,775 20%
CC-05 Height access & safety systems 3 tasks · Conveyor gallery, General $608,520 $308,286 51% 2,632.8 1,326.3 $61,816 $64,010 $47,912 +$4,664 18%
CC-06 Weatherproofing 6 tasks · Shed 1 north, Shed 2 north, Conveyor gallery, General $293,280 $122,441 42% 1,437.6 641.9 $9,801 $10,431 - +$3,096 24%
CC-08 Direct labour & plant 1 task · General $477,400 $210,056 44% 0 0 $0 $8,671 - +$8,671 13%
Job total $7,497,478 $3,367,317 45% 23,680.3 11,390.1 $888,636 $941,194 $521,698 +$96,736 18%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $2,768,450, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$548,840 of $1,045,810 · 52%
TaskSub-jobContractDone%ValueEarnedHours
Site supervision, leading hand RS-PRE-SUP General 386 day 169.84 44% $481,728 $211,960 1,783.3 of 4,053
Scaffold: supply, erect, hire 8 weeks, dismantle RS-PRE-SCF General 3,640 m² 1,856.4 51% $370,552 $188,982 111.4 of 218.4
Mobilisation & site establishment RS-PRE-MOB General 6 item 6 100% $110,700 $110,700 576 of 576
Demobilisation & make good RS-PRE-DEM General 6 item 0 0% $44,520 $0 0 of 264
Site induction & verification of competency RS-PRE-IND General 38 ea 36.1 95% $22,230 $21,119 144.4 of 152
SWMS, JSA & site-specific safety plan RS-PRE-SWM General 6 item 6 100% $16,080 $16,080 132 of 132
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$1,278,900 of $2,741,012 · 47%
TaskSub-jobContractDone%ValueEarnedHours
KLIP-LOK 700 HI-STRENGTH roof sheeting, install RS-ROF-KL7 Shed 1 north 5,120 m² 2,969.6 58% $700,416 $406,241 1,069.1 of 1,843.2
KLIP-LOK 700 HI-STRENGTH roof sheeting, install RS-ROF-KL7 Shed 2 north 4,340 m² 1,388.8 32% $593,712 $189,988 500 of 1,562.4
Box gutter, supply and install RS-ROF-GUT Shed 2 north 612 lm 220.32 36% $235,620 $84,823 233.5 of 648.7
Roof insulation blanket 75mm R1.8, install RS-ROF-INS Shed 1 north 5,120 m² 2,969.6 58% $202,752 $117,596 415.7 of 716.8
Roof insulation blanket 75mm R1.8, install RS-ROF-INS Shed 2 north 4,340 m² 1,388.8 32% $171,864 $54,996 194.4 of 607.6
Ridge ventilator, supply and install RS-ROF-VNT Shed 2 south 268 lm 75.04 28% $167,232 $46,825 120.1 of 428.8
Ridge capping & barge, supply and install RS-ROF-RDG Shed 2 north 884 lm 362.44 41% $129,064 $52,916 145 of 353.6
Safety mesh, install to purlins RS-ROF-SAF Shed 1 north 5,120 m² 3,072 60% $126,976 $76,186 291.8 of 486.4
Strip existing roof sheeting & dispose RS-ROF-STR Shed 1 north 2,180 m² 1,569.6 72% $114,232 $82,247 455.2 of 632.2
Safety mesh, install to purlins RS-ROF-SAF Shed 2 north 4,340 m² 1,475.6 34% $107,632 $36,595 140.2 of 412.3
Fibreglass roof lighting, install RS-ROF-SKY · VAR-006-01 General 380 m² 326.8 86% $75,240 $64,706 173.2 of 201.4
Downpipe & rainhead, supply and install RS-ROF-DWP Shed 2 south 72 ea 22.32 31% $62,208 $19,284 60.3 of 194.4
Safety mesh, install to purlins RS-ROF-SAF · VAR-006-02 General 2,180 m² 1,874.8 86% $54,064 $46,495 178.1 of 207.1
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$898,795 of $2,331,456 · 39%
TaskSub-jobContractDone%ValueEarnedHours
Kingspan KS1000 RW insulated panel, install RS-CLD-KSP Shed 1 south 3,480 m² 1,705.2 49% $1,007,112 $493,485 1,193.6 of 2,436
Kingspan KS1000 RW insulated panel, install RS-CLD-KSP Shed 2 south 2,760 m² 717.6 26% $798,744 $207,673 502.3 of 1,932
Custom flashings, supply and install RS-CLD-FLA Shed 1 south 2,460 lm 836.4 34% $280,440 $95,350 284.4 of 836.4
Corner & parapet capping, supply and install RS-CLD-CAP Shed 2 south 1,380 lm 400.2 29% $190,440 $55,228 160.1 of 552
Custom flashings, supply and install RS-CLD-FLA · VAR-006-02 General 480 lm 412.8 86% $54,720 $47,059 140.4 of 163.2
CC-05 Height access & safety systems Anchor points, static lines, guardrail, rope access and elevated work platforms.
$308,286 of $608,520 · 51%
TaskSub-jobContractDone%ValueEarnedHours
EWP hire & operator, 45ft boom RS-HGT-EWP General 186 day 87.42 47% $331,080 $155,608 874.2 of 1,860
Static line system: supply, install & certify RS-HGT-STA Conveyor gallery 720 lm 388.8 54% $205,920 $111,197 303.3 of 561.6
Roof anchor point: supply, install & certify RS-HGT-ANC Conveyor gallery 96 ea 55.68 58% $71,520 $41,482 122.5 of 211.2
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$122,441 of $293,280 · 42%
TaskSub-jobContractDone%ValueEarnedHours
Roof penetration flashing, form & seal RS-WPF-PEN Conveyor gallery 128 ea 33.28 26% $87,552 $22,764 76.5 of 294.4
Sealant to laps, penetrations & flashings RS-WPF-SEA Shed 1 north 2,240 lm 851.2 38% $77,952 $29,622 170.2 of 448
Sealant to laps, penetrations & flashings RS-WPF-SEA Shed 2 north 1,940 lm 523.8 27% $67,512 $18,228 104.8 of 388
Sealant to laps, penetrations & flashings RS-WPF-SEA · VAR-006-02 General 940 lm 808.4 86% $32,712 $28,132 161.7 of 188
Roof penetration flashing, form & seal RS-WPF-PEN · VAR-006-01 General 24 ea 20.64 86% $16,416 $14,118 47.5 of 55.2
Sealant to laps, penetrations & flashings RS-WPF-SEA · VAR-006-01 General 320 lm 275.2 86% $11,136 $9,577 55 of 64
CC-08 Direct labour & plant Dayworks, overtime and travel time charged at the labour rate.
$210,056 of $477,400 · 44%
TaskSub-jobContractDone%ValueEarnedHours
Travel & living away: per person, per day RS-LAB-TRV General 1,240 day 545.6 44% $477,400 $210,056 0 of 0

Sub-jobs

The same work rolled by area rather than by cost centre, which is how the site reads it.

Sub-jobCost centresValueEarned%Budget hours
Shed 1 north CC-02 · CC-06 $1,222,328 $711,892 58% 4,126.6
Shed 1 south CC-03 $1,287,552 $588,834 46% 3,272.4
Shed 2 north CC-02 · CC-06 $1,305,404 $437,547 34% 3,972.6
Shed 2 south CC-02 · CC-03 $1,218,624 $329,010 27% 3,107.2
Conveyor gallery CC-05 · CC-06 $364,992 $175,442 48% 1,067.2
General CC-01 · CC-02 · CC-03 · CC-05 · CC-06 · CC-08 $2,098,578 $1,124,592 54% 8,134.3

Drawings and documents

At their current revision. Superseded revisions stay on the register, because after an incident the question is which revision the crew were working to that day.

All documents
DocumentKindRevOwnerUpdatedSizeStatus
QJ2006 Shed 1 roof sheeting layout DOC-4412 · SharePoint / QClad / Jobs / QJ2006 / 02 Drawings Drawing D Grace Lindqvist 9 Aug 2026 8.2 MB For construction
QJ2006 Shed 1 roof sheeting layout DOC-4411 · SharePoint / QClad / Jobs / QJ2006 / 02 Drawings Drawing C Grace Lindqvist 6 Jul 2026 8.1 MB Superseded
QJ2006 Project HSE Management Plan DOC-4404 · SharePoint / QClad / Jobs / QJ2006 / 05 HSEQ Safety plan B Sam Kirkwood 31 May 2026 2.4 MB Current
SCJV subcontract SCJV-CER-SC-1180, executed DOC-4401 · SharePoint / QClad / Jobs / QJ2006 / 01 Contract Contract 1 Janelle Roe 5 Feb 2026 4.1 MB Current

Correspondence

RFIs, material approvals and anything else sent about QJ2006, with the replies on the same thread.

RFI-018 RFI Answered Marcus Deng, Saipem Clough Joint Venture 3 messages

Purlin centres at gridline 7, shed 2

Jared Ruska QClad 2026-08-12 09:12

The structural drawings issue D show purlin centres at 1200 to gridline 7, but the roof sheeting layout we have been issued is set out for 900. Sheeting cannot be laid to the current set-out without a variation to the purlins. Please confirm which is correct before we mobilise the sheeting crew on Monday.

Marcus Deng replied 2026-08-14 15:48

Confirmed 900 centres. Structural drawings are being reissued at revision E this week. Proceed on the sheeting layout as issued; the purlin variation will be instructed separately.

Jared Ruska QClad 2026-08-15 07:30

Received, thank you. Proceeding on 900. We will raise the variation for the additional purlin runs once the reissued drawings land.

Material approval Closed Marcus Deng, Saipem Clough Joint Venture 3 messages

Material approval: KLIP-LOK 700 Surfmist, shed 1 and 2

Toby Ellison QClad 2026-07-29 11:04

Material approval form attached for the roof sheeting package: Lysaght KLIP-LOK 700 HI-STRENGTH, 0.48 BMT COLORBOND in Surfmist, with the manufacturer's warranty documentation and test certificates. Requesting approval to order, noting a four week lead time on this colour.

Marcus Deng replied 2026-08-01 08:22

Approved as submitted. Please proceed to order. Note the principal has asked that the same colour be carried through to the flashings.

Toby Ellison QClad 2026-08-01 09:15

Noted, flashings will be Surfmist to match. Order placed with Lysaght today, PO-2026-0352.