VAR-039-03 Demo Purlin replacement, bays 15 to 26
Accounting connected Thu 13 Aug 2026
VAR-039-03 Submitted Crew already on it QJ2039

Variation 3, Purlin replacement, bays 15 to 26

Groote Island: Mobile Plant Workshop Re-roof · Groote Eylandt Mining Company

Raised 9 Aug 2026 by Cameron Hale

Effect of approval

These lines join QJ2039's schedule of rates. With 60% of the work already in place, the value of work in place moves with the contract sum, the open progress claim measures the difference, the job's margin recalculates, and an acknowledgement is issued to the head contractor.

Contract sum

$3,076,024 → $3,120,328

Work in place

$1,727,817 → $1,754,400

PC-2026-0197 (Aug 2026)

$164,143 → $190,725

Margin on QJ2039

20.5% → 20.4%

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-ROF-STR Strip existing roof sheeting & dispose $52.40/m² 480 $25,152.00 $23,246.40 8%
RS-CLD-FLA Custom flashings, supply and install $114.00/lm 168 $19,152.00 $15,540.00 19%
Total, ex GST $44,304.00 $38,786.40 12%
GST $4,430.40
Total, inc GST $48,734.40

Why it was raised

Same latent condition, second half of the workshop. Quantity measured off the exposed frame on 5 Aug 2026.

Gemco know it is coming. The crew are on it because the barge schedule will not wait for a purchase order to be raised twice.

Position

Value, ex GST
$44,304.00
Cost to deliver
$38,786.40
Margin
12.5%
Physically built
60%
Value already on the ground
$26,582.40
Work commenced
Yes, under site instruction

Contract

Contract no.
S32-GEM-2026-0918
Head contractor
Groote Eylandt Mining Company
Approver
Warrick Delaney
Payment terms
45 days EOM
Open claim
PC-2026-0197

Trail

  1. Raised 9 Aug 2026 by Cameron HalePriced off the job's schedule of rates
  2. Lodged with Groote Eylandt Mining CompanyAwaiting a reference