QClad
QClad
ITPs & Handover Demo 9 hold points open · 35/53 items signed
Accounting connected Wed 5 Aug 2026

Quality

ITPs & handover

Inspection and test plans signed at every hold point, plus transmittals, drawings, warranties and handover packs. Hold points must be signed before the work they gate can proceed.

Hold points open

9

work cannot proceed past these

Items signed

35/53

66% of every ITP line

ITPs in progress

8

4 complete and handed over

Overdue inspections

1

past the programmed date

Open hold points

A hold point is work that cannot proceed until it is witnessed and signed. These are the ones standing between QClad and the next stage.

ITPProjectRefInspectionStandardStatus
ITP-041-01 Roof sheeting, Banyo & Buranda canopies PRJ-2026-041 1.5 Completed roof) water test to valleys and penetrations AS 1562.1 / SA HB 39 Open
ITP-041-02 Static line and anchor system, Lindum overpass PRJ-2026-041 2.3 Proof load test 15 kN, each anchor AS/NZS 1891.2 Open
ITP-041-02 Static line and anchor system, Lindum overpass PRJ-2026-041 2.4 System certification and tagging by a competent person AS/NZS 1891.2 Open
ITP-041-03 Architectural cladding, Morningside entry PRJ-2026-041 3.3 Panel alignment and joint width, first elevation AS 1562.1 / manufacturer's specification Open
ITP-044-01 Workshop roof and wall cladding, Saraji PRJ-2026-044 4.5 Completed roof) hose test to all penetrations AS 1562.1 / BMA MES-0142 Open
ITP-038-01 Acoustic enclosure, transfer tower PRJ-2026-038 5.3 Joint and penetration sealing, no acoustic leakage AS 1055 / project acoustic report R-4412 Open
ITP-038-01 Acoustic enclosure, transfer tower PRJ-2026-038 5.4 Independent verification sound test to 38 dB(A) at the boundary AS 1055 / project acoustic report R-4412 Open
ITP-038-02 Weatherproofing, stockpile shed western wall PRJ-2026-038 6.3 Flood test to the gutter run, 24 hours AS 4654.2 Open
ITP-047-01 Hall re-roof, Mountain Creek SHS PRJ-2026-047 7.4 Completed roof, water test AS 1562.1 Open
ITP-041-01 Roof sheeting, Banyo & Buranda canopies In progress PRJ-2026-041 4/5 signed

AS 1562.1 / SA HB 39 · owned by Sam Kirkwood · Laing O'Rourke Australia

RefTypeInspectionStatusSigned
1.1 Hold Purlin set-out and level survey before sheeting Signed 4 Mar 2026 Steve Bracken
1.2 Record Sheet profile, BMT and colour verified against approved sample Signed 6 Mar 2026 P-101
1.3 Witness Fastener type, pattern and torque (first bay Signed 11 Mar 2026 Steve Bracken
1.4 Surveillance Safety mesh continuity and lap Signed 18 Mar 2026 P-009
1.5 Hold Completed roof) water test to valleys and penetrations Open -
ITP-041-02 Static line and anchor system, Lindum overpass In progress PRJ-2026-041 2/5 signed

AS/NZS 1891.2 · owned by Sam Kirkwood · Laing O'Rourke Australia

RefTypeInspectionStatusSigned
2.1 Hold Structural adequacy of the anchor substrate confirmed by the engineer Signed 28 Jul 2026 Steve Bracken
2.2 Record Anchor installation torque record, each point Signed 3 Aug 2026 P-101
2.3 Hold Proof load test 15 kN, each anchor Open -
2.4 Hold System certification and tagging by a competent person Open -
2.5 Record As-installed drawing and certificate to the handover pack Open -
ITP-041-03 Architectural cladding, Morningside entry In progress PRJ-2026-041 2/4 signed

AS 1562.1 / manufacturer's specification · owned by Sam Kirkwood · Laing O'Rourke Australia

RefTypeInspectionStatusSigned
3.1 Hold Shop drawing and set-out approved before cutting Signed 24 Jun 2026 Steve Bracken
3.2 Witness Substrate flatness within 3 mm in 3 m Signed 8 Jul 2026 P-101
3.3 Hold Panel alignment and joint width, first elevation Open -
3.4 Witness Sealant adhesion test to the cladding junction Open -
ITP-044-01 Workshop roof and wall cladding, Saraji In progress PRJ-2026-044 3/5 signed

AS 1562.1 / BMA MES-0142 · owned by Sam Kirkwood · BHP Mitsubishi Alliance

RefTypeInspectionStatusSigned
4.1 Record Existing purlin condition survey and photographic record Signed 24 Mar 2026 P-113
4.2 Hold Replacement purlin grade certificate and installation Signed 12 May 2026 Warren Idle
4.3 Witness Sheet fixing pattern to the cyclonic detail (first bay Signed 8 Apr 2026 Warren Idle
4.4 Surveillance Louvre and vent flashing weatherproofing Open -
4.5 Hold Completed roof) hose test to all penetrations Open -
ITP-038-01 Acoustic enclosure, transfer tower In progress PRJ-2026-038 2/5 signed

AS 1055 / project acoustic report R-4412 · owned by Sam Kirkwood · Rio Tinto Aluminium

RefTypeInspectionStatusSigned
5.1 Hold Panel type and acoustic rating verified against the report Signed 2 Apr 2026 Grant Hollows
5.2 Witness Isophonic mount spacing and torque Signed 19 May 2026 P-124
5.3 Hold Joint and penetration sealing, no acoustic leakage Open -
5.4 Hold Independent verification sound test to 38 dB(A) at the boundary Open -
5.5 Record Acoustic consultant's report to the handover pack Open -
ITP-038-02 Weatherproofing, stockpile shed western wall Overdue PRJ-2026-038 1/3 signed

AS 4654.2 · owned by Sam Kirkwood · Rio Tinto Aluminium

RefTypeInspectionStatusSigned
6.1 Surveillance Substrate preparation and primer Signed 11 Jun 2026 P-124
6.2 Witness Membrane dry film thickness, 5 readings per 100 m² Overdue -
6.3 Hold Flood test to the gutter run, 24 hours Open -
ITP-047-01 Hall re-roof, Mountain Creek SHS In progress PRJ-2026-047 2/5 signed

AS 1562.1 · owned by Sam Kirkwood · Mountain Creek State High School, Dept of Education

RefTypeInspectionStatusSigned
7.1 Hold Asbestos clearance certificate before re-sheeting Signed 24 Jul 2026 Ian Bardsley
7.2 Witness Purlin condition and level after strip Signed 27 Jul 2026 P-135
7.3 Surveillance Insulation and safety mesh installation Open -
7.4 Hold Completed roof, water test Open -
7.5 Record Edge protection removal and make good Open -
ITP-045-01 Facade cladding, M&A Stage 3 In progress PRJ-2026-045 2/4 signed

AS 1562.1 / NCC C1.9 · owned by Sam Kirkwood · M&A Developments

RefTypeInspectionStatusSigned
8.1 Hold Panel fire performance certification to NCC Signed 21 May 2026 Jordan Ellul
8.2 Hold Revised set-out approved before recut Signed 1 Jul 2026 Jordan Ellul
8.3 Witness Panel alignment, each elevation Open -
8.4 Witness Membrane and flashing to the window heads Open -
ITP-036-01 Workshop roofing, Mt Thorley Warkworth Complete PRJ-2025-036 5/5 signed

AS 1562.1 / Yancoal SPEC-2210 · owned by Sam Kirkwood · Yancoal Australia

RefTypeInspectionStatusSigned
9.1 Hold Purlin renewal certificate Signed 4 Dec 2025 Dean Copeland
9.2 Witness Fixing pattern verification Signed 16 Oct 2025 Dean Copeland
9.3 Hold Anchor proof load, each point Signed 21 May 2026 Dean Copeland
9.4 Hold Completed roof water test Signed 18 Jun 2026 Dean Copeland
9.5 Record Warranty and as-built pack issued Signed 10 Jul 2026 P-011
ITP-031-01 Insulated panel cladding, Damascus B004 Complete PRJ-2025-031 4/4 signed

AS 1562.1 / Defence ESM · owned by Sam Kirkwood · Department of Defence, Estate & Infrastructure

RefTypeInspectionStatusSigned
10.1 Hold Panel certification and security clearance record Signed 10 Jun 2025 Maj. Ellen Straub
10.2 Witness Penetration flashing, all 19 points Signed 2 Oct 2025 Maj. Ellen Straub
10.3 Witness Membrane DFT readings Signed 18 Nov 2025 P-009
10.4 Record Handover pack and warranties Signed 6 Mar 2026 P-011
ITP-039-01 Cold store insulated panel, Yatala Complete PRJ-2025-039 4/4 signed

AS 1562.1 / HACCP facility standard · owned by Sam Kirkwood · McNab Constructions

RefTypeInspectionStatusSigned
11.1 Hold Panel core certification Signed 20 Nov 2025 Alex Farrer
11.2 Hold Sealed joint detail, certifier witness Signed 4 Mar 2026 Alex Farrer
11.3 Witness Thermal imaging survey for cold bridging Signed 14 May 2026 P-009
11.4 Record Handover pack Signed 12 Jun 2026 P-011
ITP-034-01 Hangar cladding renewal, Williamtown Complete PRJ-2025-034 4/4 signed

AS 1562.1 / Defence ESM · owned by Sam Kirkwood · Department of Defence, Estate & Infrastructure

RefTypeInspectionStatusSigned
12.1 Hold Panel colour approval after the client change Signed 9 Sep 2025 Maj. Ellen Straub
12.2 Witness Fixing and sealant to the parapet Signed 6 Nov 2025 P-009
12.3 Hold Completed facade water test Signed 11 Dec 2025 Maj. Ellen Straub
12.4 Record Handover pack and warranties Signed 19 Dec 2025 P-011

Document control

Transmittals, the drawing register, handover packs and warranties.

RegisterRecordsWhere it lands
Transmittal 2,640 Document control
Drawing_Register 8,204 Drawings
Handover_Pack 186 Handover
Warranty 412 Warranties

Object-by-object mapping is in the migration console.

Handover packs

Assembled from the ITPs, warranties and as-installed records held against the job.

PRJ-2025-031

Damascus Barracks B004: Cladding Rectification

PC 6 Mar 2026 · DLP ends 6 Mar 2027

Issued
PRJ-2025-036

Mt Thorley Warkworth Mine Workshop: Roofing & Cladding

PC 10 Jul 2026 · DLP ends 10 Jul 2027

Issued
PRJ-2025-028

Coomera Station Re-roof

PC 23 May 2025 · DLP ends 23 May 2026

Migrated
PRJ-2025-024

RTAY Yarwun Central Workshop: Cladding

PC 4 Apr 2025 · DLP ends 4 Apr 2026

Migrated
PRJ-2025-019

Wambo Mine: Roofing & Cladding Renewal

PC 10 Jan 2025 · DLP ends 10 Jan 2026

Migrated
PRJ-2024-014

Mount Pleasant Mine: Workshop Roofing

PC 28 Jun 2024 · DLP ends 28 Jun 2025

Migrated
PRJ-2024-009

Rio Tinto Boyne Smelters: Potline Cladding

PC 5 Apr 2023 · DLP ends 5 Apr 2024

Migrated
PRJ-2025-034

Williamtown RAAF: NACC Hangar Cladding Renewal

PC 19 Dec 2025 · DLP ends 19 Dec 2026

Issued
PRJ-2025-039

McNab: Yatala Cold Store Insulated Panel

PC 12 Jun 2026 · DLP ends 12 Jun 2027

Issued
PRJ-2024-021

Clermont Coal: CHPP Conveyor Sheeting

PC 29 Feb 2024 · DLP ends 28 Feb 2025

Migrated
PRJ-2024-018

RNA Showgrounds: Pavilion Roof Renewal Stage 4

PC 2 Feb 2024 · DLP ends 2 Feb 2025

Migrated