Variation 1, Conveyor cover extension, 40 lm
Clermont Coal: CHPP Conveyor Sheeting · BHP Mitsubishi Alliance · their reference BMA-VO-1802
Raised 4 Dec 2023 by Marcus Deng · approved 18 Dec 2023 by Warren Idle
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-CLD-CUS CUSTOM ORB wall cladding, install | $102.40/m² | 220 | $22,528.00 | $18,667.00 | 17% |
| RS-WPF-SEA Sealant to laps, penetrations & flashings | $34.80/lm | 140 | $4,872.00 | $3,868.20 | 21% |
| Total, ex GST | $27,400.00 | $22,535.20 | 18% | ||
| GST | $2,740.00 | ||||
| Total, inc GST | $30,140.00 | ||||
Why it was raised
Dust suppression audit extended the covered length.
Position
- Value, ex GST
- $27,400.00
- Cost to deliver
- $22,535.20
- Margin
- 17.8%
- Physically built
- 100%
- Value already on the ground
- $27,400.00
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2024-021
- Contract no.
- BMA-CLM-CHPP-2023-6602
- Head contractor
- BHP Mitsubishi Alliance
- Approver
- Warren Idle
- Payment terms
- 45 days EOM
Trail
- Raised 4 Dec 2023 by Marcus DengPriced off the project schedule of rates
- Lodged with BHP Mitsubishi AllianceTheir reference BMA-VO-1802
- Approved 18 Dec 2023Warren Idle · added to the contract sum and the open claim