VAR-939-01 Demo Panel joint upgrade for cold-store certification
Accounting connected Thu 13 Aug 2026
VAR-939-01 Approved QJ1939

Variation 1, Panel joint upgrade for cold-store certification

McNab: Yatala Cold Store Insulated Panel · McNab Constructions · their reference MCN-VO-0442

Raised 21 Feb 2026 by Cameron Hale · approved 12 Mar 2026 by Alex Farrer

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 640 $22,272.00 $17,683.20 21%
RS-CLD-FLA Custom flashings, supply and install $114.00/lm 96 $10,944.00 $8,880.00 19%
Total, ex GST $33,216.00 $26,563.20 20%
GST $3,321.60
Total, inc GST $36,537.60

Why it was raised

Certifier required a sealed joint detail beyond the specified system.

Position

Value, ex GST
$33,216.00
Cost to deliver
$26,563.20
Margin
20.0%
Physically built
100%
Value already on the ground
$33,216.00
Work commenced
Yes, under site instruction

Contract

Contract no.
MCN-YAT-CS-2025-2214
Head contractor
McNab Constructions
Approver
Alex Farrer
Payment terms
30 days

Trail

  1. Raised 21 Feb 2026 by Cameron HalePriced off the job's schedule of rates
  2. Lodged with McNab ConstructionsTheir reference MCN-VO-0442
  3. Approved 12 Mar 2026Alex Farrer · added to the contract sum and the open claim