Knowledge
Tasks
Assigned actions, with the record that raised each one a click away. Nothing here is typed twice: closing the task is closing the thing.
Open
21
2 closed
Assigned to you
2
Nathan Carter
Overdue
0
past the due date
Urgent
4
today, not this week
Everything open
Urgent first, then by due date. Closed tasks sit at the bottom.
Approve the two Ceres purchase orders
PO-2026-0352 and PO-2026-0351, $255k between them. The Kingspan panel has a twenty-eight day lead, so the second one cannot sit.
Nathan Carter · raised by Toby Ellison · due 13 Aug 2026
Chase Laing O'Rourke on the July payment schedule
PC-2026-0187 is past the fifteen business day window under the BIF Act. Ring Steve Bracken, then follow up in writing the same day.
Janelle Roe · raised by Nathan Carter · due 13 Aug 2026
Fix the mesh panel on Shed 2 north
Hazard report HSE_FRM_011_340. Exclusion zone in place until it is fixed.
Zeb Marchetti · raised by Levi Sandford · due 13 Aug 2026
Get VAR-041-04 approved before any more of it is built
Crew are 86% through the work and there is no approval on file. Nathan authorised the order to hold the programme.
Marcus Deng · raised by Nathan Carter · due 14 Aug 2026
Book the spider lift service technician to Groote
PL-009 service due 19 Aug 2026. Technician has to fly in, so the booking needs a week's notice.
Toby Ellison · raised by Cameron Hale · due 14 Aug 2026
Get the Lysaght short-shipped 160 m² onto the 14 Aug 2026 run
PO-2026-0337. Saraji cannot start bay 6 without it.
Toby Ellison · raised by Mitch Ravenscroft · due 14 Aug 2026
Reinstate the sediment fence at the Ceres laydown
Raised on site inspection HSE_FRM_014_287. Needs doing before the next rain event.
Zeb Marchetti · raised by Sam Kirkwood · due 15 Aug 2026
Remeasure the QJ2039 purlin quantity and issue the variation
Provisional quantity at tender. The sheeting is off bays 1 to 14 and the actual is materially different.
Cameron Hale · raised by Nathan Carter · due 16 Aug 2026
Sign off the liquidated damages position on Q32235
Uncapped as drafted. Legal have marked it up. Morgan will not start until we come back.
Adam Doyle · raised by Janelle Roe · due 17 Aug 2026
Renew Dane Kelso's working at heights ticket
Expires inside 30 days. He is rostered on the next Ceres swing and will not get through the gate without it.
Sam Kirkwood · raised by Sam Kirkwood · due 18 Aug 2026
Return the Q32235 Morgan contract to legal
Liquidated damages clause is uncapped as drafted. Nothing starts until it is resolved.
Janelle Roe · raised by Adam Doyle · due 19 Aug 2026
Sign off the QJ2041 roof ITP hold point at Buranda
Sam Kirkwood · raised by Marcus Deng · due 15 Aug 2026
File the August SCJV hours reconciliation
The joint venture's clock-on data has to agree with QClad's day cards every week.
Raelene Brown · raised by Marcus Deng · due 15 Aug 2026
Key the crib allowance into the Xero pay run
PAY-2026-16. Xero's API will not take an hourly crib allowance, so it goes in by hand once timesheets close Sunday.
Raelene Brown · raised by Raelene Brown · due 16 Aug 2026
Lodge the Hillgrove price with MACA
Q32916 has been priced and sitting since February. MACA extended the close twice and have not come back.
Dylan Fraser · raised by Nathan Carter · due 17 Aug 2026
Issue new gloves across Crew 3
Three month replacement cycle is up for eleven of the twelve on the Ceres swing.
Toby Ellison · raised by Zeb Marchetti · due 17 Aug 2026
Label the waste segregation bins at the Groote barge landing
Raised on environmental inspection HSE_FRM_019_153. Labels are on the next barge.
Dom Falzon · raised by Sam Kirkwood · due 22 Aug 2026
Complete KB-009, raising a variation before you build it
Mandatory for leading hands. Twelve of the crew have done it.
Blake Tuiala · raised by Janelle Roe · due 23 Aug 2026
Decide on Project Braemer before the December close
QPL2376. Largest number on the board by a factor of nine. If we go, the panel order has to be placed at award, not after.
Nathan Carter · raised by Dylan Fraser · due 3 Sep 2026
Close out Q27503 Townsville budget pricing
Two years old and still on the board. Either re-price it or mark it lost so the pipeline number means something.
Priya Raghavan · raised by Dylan Fraser · due 20 Aug 2026
Replace PL-002 tyres and book the service
Toby Ellison · raised by Mitch Ravenscroft · due 27 Aug 2026
Order the Ceres Shed 2 flashing prefabrication
Toby Ellison · raised by Marcus Deng · due 12 Aug 2026
Send the QJ2039 barge manifest to Gemco
Toby Ellison · raised by Cameron Hale · due 10 Aug 2026
Nothing matches that filter.