Variation 1, Asbestos-containing sarking found, hold and dispose
Mountain Creek SHS: Hall Re-roof & Cladding · Mountain Creek State High School, Dept of Education · their reference QED-VO-0114
Raised 13 Jul 2026 by Cameron Doyle · approved 24 Jul 2026 by Ian Bardsley
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-PRE-SUP Site supervision, leading hand | $1,248.00/day | 8 | $9,984.00 | $8,280.00 | 17% |
| RS-ROF-STR Strip existing roof sheeting & dispose | $52.40/m² | 220 | $11,528.00 | $10,654.60 | 8% |
| Total, ex GST | $21,512.00 | $18,934.60 | 12% | ||
| GST | $2,151.20 | ||||
| Total, inc GST | $23,663.20 | ||||
Why it was raised
ACM sarking encountered under the existing sheets; hygienist engaged, works held eight days.
Excluded from the tender, correctly. Hygienist and licensed removalist billed at cost plus the standby.
Position
- Value, ex GST
- $21,512.00
- Cost to deliver
- $18,934.60
- Margin
- 12.0%
- Physically built
- 86%
- Value already on the ground
- $18,500.32
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2026-047
- Contract no.
- QED-MCSHS-2026-0331
- Head contractor
- Mountain Creek State High School, Dept of Education
- Approver
- Ian Bardsley
- Payment terms
- 30 days
Trail
- Raised 13 Jul 2026 by Cameron DoylePriced off the project schedule of rates
- Lodged with Mountain Creek State High School, Dept of EducationTheir reference QED-VO-0114
- Approved 24 Jul 2026Ian Bardsley · added to the contract sum and the open claim