VAR-047-01 Demo Asbestos-containing sarking found, hold and dispose
Accounting connected Thu 13 Aug 2026
VAR-047-01 Approved QJ2047

Variation 1, Asbestos-containing sarking found, hold and dispose

Mountain Creek SHS: Hall Re-roof & Cladding · Mountain Creek State High School, Dept of Education · their reference QED-VO-0114

Raised 21 Jul 2026 by Cameron Hale · approved 1 Aug 2026 by Ian Bardsley

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 8 $9,984.00 $8,280.00 17%
RS-ROF-STR Strip existing roof sheeting & dispose $52.40/m² 220 $11,528.00 $10,654.60 8%
Total, ex GST $21,512.00 $18,934.60 12%
GST $2,151.20
Total, inc GST $23,663.20

Why it was raised

ACM sarking encountered under the existing sheets; hygienist engaged, works held eight days.

Excluded from the tender, correctly. Hygienist and licensed removalist billed at cost plus the standby.

Position

Value, ex GST
$21,512.00
Cost to deliver
$18,934.60
Margin
12.0%
Physically built
86%
Value already on the ground
$18,500.32
Work commenced
Yes, under site instruction

Contract

Contract no.
QED-MCSHS-2026-0331
Head contractor
Mountain Creek State High School, Dept of Education
Approver
Ian Bardsley
Payment terms
30 days

Trail

  1. Raised 21 Jul 2026 by Cameron HalePriced off the job's schedule of rates
  2. Lodged with Mountain Creek State High School, Dept of EducationTheir reference QED-VO-0114
  3. Approved 1 Aug 2026Ian Bardsley · added to the contract sum and the open claim