VAR-047-01 Demo Asbestos-containing sarking found, hold and dispose
Accounting connected Wed 5 Aug 2026
VAR-047-01 Approved PRJ-2026-047

Variation 1, Asbestos-containing sarking found, hold and dispose

Mountain Creek SHS: Hall Re-roof & Cladding · Mountain Creek State High School, Dept of Education · their reference QED-VO-0114

Raised 13 Jul 2026 by Cameron Doyle · approved 24 Jul 2026 by Ian Bardsley

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 8 $9,984.00 $8,280.00 17%
RS-ROF-STR Strip existing roof sheeting & dispose $52.40/m² 220 $11,528.00 $10,654.60 8%
Total, ex GST $21,512.00 $18,934.60 12%
GST $2,151.20
Total, inc GST $23,663.20

Why it was raised

ACM sarking encountered under the existing sheets; hygienist engaged, works held eight days.

Excluded from the tender, correctly. Hygienist and licensed removalist billed at cost plus the standby.

Position

Value, ex GST
$21,512.00
Cost to deliver
$18,934.60
Margin
12.0%
Physically built
86%
Value already on the ground
$18,500.32
Work commenced
Yes, under site instruction

Contract

Contract no.
QED-MCSHS-2026-0331
Head contractor
Mountain Creek State High School, Dept of Education
Approver
Ian Bardsley
Payment terms
30 days

Trail

  1. Raised 13 Jul 2026 by Cameron DoylePriced off the project schedule of rates
  2. Lodged with Mountain Creek State High School, Dept of EducationTheir reference QED-VO-0114
  3. Approved 24 Jul 2026Ian Bardsley · added to the contract sum and the open claim