QJ2038 Demo Boyne Smelters Stockpile Shed: Re-clad & Acoustics
Accounting connected Thu 13 Aug 2026
QJ2038 On site Mining & Resources P6 BSL.SPS.7710

Boyne Smelters Stockpile Shed: Re-clad & Acoustics

Rio Tinto Aluminium · Boyne Island, Gladstone, QLD · contract RTA-BSL-SC-88104

Marcus Deng · 17 Feb 2026 → 5 Sep 2026

Client view

Shutdown windows only, the conveyor beneath cannot be stopped outside them. Acoustic enclosure to the transfer tower is verified by an independent sound test before handover.

The position

Every figure below is the sum of rows on this page.

Contract sum

$2,650,824

Tendered
$2,542,100
Approved variations
+$108,724
Lodged, not approved
$42,111

Work in place

$2,050,266

Complete
77.3%
Still to run
$600,558

Claimed & certified

$1,984,657

Certified
$1,755,028
Unclaimed WIP
$65,609
Retention held
$87,751

Margin

$312,325 15.2%

Cost of work in place
$1,737,940
Against the build-up
+$8,900
Committed, not received
$68,388

$25,266.60 of work is on the ground against variations nobody has approved.

VAR-038-04, Additional shutdown attendance, July window · VAR-038-03, Membrane to the western gutter run. Until they are approved they sit in cost with no revenue against them.

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 5 tasks · General $184,004 $145,659 79% 1,457 1,165.1 $0 $131 - +$1,291 16%
CC-02 Roofing 1 task · General $183,864 $167,316 91% 564 515.5 $67,183 $67,471 - +$502 16%
CC-03 Wall cladding 3 tasks · General $777,984 $678,926 87% 2,761.4 2,460.4 $186,595 $187,836 - +$2,513 17%
CC-04 Acoustics 9 tasks · General $1,093,180 $737,438 67% 2,907.7 1,969.5 $319,752 $321,927 $79,780 +$3,497 18%
CC-05 Height access & safety systems 4 tasks · General $251,880 $212,764 84% 1,369.6 1,147.6 $33,319 $33,473 - +$455 20%
CC-06 Weatherproofing 2 tasks · General $159,912 $108,163 68% 712.8 511.3 $64,137 $64,489 $6,708 +$642 -22%
Job total $2,650,824 $2,050,266 77% 9,772.5 7,769.4 $670,986 $675,328 $86,488 +$8,900 15%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $1,737,940, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$145,659 of $184,004 · 79%
TaskSub-jobContractDone%ValueEarnedHours
Site supervision, leading hand RS-PRE-SUP General 118 day 93.22 79% $147,264 $116,339 978.8 of 1,239
Mobilisation & site establishment RS-PRE-MOB General 1 item 1 100% $18,450 $18,450 96 of 96
Site induction & verification of competency RS-PRE-IND General 14 ea 14 100% $8,190 $8,190 56 of 56
Demobilisation & make good RS-PRE-DEM General 1 item 0 0% $7,420 $0 0 of 44
SWMS, JSA & site-specific safety plan RS-PRE-SWM General 1 item 1 100% $2,680 $2,680 22 of 22
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$167,316 of $183,864 · 91%
TaskSub-jobContractDone%ValueEarnedHours
TRIMDEK roof sheeting, install RS-ROF-TRM General 1,880 m² 1,710.8 91% $183,864 $167,316 513.2 of 564
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$678,926 of $777,984 · 87%
TaskSub-jobContractDone%ValueEarnedHours
CUSTOM ORB wall cladding, install RS-CLD-CUS General 4,260 m² 3,663.6 86% $459,228 $394,936 1,099.1 of 1,278
Strip existing wall cladding & dispose RS-CLD-STR General 4,260 m² 4,004.4 94% $207,036 $194,614 1,081.2 of 1,150.2
Custom flashings, supply and install RS-CLD-FLA General 980 lm 784 80% $111,720 $89,376 266.6 of 333.2
CC-04 Acoustics Enclosures, absorptive lining, barrier, isolation mounts and commissioning tests.
$737,438 of $1,093,180 · 67%
TaskSub-jobContractDone%ValueEarnedHours
Acoustic absorption panel, install RS-ACO-PNL General 1,240 m² 892.8 72% $283,960 $204,451 553.5 of 768.8
Perforated acoustic liner tray, install RS-ACO-LIN General 860 m² 567.6 66% $227,040 $149,846 397.3 of 602
Mass-loaded acoustic barrier mat, install RS-ACO-BAR General 1,240 m² 868 70% $193,440 $135,408 364.6 of 520.8
Plant acoustic enclosure, fabricate and install RS-ACO-ENC General 380 m² 182.4 48% $183,160 $87,917 240.8 of 501.6
Isophonic bracket & resilient mount system RS-ACO-ISO General 1,240 m² 917.6 74% $110,856 $82,033 192.7 of 260.4
Plant acoustic enclosure, fabricate and install RS-ACO-ENC · VAR-038-01 General 96 m² 82.56 86% $46,272 $39,794 109 of 126.7
Mass-loaded acoustic barrier mat, install RS-ACO-BAR · VAR-038-01 General 180 m² 154.8 86% $28,080 $24,149 65 of 75.6
Isophonic bracket & resilient mount system RS-ACO-ISO · VAR-038-01 General 180 m² 154.8 86% $16,092 $13,839 32.5 of 37.8
Post-installation acoustic verification test RS-ACO-TST General 1 item 0 0% $4,280 $0 0 of 14
CC-05 Height access & safety systems Anchor points, static lines, guardrail, rope access and elevated work platforms.
$212,764 of $251,880 · 84%
TaskSub-jobContractDone%ValueEarnedHours
Rope access technician, IRATA RS-HGT-ROP General 96 day 78.72 82% $142,080 $116,506 787.2 of 960
Static line system: supply, install & certify RS-HGT-STA General 320 lm 281.6 88% $91,520 $80,538 219.6 of 249.6
Rope access technician, IRATA RS-HGT-ROP · VAR-038-02 General 34 day 29.24 86% $50,320 $43,275 292.4 of 340
EWP hire & operator, 45ft boom RS-HGT-EWP · VAR-038-02 General -18 day -15.48 86% -$32,040 -$27,554 -154.8 of -180
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$108,163 of $159,912 · 68%
TaskSub-jobContractDone%ValueEarnedHours
Sealant to laps, penetrations & flashings RS-WPF-SEA General 2,640 lm 2,032.8 77% $91,872 $70,741 406.6 of 528
Liquid-applied weatherproof membrane RS-WPF-MEM General 420 m² 231 55% $68,040 $37,422 101.6 of 184.8

Correspondence

RFIs, material approvals and anything else sent about QJ2038, with the replies on the same thread.

Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.