QJ1818 Demo RNA Showgrounds: Pavilion Roof Renewal Stage 4
Accounting connected Thu 13 Aug 2026
QJ1818 Complete Commercial

RNA Showgrounds: Pavilion Roof Renewal Stage 4

ADCO Constructions · Bowen Hills, Brisbane, QLD · contract ADC-RNA-S4-2023-4419

Cameron Hale · 29 Aug 2023 → 27 Jan 2024 · PC 10 Feb 2024 · DLP ends 10 Feb 2025

Client view

The position

Every figure below is the sum of rows on this page.

Contract sum

$651,368

Tendered
$619,520
Approved variations
+$31,848

Work in place

$651,368

Complete
100.0%
Still to run
$0

Claimed & certified

$651,368

Certified
$85,329
Unclaimed WIP
$0
Retention held
$0

Margin

$99,985 15.4%

Cost of work in place
$551,383
Against the build-up
+$7,200
Committed, not received
$0

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 4 tasks · General $209,764 $209,764 100% 819.8 839.3 $0 $2,264 - +$4,102 16%
CC-02 Roofing 4 tasks · General $372,172 $372,172 100% 1,278.9 1,291.5 $121,218 $122,550 - +$2,517 14%
CC-03 Wall cladding 2 tasks · General $31,848 $31,848 100% 93.9 95.1 $12,390 $12,537 - +$255 19%
CC-06 Weatherproofing 1 task · General $37,584 $37,584 100% 216 218.9 $2,117 $2,168 - +$326 20%
Job total $651,368 $651,368 100% 2,408.6 2,444.8 $135,725 $139,518 $0 +$7,200 15%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $551,383, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$209,764 of $209,764 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Scaffold: supply, erect, hire 8 weeks, dismantle RS-PRE-SCF General 1,180 m² 1,180 100% $111,510 $111,510 70.8 of 70.8
Site supervision, leading hand RS-PRE-SUP General 58 day 58 100% $72,384 $72,384 609 of 609
Mobilisation & site establishment RS-PRE-MOB General 1 item 1 100% $18,450 $18,450 96 of 96
Demobilisation & make good RS-PRE-DEM General 1 item 1 100% $7,420 $7,420 44 of 44
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$372,172 of $372,172 · 100%
TaskSub-jobContractDone%ValueEarnedHours
KLIP-LOK 406 roof sheeting, install RS-ROF-KL4 General 1,640 m² 1,640 100% $190,896 $190,896 541.2 of 541.2
Strip existing roof sheeting & dispose RS-ROF-STR General 1,640 m² 1,640 100% $85,936 $85,936 475.6 of 475.6
Box gutter, supply and install RS-ROF-GUT General 168 lm 168 100% $64,680 $64,680 178.1 of 178.1
Ridge capping & barge, supply and install RS-ROF-RDG General 210 lm 210 100% $30,660 $30,660 84 of 84
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$31,848 of $31,848 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Custom flashings, supply and install RS-CLD-FLA · VAR-018-01 General 168 lm 168 100% $19,152 $19,152 57.1 of 57.1
Corner & parapet capping, supply and install RS-CLD-CAP · VAR-018-01 General 92 lm 92 100% $12,696 $12,696 36.8 of 36.8
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$37,584 of $37,584 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Sealant to laps, penetrations & flashings RS-WPF-SEA General 1,080 lm 1,080 100% $37,584 $37,584 216 of 216

Correspondence

RFIs, material approvals and anything else sent about QJ1818, with the replies on the same thread.