Variation 1, Early works, conveyor permit and survey
Bengalla VDC Re-roof Stage 2 · Bengalla Mining Company · their reference BGA-VO-0104
Raised 28 Jul 2026 by Marcus Deng · approved 3 Aug 2026 by Kate Mercer
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-PRE-SWM SWMS, JSA & site-specific safety plan | $2,680.00/item | 1 | $2,680.00 | $2,288.00 | 15% |
| RS-PRE-SUP Site supervision, leading hand | $1,248.00/day | 6 | $7,488.00 | $6,210.00 | 17% |
| Total, ex GST | $10,168.00 | $8,498.00 | 16% | ||
| GST | $1,016.80 | ||||
| Total, inc GST | $11,184.80 | ||||
Why it was raised
Bengalla required the permit-to-work regime and a laser survey established before mobilisation.
Position
- Value, ex GST
- $10,168.00
- Cost to deliver
- $8,498.00
- Margin
- 16.4%
- Physically built
- 86%
- Value already on the ground
- $8,744.48
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2026-049
- Contract no.
- BGA-VDC-S2-40118
- Head contractor
- Bengalla Mining Company
- Approver
- Kate Mercer
- Payment terms
- 45 days EOM
- Open claim
- PC-2026-0194
Trail
- Raised 28 Jul 2026 by Marcus DengPriced off the project schedule of rates
- Lodged with Bengalla Mining CompanyTheir reference BGA-VO-0104
- Approved 3 Aug 2026Kate Mercer · added to the contract sum and the open claim