VAR-046-02 Demo Shed 7 roof lighting replacement
Accounting connected Thu 13 Aug 2026
VAR-046-02 Approved QJ2046

Variation 2, Shed 7 roof lighting replacement

Downer Rail Maryborough: Periodic Roofing Works 2026 · Downer Rail · their reference DWN-VO-0214

Raised 7 Jul 2026 by Cameron Hale · approved 16 Jul 2026 by Paul Mistry

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-ROF-SKY Fibreglass roof lighting, install $198.00/m² 84 $16,632.00 $14,220.36 14%
Total, ex GST $16,632.00 $14,220.36 14%
GST $1,663.20
Total, inc GST $18,295.20

Why it was raised

Called off against the standing rates after a hail event in June.

Position

Value, ex GST
$16,632.00
Cost to deliver
$14,220.36
Margin
14.5%
Physically built
86%
Value already on the ground
$14,303.52
Work commenced
Yes, under site instruction

Contract

Contract no.
DWN-MBH-PER-2026
Head contractor
Downer Rail
Approver
Paul Mistry
Payment terms
30 days

Trail

  1. Raised 7 Jul 2026 by Cameron HalePriced off the job's schedule of rates
  2. Lodged with Downer RailTheir reference DWN-VO-0214
  3. Approved 16 Jul 2026Paul Mistry · added to the contract sum and the open claim