VAR-046-02 Demo Shed 7 roof lighting replacement
Accounting connected Wed 5 Aug 2026
VAR-046-02 Approved PRJ-2026-046

Variation 2, Shed 7 roof lighting replacement

Downer Rail Maryborough: Periodic Roofing Works 2026 · Downer Rail · their reference DWN-VO-0214

Raised 29 Jun 2026 by Cameron Doyle · approved 8 Jul 2026 by Paul Mistry

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-ROF-SKY Fibreglass roof lighting, install $198.00/m² 84 $16,632.00 $14,220.36 14%
Total, ex GST $16,632.00 $14,220.36 14%
GST $1,663.20
Total, inc GST $18,295.20

Why it was raised

Called off against the standing rates after a hail event in June.

Position

Value, ex GST
$16,632.00
Cost to deliver
$14,220.36
Margin
14.5%
Physically built
86%
Value already on the ground
$14,303.52
Work commenced
Yes, under site instruction

Contract

Contract no.
DWN-MBH-PER-2026
Head contractor
Downer Rail
Approver
Paul Mistry
Payment terms
30 days

Trail

  1. Raised 29 Jun 2026 by Cameron DoylePriced off the project schedule of rates
  2. Lodged with Downer RailTheir reference DWN-VO-0214
  3. Approved 8 Jul 2026Paul Mistry · added to the contract sum and the open claim