Variation 2, Shed 7 roof lighting replacement
Downer Rail Maryborough: Periodic Roofing Works 2026 · Downer Rail · their reference DWN-VO-0214
Raised 29 Jun 2026 by Cameron Doyle · approved 8 Jul 2026 by Paul Mistry
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-ROF-SKY Fibreglass roof lighting, install | $198.00/m² | 84 | $16,632.00 | $14,220.36 | 14% |
| Total, ex GST | $16,632.00 | $14,220.36 | 14% | ||
| GST | $1,663.20 | ||||
| Total, inc GST | $18,295.20 | ||||
Why it was raised
Called off against the standing rates after a hail event in June.
Position
- Value, ex GST
- $16,632.00
- Cost to deliver
- $14,220.36
- Margin
- 14.5%
- Physically built
- 86%
- Value already on the ground
- $14,303.52
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2026-046
- Contract no.
- DWN-MBH-PER-2026
- Head contractor
- Downer Rail
- Approver
- Paul Mistry
- Payment terms
- 30 days
Trail
- Raised 29 Jun 2026 by Cameron DoylePriced off the project schedule of rates
- Lodged with Downer RailTheir reference DWN-VO-0214
- Approved 8 Jul 2026Paul Mistry · added to the contract sum and the open claim