Accounting connected Thu 13 Aug 2026
QJ1814 Complete Mining & Resources

Mount Pleasant Mine: Workshop Roofing

MACH Energy, Mount Pleasant Operations · Mount Pleasant, Muswellbrook, NSW · contract MACH-MP-WS-2023-8890

Cameron Hale · 30 Jan 2024 → 22 Jun 2024 · PC 6 Jul 2024 · DLP ends 6 Jul 2025

Client view

The position

Every figure below is the sum of rows on this page.

Contract sum

$721,334

Tendered
$705,958
Approved variations
+$15,376

Work in place

$721,334

Complete
100.0%
Still to run
$0

Claimed & certified

$721,334

Certified
$53,379
Unclaimed WIP
$0
Retention held
$0

Margin

$129,856 18.0%

Cost of work in place
$591,478
Against the build-up
-$9,400
Committed, not received
$0

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 3 tasks · General $118,222 $118,222 100% 917 889.2 $0 -$362 - -$2,979 20%
CC-02 Roofing 4 tasks · General $402,092 $402,092 100% 1,459.5 1,441.2 $117,370 $115,676 - -$3,415 17%
CC-03 Wall cladding 1 task · General $54,720 $54,720 100% 163.2 160.6 $21,269 $20,948 - -$562 20%
CC-08 Direct labour & plant 1 task · General $146,300 $146,300 100% 0 0 $0 -$2,445 - -$2,445 19%
Job total $721,334 $721,334 100% 2,539.7 2,491 $138,639 $133,817 $0 -$9,400 18%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $591,478, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$118,222 of $118,222 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Site supervision, leading hand RS-PRE-SUP General 74 day 74 100% $92,352 $92,352 777 of 777
Mobilisation & site establishment RS-PRE-MOB General 1 item 1 100% $18,450 $18,450 96 of 96
Demobilisation & make good RS-PRE-DEM General 1 item 1 100% $7,420 $7,420 44 of 44
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$402,092 of $402,092 · 100%
TaskSub-jobContractDone%ValueEarnedHours
KLIP-LOK 700 HI-STRENGTH roof sheeting, install RS-ROF-KL7 General 1,880 m² 1,880 100% $241,580 $241,580 676.8 of 676.8
Strip existing roof sheeting & dispose RS-ROF-STR General 1,880 m² 1,880 100% $98,512 $98,512 545.2 of 545.2
Safety mesh, install to purlins RS-ROF-SAF General 1,880 m² 1,880 100% $46,624 $46,624 178.6 of 178.6
Safety mesh, install to purlins RS-ROF-SAF · VAR-014-01 General 620 m² 620 100% $15,376 $15,376 58.9 of 58.9
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$54,720 of $54,720 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Custom flashings, supply and install RS-CLD-FLA General 480 lm 480 100% $54,720 $54,720 163.2 of 163.2
CC-08 Direct labour & plant Dayworks, overtime and travel time charged at the labour rate.
$146,300 of $146,300 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Travel & living away: per person, per day RS-LAB-TRV General 380 day 380 100% $146,300 $146,300 0 of 0