QClad
QClad
QJ1934 Demo Williamtown RAAF: NACC Hangar Cladding Renewal
Accounting connected Thu 13 Aug 2026
QJ1934 Defects liability Defence

Williamtown RAAF: NACC Hangar Cladding Renewal

Department of Defence, Estate & Infrastructure · RAAF Base Williamtown, NSW · contract DEF-EI-WLM-NACC-8804

Marcus Deng · 22 Apr 2025 → 20 Dec 2025 · PC 27 Dec 2025 · DLP ends 27 Dec 2026

Client view

Follows the 2018 WE02 package. Two defect items open: sealant to the northern parapet, and a rain-head overflow. Attendance booked for 27 Aug 2026.

The position

Every figure below is the sum of rows on this page.

Contract sum

$1,795,916

Tendered
$1,593,424
Approved variations
+$202,492
Lodged, not approved
$4,867

Work in place

$1,790,610

Complete
99.7%
Still to run
$5,306

Claimed & certified

$1,790,610

Certified
$91,321
Unclaimed WIP
$0
Retention held
$2,283

Margin

$247,734 13.8%

Cost of work in place
$1,542,876
Against the build-up
+$4,800
Committed, not received
$0

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 4 tasks · General $198,796 $198,796 100% 1,582 1,592.5 $0 $106 - +$1,091 17%
CC-03 Wall cladding 5 tasks · General $1,274,416 $1,274,416 100% 3,786.4 3,799.4 $468,452 $470,106 - +$2,872 18%
CC-05 Height access & safety systems 1 task · General $170,880 $170,880 100% 960 961.6 $0 $73 - +$223 21%
CC-06 Weatherproofing 2 tasks · General $143,904 $143,904 100% 620.8 623.1 $113,641 $114,017 - +$596 -37%
CC-07 Rectification & defects 1 task · General $7,920 $2,614 33% 60 20 $0 $3 - +$18 14%
Job total $1,795,916 $1,790,610 100% 7,009.2 6,996.6 $582,093 $584,305 $0 +$4,800 14%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $1,542,876, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$198,796 of $198,796 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Site supervision, leading hand RS-PRE-SUP General 132 day 132 100% $164,736 $164,736 1,386 of 1,386
Mobilisation & site establishment RS-PRE-MOB General 1 item 1 100% $18,450 $18,450 96 of 96
Site induction & verification of competency RS-PRE-IND General 14 ea 14 100% $8,190 $8,190 56 of 56
Demobilisation & make good RS-PRE-DEM General 1 item 1 100% $7,420 $7,420 44 of 44
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$1,274,416 of $1,274,416 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Kingspan KS1000 RW insulated panel, install RS-CLD-KSP General 2,940 m² 2,940 100% $817,320 $817,320 2,058 of 2,058
Kingspan KS1000 RW insulated panel, install RS-CLD-KSP · VAR-034-01 General 620 m² 620 100% $172,360 $172,360 434 of 434
Strip existing wall cladding & dispose RS-CLD-STR General 2,940 m² 2,940 100% $142,884 $142,884 793.8 of 793.8
Custom flashings, supply and install RS-CLD-FLA General 980 lm 980 100% $111,720 $111,720 333.2 of 333.2
Strip existing wall cladding & dispose RS-CLD-STR · VAR-034-01 General 620 m² 620 100% $30,132 $30,132 167.4 of 167.4
CC-05 Height access & safety systems Anchor points, static lines, guardrail, rope access and elevated work platforms.
$170,880 of $170,880 · 100%
TaskSub-jobContractDone%ValueEarnedHours
EWP hire & operator, 45ft boom RS-HGT-EWP General 96 day 96 100% $170,880 $170,880 960 of 960
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$143,904 of $143,904 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Sealant to laps, penetrations & flashings RS-WPF-SEA General 2,180 lm 2,180 100% $75,864 $75,864 436 of 436
Liquid-applied weatherproof membrane RS-WPF-MEM General 420 m² 420 100% $68,040 $68,040 184.8 of 184.8
CC-07 Rectification & defects Fastener replacement, sheet repairs and defects liability work.
$2,614 of $7,920 · 33%
TaskSub-jobContractDone%ValueEarnedHours
Defects-liability attendance RS-REC-DEF General 6 day 1.98 33% $7,920 $2,614 19.8 of 60

Correspondence

RFIs, material approvals and anything else sent about QJ1934, with the replies on the same thread.

Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.