QClad
QClad
VAR-006-03 Demo Conveyor gallery access platform, additional static line
Accounting connected Thu 13 Aug 2026
VAR-006-03 Submitted Crew already on it QJ2006

Variation 3, Conveyor gallery access platform, additional static line

PROJECT CERES - UREA SHEDS · Saipem Clough Joint Venture · their reference SCJV-VO-0271

Raised 29 Jul 2026 by Marcus Deng

Effect of approval

These lines join QJ2006's schedule of rates. With 60% of the work already in place, the value of work in place moves with the contract sum, the open progress claim measures the difference, the job's margin recalculates, and an acknowledgement is issued to the head contractor.

Contract sum

$7,497,478 → $7,540,430

Work in place

$3,367,317 → $3,393,088

PC-2026-0196 (Aug 2026)

$343,466 → $369,238

Margin on QJ2006

17.8% → 17.8%

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-HGT-STA Static line system: supply, install & certify $286.00/lm 92 $26,312.00 $21,759.84 17%
RS-HGT-ANC Roof anchor point: supply, install & certify $745.00/ea 8 $5,960.00 $4,958.32 17%
RS-HGT-EWP EWP hire & operator, 45ft boom $1,780.00/day 6 $10,680.00 $8,400.00 21%
Total, ex GST $42,952.00 $35,118.16 18%
GST $4,295.20
Total, inc GST $47,247.20

Why it was raised

The gallery walkway was extended 46m during construction and the original static line no longer reaches the far end.

Lodged 29 Jul 2026, no answer. The crew are 62% through it because the gallery cannot be handed over without it.

Position

Value, ex GST
$42,952.00
Cost to deliver
$35,118.16
Margin
18.2%
Physically built
60%
Value already on the ground
$25,771.20
Work commenced
Yes, under site instruction

Contract

Contract no.
SCJV-CER-SC-1180
Head contractor
Saipem Clough Joint Venture
Approver
Dean Marchetti
Payment terms
45 days EOM
Open claim
PC-2026-0196

Trail

  1. Raised 29 Jul 2026 by Marcus DengPriced off the job's schedule of rates
  2. Lodged with Saipem Clough Joint VentureTheir reference SCJV-VO-0271