Accounting connected Thu 13 Aug 2026
QJ1928 Complete Transport

Coomera Station Re-roof

Queensland Rail · Coomera, Gold Coast, QLD · contract QR-COO-RR-2024-7712

Marcus Deng · 21 Jan 2025 → 24 May 2025 · PC 31 May 2025 · DLP ends 31 May 2026

Client view

Closed out. Defects liability expired 31 May 2026, retention fully released.

The position

Every figure below is the sum of rows on this page.

Contract sum

$769,330

Tendered
$727,900
Approved variations
+$41,430

Work in place

$769,330

Complete
100.0%
Still to run
$0

Claimed & certified

$769,330

Certified
$67,701
Unclaimed WIP
$0
Retention held
$0

Margin

$155,755 20.2%

Cost of work in place
$613,575
Against the build-up
-$11,800
Committed, not received
$0

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 6 tasks · General $295,686 $295,686 100% 2,221 2,149.5 $0 -$754 - -$7,476 24%
CC-02 Roofing 7 tasks · General $440,932 $440,932 100% 1,511.3 1,491.2 $143,284 $141,233 - -$3,941 18%
CC-06 Weatherproofing 1 task · General $32,712 $32,712 100% 188 184.6 $1,842 $1,782 - -$383 22%
Job total $769,330 $769,330 100% 3,920.3 3,825.3 $145,126 $142,262 $0 -$11,800 20%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $613,575, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$295,686 of $295,686 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Rail shutdown premium, night possession RS-PRE-SHT General 14 day 14 100% $166,040 $166,040 1,232 of 1,232
Site supervision, leading hand RS-PRE-SUP General 62 day 62 100% $77,376 $77,376 651 of 651
Rail shutdown premium, night possession RS-PRE-SHT · VAR-028-01 General 2 day 2 100% $23,720 $23,720 176 of 176
Mobilisation & site establishment RS-PRE-MOB General 1 item 1 100% $18,450 $18,450 96 of 96
Demobilisation & make good RS-PRE-DEM General 1 item 1 100% $7,420 $7,420 44 of 44
SWMS, JSA & site-specific safety plan RS-PRE-SWM General 1 item 1 100% $2,680 $2,680 22 of 22
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$440,932 of $440,932 · 100%
TaskSub-jobContractDone%ValueEarnedHours
KLIP-LOK 700 HI-STRENGTH roof sheeting, install RS-ROF-KL7 General 1,420 m² 1,420 100% $182,470 $182,470 511.2 of 511.2
Strip existing roof sheeting & dispose RS-ROF-STR General 1,420 m² 1,420 100% $74,408 $74,408 411.8 of 411.8
Roof insulation blanket 75mm R1.8, install RS-ROF-INS General 1,420 m² 1,420 100% $56,232 $56,232 198.8 of 198.8
Box gutter, supply and install RS-ROF-GUT General 124 lm 124 100% $47,740 $47,740 131.4 of 131.4
Safety mesh, install to purlins RS-ROF-SAF General 1,420 m² 1,420 100% $35,216 $35,216 134.9 of 134.9
Ridge capping & barge, supply and install RS-ROF-RDG General 186 lm 186 100% $27,156 $27,156 74.4 of 74.4
Box gutter, supply and install RS-ROF-GUT · VAR-028-02 General 46 lm 46 100% $17,710 $17,710 48.8 of 48.8
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$32,712 of $32,712 · 100%
TaskSub-jobContractDone%ValueEarnedHours
Sealant to laps, penetrations & flashings RS-WPF-SEA General 940 lm 940 100% $32,712 $32,712 188 of 188

Correspondence

RFIs, material approvals and anything else sent about QJ1928, with the replies on the same thread.

Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.