Variation 2, Wet weather standby, February
Mt Thorley Warkworth Mine Workshop: Roofing & Cladding · Yancoal Australia · their reference YAN-VO-3352
Raised 4 Mar 2026 by Marcus Deng · approved 27 Mar 2026 by Dean Copeland
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-LAB-TRV Travel & living away: per person, per day | $385.00/day | 84 | $32,340.00 | $26,712.00 | 17% |
| RS-PRE-SUP Site supervision, leading hand | $1,248.00/day | 14 | $17,472.00 | $14,490.00 | 17% |
| Total, ex GST | $49,812.00 | $41,202.00 | 17% | ||
| GST | $4,981.20 | ||||
| Total, inc GST | $54,793.20 | ||||
Why it was raised
Fourteen shifts lost to weather with crews in camp; standby claimed under the contract.
Position
- Value, ex GST
- $49,812.00
- Cost to deliver
- $41,202.00
- Margin
- 17.3%
- Physically built
- 100%
- Value already on the ground
- $49,812.00
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2025-036
- Contract no.
- YAN-MTW-WS-2025-6614
- Head contractor
- Yancoal Australia
- Approver
- Dean Copeland
- Payment terms
- 45 days EOM
Trail
- Raised 4 Mar 2026 by Marcus DengPriced off the project schedule of rates
- Lodged with Yancoal AustraliaTheir reference YAN-VO-3352
- Approved 27 Mar 2026Dean Copeland · added to the contract sum and the open claim