VAR-036-02 Demo Wet weather standby, February
Accounting connected Wed 5 Aug 2026
VAR-036-02 Approved PRJ-2025-036

Variation 2, Wet weather standby, February

Mt Thorley Warkworth Mine Workshop: Roofing & Cladding · Yancoal Australia · their reference YAN-VO-3352

Raised 4 Mar 2026 by Marcus Deng · approved 27 Mar 2026 by Dean Copeland

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-LAB-TRV Travel & living away: per person, per day $385.00/day 84 $32,340.00 $26,712.00 17%
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 14 $17,472.00 $14,490.00 17%
Total, ex GST $49,812.00 $41,202.00 17%
GST $4,981.20
Total, inc GST $54,793.20

Why it was raised

Fourteen shifts lost to weather with crews in camp; standby claimed under the contract.

Position

Value, ex GST
$49,812.00
Cost to deliver
$41,202.00
Margin
17.3%
Physically built
100%
Value already on the ground
$49,812.00
Work commenced
Yes, under site instruction

Contract

Contract no.
YAN-MTW-WS-2025-6614
Head contractor
Yancoal Australia
Approver
Dean Copeland
Payment terms
45 days EOM

Trail

  1. Raised 4 Mar 2026 by Marcus DengPriced off the project schedule of rates
  2. Lodged with Yancoal AustraliaTheir reference YAN-VO-3352
  3. Approved 27 Mar 2026Dean Copeland · added to the contract sum and the open claim