Activity Demo 12 entries · 5 unread
Accounting connected Wed 5 Aug 2026

System

Activity

Every mutation in the system writes here: a variation approved, a claim lodged, a purchase order received, a day card submitted. It is the audit trail and the notification feed in the same list, because they are the same thing.

12 shown
Contracts 2026-08-05 08:12

PC-2026-0184, no payment schedule from Rio Tinto

Sixteen business days since lodgement on the Boyne Smelters claim. Under s.76 of the BIF Act, Rio Tinto are now liable for the full claimed amount of $244,000. The notice is drafted and awaiting director sign-off.

Contracts 2026-08-05 07:44

VAR-041-04 unapproved, crew already on it

Lindum static line and anchors, $76,470 ex GST. Crew 1 started 27 July on a verbal instruction. Largest unapproved exposure on the book.

Safety 2026-08-05 06:30

Three height tickets expire inside 30 days

Tyrone Baker (Working at Heights, 19 Aug), Kirk Danaher (EWP over 11m, 27 Aug) and Brett Hallam (IRATA Level 1, 1 Sep). All three are rostered on site next week.

Supply 2026-08-04 16:20

KingKlip 700 below minimum

312 m² on hand against a 350 m² minimum, and 300 m² already allocated to M&A Stage 3. PO-2026-0329 lands 14 Aug, 18-day lead from Adelaide.

Finance 2026-08-04 14:02

INV-26-0398 paid: $683,164 inc GST

Laing O'Rourke settled the June QRSAUP claim on 4 Aug, one day inside the BIF window.

Site 2026-08-05 05:48

Crew 2 clocked on at Saraji, 11 of 12

Kirk Danaher marked off site: EWP ticket verification pending. Mitch Ravenscroft has him on the ground until it clears.

Contracts 2026-08-04 11:15

PC-2026-0185 short certified by $2,500

Laing O'Rourke disallowed part of the July shutdown premium pending the possession log. Janelle has the log and is responding today.

Safety 2026-08-03 15:40

Incident INC-2026-018 open: dropped object, Morningside

A 1.2 m offcut fell 4 m inside the exclusion zone on 31 Jul. No injury. ICAM under way, corrective actions due 12 Aug.

Supply 2026-08-04 09:26

PO-2026-0337 part received at Saraji

Lysaght short-shipped 160 m² of KLIP-LOK 700. Balance confirmed on the 6 Aug run, no programme impact.

Contracts 2026-08-01 10:05

Bengalla Stage 2 awarded, $1.28M ex GST

T-2026-0122 converted to PRJ-2026-049 on 21 Jul. Stage 1 in 2023 is why this came back without a competitive tender.

Supply 2026-07-31 13:18

Coral Coast Labour Hire suspended

WorkCover certificate lapsed 24 Jul. Their crew is off site and SCC-2026-0203 is on hold until it is reinstated.

System 2026-08-05 09:14

Xero sync completed, 18 documents

Sixteen invoices and two credit notes pushed at 09:14. No exceptions.