QClad
QClad
VAR-044-04 Demo Second personnel door, eastern elevation
Accounting connected Wed 5 Aug 2026
VAR-044-04 Approved PRJ-2026-044

Variation 4, Second personnel door, eastern elevation

BMA Saraji Workshop Upgrade: Cladding · BHP Mitsubishi Alliance · their reference BMA-VO-2291

Raised 16 Jul 2026 by Cameron Doyle · approved 28 Jul 2026 by Warren Idle

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-CLD-DOR Personnel access door in cladding, form and trim $1,840.00/ea 1 $1,840.00 $1,220.39 34%
Total, ex GST $1,840.00 $1,220.39 34%
GST $184.00
Total, inc GST $2,024.00

Why it was raised

Site requested an additional access door after the layout changed.

Position

Value, ex GST
$1,840.00
Cost to deliver
$1,220.39
Margin
33.7%
Physically built
12%
Value already on the ground
$220.80
Work commenced
No

Contract

Contract no.
BMA-SAR-2026-1187
Head contractor
BHP Mitsubishi Alliance
Approver
Warren Idle
Payment terms
45 days EOM

Trail

  1. Raised 16 Jul 2026 by Cameron DoylePriced off the project schedule of rates
  2. Lodged with BHP Mitsubishi AllianceTheir reference BMA-VO-2291
  3. Approved 28 Jul 2026Warren Idle · added to the contract sum and the open claim