Variation 4, Second personnel door, eastern elevation
BMA Saraji Workshop Upgrade: Cladding · BHP Mitsubishi Alliance · their reference BMA-VO-2291
Raised 16 Jul 2026 by Cameron Doyle · approved 28 Jul 2026 by Warren Idle
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-CLD-DOR Personnel access door in cladding, form and trim | $1,840.00/ea | 1 | $1,840.00 | $1,220.39 | 34% |
| Total, ex GST | $1,840.00 | $1,220.39 | 34% | ||
| GST | $184.00 | ||||
| Total, inc GST | $2,024.00 | ||||
Why it was raised
Site requested an additional access door after the layout changed.
Position
- Value, ex GST
- $1,840.00
- Cost to deliver
- $1,220.39
- Margin
- 33.7%
- Physically built
- 12%
- Value already on the ground
- $220.80
- Work commenced
- No
Contract
- Project
- PRJ-2026-044
- Contract no.
- BMA-SAR-2026-1187
- Head contractor
- BHP Mitsubishi Alliance
- Approver
- Warren Idle
- Payment terms
- 45 days EOM
Trail
- Raised 16 Jul 2026 by Cameron DoylePriced off the project schedule of rates
- Lodged with BHP Mitsubishi AllianceTheir reference BMA-VO-2291
- Approved 28 Jul 2026Warren Idle · added to the contract sum and the open claim