VAR-044-01 Demo Corroded purlin replacement, bays 4 to 9
Accounting connected Wed 5 Aug 2026
VAR-044-01 Approved PRJ-2026-044

Variation 1, Corroded purlin replacement, bays 4 to 9

BMA Saraji Workshop Upgrade: Cladding · BHP Mitsubishi Alliance · their reference BMA-VO-2211

Raised 15 Apr 2026 by Cameron Doyle · approved 6 May 2026 by Warren Idle

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-CLD-PUR Purlin & girt, supply and install $7,620.00/t 4.8 $36,576.00 $30,318.34 17%
Total, ex GST $36,576.00 $30,318.34 17%
GST $3,657.60
Total, inc GST $40,233.60

Why it was raised

Six bays of purlin found beyond repair once the cladding came off. Latent condition.

Position

Value, ex GST
$36,576.00
Cost to deliver
$30,318.34
Margin
17.1%
Physically built
86%
Value already on the ground
$31,455.36
Work commenced
Yes, under site instruction

Contract

Contract no.
BMA-SAR-2026-1187
Head contractor
BHP Mitsubishi Alliance
Approver
Warren Idle
Payment terms
45 days EOM

Trail

  1. Raised 15 Apr 2026 by Cameron DoylePriced off the project schedule of rates
  2. Lodged with BHP Mitsubishi AllianceTheir reference BMA-VO-2211
  3. Approved 6 May 2026Warren Idle · added to the contract sum and the open claim