VAR-044-01 Demo Corroded purlin replacement, bays 4 to 9
Accounting connected Thu 13 Aug 2026
VAR-044-01 Approved QJ2044

Variation 1, Corroded purlin replacement, bays 4 to 9

BMA Saraji Workshop Upgrade: Cladding · BHP Mitsubishi Alliance · their reference BMA-VO-2211

Raised 23 Apr 2026 by Cameron Hale · approved 14 May 2026 by Warren Idle

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-CLD-PUR Purlin & girt, supply and install $7,620.00/t 4.8 $36,576.00 $30,318.34 17%
Total, ex GST $36,576.00 $30,318.34 17%
GST $3,657.60
Total, inc GST $40,233.60

Why it was raised

Six bays of purlin found beyond repair once the cladding came off. Latent condition.

Position

Value, ex GST
$36,576.00
Cost to deliver
$30,318.34
Margin
17.1%
Physically built
86%
Value already on the ground
$31,455.36
Work commenced
Yes, under site instruction

Contract

Contract no.
BMA-SAR-2026-1187
Head contractor
BHP Mitsubishi Alliance
Approver
Warren Idle
Payment terms
45 days EOM

Trail

  1. Raised 23 Apr 2026 by Cameron HalePriced off the job's schedule of rates
  2. Lodged with BHP Mitsubishi AllianceTheir reference BMA-VO-2211
  3. Approved 14 May 2026Warren Idle · added to the contract sum and the open claim