VAR-034-01 Demo Panel colour change, full northern elevation
Accounting connected Wed 5 Aug 2026
VAR-034-01 Approved PRJ-2025-034

Variation 1, Panel colour change, full northern elevation

Williamtown RAAF: NACC Hangar Cladding Renewal · Department of Defence, Estate & Infrastructure · their reference DEF-VO-0918

Raised 19 Aug 2025 by Marcus Deng · approved 9 Sep 2025 by Maj. Ellen Straub

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-CLD-KSP Kingspan KS1000 RW insulated panel, install $278.00/m² 620 $172,360.00 $137,522.20 20%
RS-CLD-STR Strip existing wall cladding & dispose $48.60/m² 620 $30,132.00 $27,893.80 7%
Total, ex GST $202,492.00 $165,416.00 18%
GST $20,249.20
Total, inc GST $222,741.20

Why it was raised

Defence changed the colour after 40% of the panel was on the wall.

Position

Value, ex GST
$202,492.00
Cost to deliver
$165,416.00
Margin
18.3%
Physically built
100%
Value already on the ground
$202,492.00
Work commenced
Yes, under site instruction

Contract

Contract no.
DEF-EI-WLM-NACC-8804
Head contractor
Department of Defence, Estate & Infrastructure
Approver
Maj. Ellen Straub
Payment terms
30 days

Trail

  1. Raised 19 Aug 2025 by Marcus DengPriced off the project schedule of rates
  2. Lodged with Department of Defence, Estate & InfrastructureTheir reference DEF-VO-0918
  3. Approved 9 Sep 2025Maj. Ellen Straub · added to the contract sum and the open claim