QJ2042 Demo Village Building: Fyshwick Warehouse Re-roof
Accounting connected Thu 13 Aug 2026
QJ2042 On hold Commercial

Village Building: Fyshwick Warehouse Re-roof

Village Building Co. · Fyshwick, ACT, NSW · contract VIL-FYS-RR-2026-0117

Cameron Hale · 14 Jul 2026 → 21 Nov 2026

Client view

On hold at the client's request while the tenant fit-out is re-scoped. Material ordered and held at Landsborough, carrying cost sits against this job.

The position

Every figure below is the sum of rows on this page.

Contract sum

$826,722

Tendered
$826,722
Approved variations
+$0
Lodged, not approved
$4,992

Work in place

$17,248

Complete
2.1%
Still to run
$809,474

Claimed & certified

$17,248

Certified
$0
Unclaimed WIP
$0
Retention held
$0

Margin

$1,049 6.1%

Cost of work in place
$16,199
Against the build-up
+$1,860
Committed, not received
$0

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 4 tasks · General $118,406 $17,248 15% 918 136.6 $0 $386 - +$1,860 6%
CC-02 Roofing 5 tasks · General $651,244 $0 0% 2,411.2 0 $0 $0 $157,080 $0 0%
CC-06 Weatherproofing 1 task · General $57,072 $0 0% 328 0 $0 $0 - $0 0%
Job total $826,722 $17,248 2% 3,657.2 136.6 $0 $386 $157,080 +$1,860 6%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $16,199, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$17,248 of $118,406 · 15%
TaskSub-jobContractDone%ValueEarnedHours
Site supervision, leading hand RS-PRE-SUP General 72 day 5.76 8% $89,856 $7,188 60.5 of 756
Mobilisation & site establishment RS-PRE-MOB General 1 item 0.4 40% $18,450 $7,380 38.4 of 96
Demobilisation & make good RS-PRE-DEM General 1 item 0 0% $7,420 $0 0 of 44
SWMS, JSA & site-specific safety plan RS-PRE-SWM General 1 item 1 100% $2,680 $2,680 22 of 22
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$0 of $651,244 · 0%
TaskSub-jobContractDone%ValueEarnedHours
TRIMDEK roof sheeting, install RS-ROF-TRM General 2,640 m² 0 0% $258,192 $0 0 of 792
Strip existing roof sheeting & dispose RS-ROF-STR General 2,640 m² 0 0% $138,336 $0 0 of 765.6
Roof insulation blanket 75mm R1.8, install RS-ROF-INS General 2,640 m² 0 0% $104,544 $0 0 of 369.6
Box gutter, supply and install RS-ROF-GUT General 220 lm 0 0% $84,700 $0 0 of 233.2
Safety mesh, install to purlins RS-ROF-SAF General 2,640 m² 0 0% $65,472 $0 0 of 250.8
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$0 of $57,072 · 0%
TaskSub-jobContractDone%ValueEarnedHours
Sealant to laps, penetrations & flashings RS-WPF-SEA General 1,640 lm 0 0% $57,072 $0 0 of 328

Correspondence

RFIs, material approvals and anything else sent about QJ2042, with the replies on the same thread.

Nothing sent about this job yetAn RFI or a material approval sent from here keeps its whole thread against the job.