These lines join QJ2041's schedule of rates. With no work yet started,
the value of work in place moves with the contract sum, the open progress claim measures the difference, the job's margin recalculates,
and an acknowledgement is issued to the head contractor.
Contract sum
$4,093,279 → $4,080,607
Work in place
$2,499,553 → $2,499,553
PC-2026-0187 (Aug 2026)
$112,480 → $112,480
Margin on QJ2041
18.3%
→ 18.3%
Scope
Priced off the pricing schedule the contract is measured against.
Rate
Rate, ex GST
Qty
Value
Cost
Margin
RS-ROF-SKYFibreglass roof lighting, install
$198.00/m²
-64
-$12,672.00
-$10,834.56
-
Total, ex GST
-$12,672.00
-$10,834.56
0%
GST
-$1,267.20
Total, inc GST
-$13,939.20
Why it was raised
Client deleted the roof lighting to the Buranda canopy after a daylight study.