Variation 5, Buranda: deletion of platform canopy roof lighting
QRSAUP: Brisbane Rail Stations Roofing & Cladding · Laing O'Rourke Australia
Raised 30 Jul 2026 by Janelle Roe
Effect of approval
These lines join PRJ-2026-041's schedule of rates. With no work yet started, the value of work in place moves with the contract sum, the open progress claim measures the difference, the job's margin recalculates, and an acknowledgement is issued to the head contractor.
Contract sum
$4,093,279 → $4,080,607
Work in place
$2,499,553 → $2,499,553
PC-2026-0187 (Aug 2026)
$112,480 → $112,480
Margin on PRJ-2026-041
18.3% → 18.3%
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-ROF-SKY Fibreglass roof lighting, install | $198.00/m² | -64 | -$12,672.00 | -$10,834.56 | - |
| Total, ex GST | -$12,672.00 | -$10,834.56 | 0% | ||
| GST | -$1,267.20 | ||||
| Total, inc GST | -$13,939.20 | ||||
Why it was raised
Client deleted the roof lighting to the Buranda canopy after a daylight study.
Position
- Value, ex GST
- -$12,672.00
- Cost to deliver
- -$10,834.56
- Margin
- 0.0%
- Physically built
- 0%
- Value already on the ground
- -$0.00
- Work commenced
- No
Contract
- Project
- PRJ-2026-041
- Contract no.
- LOR-QRSAUP-SC-0442
- Head contractor
- Laing O'Rourke Australia
- Approver
- Steve Bracken
- Payment terms
- BIF 15/25
- Open claim
- PC-2026-0187
Trail
- Raised 30 Jul 2026 by Janelle RoePriced off the project schedule of rates