Variation 2, Extended possession, three additional night shutdowns
QRSAUP: Brisbane Rail Stations Roofing & Cladding · Laing O'Rourke Australia · their reference LOR-VO-0141
Raised 8 Apr 2026 by Marcus Deng · approved 24 Apr 2026 by Steve Bracken
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-PRE-SHT Rail shutdown premium, night possession | $11,860.00/day | 3 | $35,580.00 | $27,036.00 | 24% |
| Total, ex GST | $35,580.00 | $27,036.00 | 24% | ||
| GST | $3,558.00 | ||||
| Total, inc GST | $39,138.00 | ||||
Why it was raised
QR granted three fewer possessions than programmed; the recovery required three additional night shifts.
Position
- Value, ex GST
- $35,580.00
- Cost to deliver
- $27,036.00
- Margin
- 24.0%
- Physically built
- 86%
- Value already on the ground
- $30,598.80
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2026-041
- Contract no.
- LOR-QRSAUP-SC-0442
- Head contractor
- Laing O'Rourke Australia
- Approver
- Steve Bracken
- Payment terms
- BIF 15/25
- Open claim
- PC-2026-0187
Trail
- Raised 8 Apr 2026 by Marcus DengPriced off the project schedule of rates
- Lodged with Laing O'Rourke AustraliaTheir reference LOR-VO-0141
- Approved 24 Apr 2026Steve Bracken · added to the contract sum and the open claim