VAR-038-04 Demo Additional shutdown attendance, July window
Accounting connected Wed 5 Aug 2026
VAR-038-04 Draft Crew already on it PRJ-2026-038

Variation 4, Additional shutdown attendance, July window

Boyne Smelters Stockpile Shed: Re-clad & Acoustics · Rio Tinto Aluminium

Raised 27 Jul 2026 by Marcus Deng

Effect of approval

These lines join PRJ-2026-038's schedule of rates. With 60% of the work already in place, the value of work in place moves with the contract sum, the open progress claim measures the difference, the job's margin recalculates, and an acknowledgement is issued to the head contractor.

Contract sum

$2,650,824 → $2,663,847

Work in place

$2,050,266 → $2,058,080

Next claim

$0 → $7,814

Margin on PRJ-2026-038

15.2% → 15.2%

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 6 $7,488.00 $6,210.00 17%
RS-PRE-MOB Mobilisation & site establishment $18,450.00/item 0.3 $5,535.00 $4,567.20 17%
Total, ex GST $13,023.00 $10,777.20 17%
GST $1,302.30
Total, inc GST $14,325.30

Why it was raised

Rio Tinto brought the July shutdown forward by nine days; crew remobilised.

Position

Value, ex GST
$13,023.00
Cost to deliver
$10,777.20
Margin
17.2%
Physically built
60%
Value already on the ground
$7,813.80
Work commenced
Yes, under site instruction

Contract

Contract no.
RTA-BSL-SC-88104
Head contractor
Rio Tinto Aluminium
Approver
Grant Hollows
Payment terms
45 days EOM

Trail

  1. Raised 27 Jul 2026 by Marcus DengPriced off the project schedule of rates