QClad
QClad
VAR-039-02 Demo Wash bay roof lighting replacement
Accounting connected Thu 13 Aug 2026
VAR-039-02 Approved QJ2039

Variation 2, Wash bay roof lighting replacement

Groote Island: Mobile Plant Workshop Re-roof · Groote Eylandt Mining Company · their reference GEM-VO-0124

Raised 14 Jul 2026 by Cameron Hale · approved 30 Jul 2026 by Warrick Delaney

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-ROF-SKY Fibreglass roof lighting, install $198.00/m² 186 $36,828.00 $31,487.94 14%
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 240 $8,352.00 $6,631.20 21%
Total, ex GST $45,180.00 $38,119.14 16%
GST $4,518.00
Total, inc GST $49,698.00

Why it was raised

Existing fibreglass sheeting found brittle and unsafe to walk on. Replacement was not in the scope.

Position

Value, ex GST
$45,180.00
Cost to deliver
$38,119.14
Margin
15.6%
Physically built
86%
Value already on the ground
$38,854.80
Work commenced
Yes, under site instruction

Contract

Contract no.
S32-GEM-2026-0918
Head contractor
Groote Eylandt Mining Company
Approver
Warrick Delaney
Payment terms
45 days EOM
Open claim
PC-2026-0197

Trail

  1. Raised 14 Jul 2026 by Cameron HalePriced off the job's schedule of rates
  2. Lodged with Groote Eylandt Mining CompanyTheir reference GEM-VO-0124
  3. Approved 30 Jul 2026Warrick Delaney · added to the contract sum and the open claim