VAR-036-03 Demo Additional roof anchors to the crane runway
Accounting connected Wed 5 Aug 2026
VAR-036-03 Approved PRJ-2025-036

Variation 3, Additional roof anchors to the crane runway

Mt Thorley Warkworth Mine Workshop: Roofing & Cladding · Yancoal Australia · their reference YAN-VO-3371

Raised 22 Apr 2026 by Marcus Deng · approved 8 May 2026 by Dean Copeland

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-HGT-ANC Roof anchor point: supply, install & certify $745.00/ea 22 $16,390.00 $13,635.38 17%
RS-HGT-STA Static line system: supply, install & certify $286.00/lm 96 $27,456.00 $22,705.92 17%
Total, ex GST $43,846.00 $36,341.30 17%
GST $4,384.60
Total, inc GST $48,230.60

Why it was raised

Yancoal added anchors along the runway for future maintenance access.

Position

Value, ex GST
$43,846.00
Cost to deliver
$36,341.30
Margin
17.1%
Physically built
100%
Value already on the ground
$43,846.00
Work commenced
Yes, under site instruction

Contract

Contract no.
YAN-MTW-WS-2025-6614
Head contractor
Yancoal Australia
Approver
Dean Copeland
Payment terms
45 days EOM

Trail

  1. Raised 22 Apr 2026 by Marcus DengPriced off the project schedule of rates
  2. Lodged with Yancoal AustraliaTheir reference YAN-VO-3371
  3. Approved 8 May 2026Dean Copeland · added to the contract sum and the open claim