VAR-044-02 Demo Additional louvre panels to the wash bay
Accounting connected Wed 5 Aug 2026
VAR-044-02 Approved PRJ-2026-044

Variation 2, Additional louvre panels to the wash bay

BMA Saraji Workshop Upgrade: Cladding · BHP Mitsubishi Alliance · their reference BMA-VO-2248

Raised 28 May 2026 by Cameron Doyle · approved 11 Jun 2026 by Warren Idle

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-CLD-LOU Weatherproof louvre panel, install $346.00/m² 42 $14,532.00 $13,137.60 10%
RS-CLD-FLA Custom flashings, supply and install $114.00/lm 86 $9,804.00 $7,955.00 19%
Total, ex GST $24,336.00 $21,092.60 13%
GST $2,433.60
Total, inc GST $26,769.60

Why it was raised

BMA added ventilation to the wash bay after a hygiene assessment.

Position

Value, ex GST
$24,336.00
Cost to deliver
$21,092.60
Margin
13.3%
Physically built
86%
Value already on the ground
$20,928.96
Work commenced
Yes, under site instruction

Contract

Contract no.
BMA-SAR-2026-1187
Head contractor
BHP Mitsubishi Alliance
Approver
Warren Idle
Payment terms
45 days EOM

Trail

  1. Raised 28 May 2026 by Cameron DoylePriced off the project schedule of rates
  2. Lodged with BHP Mitsubishi AllianceTheir reference BMA-VO-2248
  3. Approved 11 Jun 2026Warren Idle · added to the contract sum and the open claim