Variation 2, Additional louvre panels to the wash bay
BMA Saraji Workshop Upgrade: Cladding · BHP Mitsubishi Alliance · their reference BMA-VO-2248
Raised 28 May 2026 by Cameron Doyle · approved 11 Jun 2026 by Warren Idle
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-CLD-LOU Weatherproof louvre panel, install | $346.00/m² | 42 | $14,532.00 | $13,137.60 | 10% |
| RS-CLD-FLA Custom flashings, supply and install | $114.00/lm | 86 | $9,804.00 | $7,955.00 | 19% |
| Total, ex GST | $24,336.00 | $21,092.60 | 13% | ||
| GST | $2,433.60 | ||||
| Total, inc GST | $26,769.60 | ||||
Why it was raised
BMA added ventilation to the wash bay after a hygiene assessment.
Position
- Value, ex GST
- $24,336.00
- Cost to deliver
- $21,092.60
- Margin
- 13.3%
- Physically built
- 86%
- Value already on the ground
- $20,928.96
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2026-044
- Contract no.
- BMA-SAR-2026-1187
- Head contractor
- BHP Mitsubishi Alliance
- Approver
- Warren Idle
- Payment terms
- 45 days EOM
Trail
- Raised 28 May 2026 by Cameron DoylePriced off the project schedule of rates
- Lodged with BHP Mitsubishi AllianceTheir reference BMA-VO-2248
- Approved 11 Jun 2026Warren Idle · added to the contract sum and the open claim