QJ2046 Demo Downer Rail Maryborough: Periodic Roofing Works 2026
Accounting connected Thu 13 Aug 2026
QJ2046 On site Industrial

Downer Rail Maryborough: Periodic Roofing Works 2026

Downer Rail · Downer Rail, Maryborough, QLD · contract DWN-MBH-PER-2026

Cameron Hale · 10 Feb 2026 → 26 Dec 2026

Client view

Periodic works, ongoing since 2012, the longest-running relationship on the book. Called off shed by shed against a standing schedule of rates.

The position

Every figure below is the sum of rows on this page.

Contract sum

$807,398

Tendered
$772,216
Approved variations
+$35,182
Lodged, not approved
$17,120

Work in place

$483,937

Complete
59.9%
Still to run
$323,461

Claimed & certified

$463,612

Certified
$241,969
Unclaimed WIP
$20,325
Retention held
$12,098

Margin

$75,840 15.7%

Cost of work in place
$408,098
Against the build-up
-$6,400
Committed, not received
$0

Cost centres

Hours and material book to a cost centre, and so do purchase orders. The totals here are the job, to the cent.

Cost centre Value Earned % Budget hrs Actual hrs Budget material Actual material Committed Run Margin
CC-01 Preliminaries & establishment 1 task · General $119,808 $69,489 58% 1,008 569.6 $0 -$69 - -$1,482 19%
CC-02 Roofing 6 tasks · General $305,158 $185,116 61% 1,054.9 642.6 $61,373 $60,650 - -$1,372 14%
CC-03 Wall cladding 1 task · General $47,880 $24,898 52% 142.8 73.3 $9,677 $9,554 - -$216 20%
CC-05 Height access & safety systems 1 task · General $131,720 $77,715 59% 740 433.8 $0 -$129 - -$393 22%
CC-06 Weatherproofing 3 tasks · General $92,808 $52,049 56% 442.6 251.7 $2,864 $2,717 - -$449 28%
CC-07 Rectification & defects 2 tasks · General $110,024 $74,672 68% 537 355.9 $29,218 $28,118 - -$2,488 -0%
Job total $807,398 $483,937 60% 3,925.3 2,326.9 $103,132 $100,840 $0 -$6,400 16%

The run is this job's cost against budget, spread across the centres by exposure: preliminaries and rectification carry more of it than sheeting to a measured rate, because that is where jobs actually bleed. The centres add to $408,098, which is the job's actual cost.

CC-01 Preliminaries & establishment Mobilisation, supervision, inductions, safety documentation, scaffold and access hire.
$69,489 of $119,808 · 58%
TaskSub-jobContractDone%ValueEarnedHours
Site supervision, leading hand RS-PRE-SUP General 96 day 55.68 58% $119,808 $69,489 584.6 of 1,008
CC-02 Roofing Strip, sheet, insulate, safety mesh, ridge, gutter, downpipes and roof lighting.
$185,116 of $305,158 · 61%
TaskSub-jobContractDone%ValueEarnedHours
TRIMDEK roof sheeting, install RS-ROF-TRM General 1,240 m² 756.4 61% $121,272 $73,976 226.9 of 372
Strip existing roof sheeting & dispose RS-ROF-STR General 1,240 m² 818.4 66% $64,976 $42,884 237.3 of 359.6
Box gutter, supply and install RS-ROF-GUT General 148 lm 69.56 47% $56,980 $26,781 73.7 of 156.9
Fibreglass roof lighting, install RS-ROF-SKY General 186 m² 100.44 54% $36,828 $19,887 53.2 of 98.6
Fibreglass roof lighting, install RS-ROF-SKY · VAR-046-02 General 84 m² 72.24 86% $16,632 $14,304 38.3 of 44.5
Box gutter, supply and install RS-ROF-GUT · VAR-046-01 General 22 lm 18.92 86% $8,470 $7,284 20.1 of 23.3
CC-03 Wall cladding Wall sheet, insulated panel, architectural cladding, flashings and cappings.
$24,898 of $47,880 · 52%
TaskSub-jobContractDone%ValueEarnedHours
Custom flashings, supply and install RS-CLD-FLA General 420 lm 218.4 52% $47,880 $24,898 74.3 of 142.8
CC-05 Height access & safety systems Anchor points, static lines, guardrail, rope access and elevated work platforms.
$77,715 of $131,720 · 59%
TaskSub-jobContractDone%ValueEarnedHours
EWP hire & operator, 45ft boom RS-HGT-EWP General 74 day 43.66 59% $131,720 $77,715 436.6 of 740
CC-06 Weatherproofing Sealing, membrane, penetration flashing and leak rectification.
$52,049 of $92,808 · 56%
TaskSub-jobContractDone%ValueEarnedHours
Roof penetration flashing, form & seal RS-WPF-PEN General 62 ea 31 50% $42,408 $21,204 71.3 of 142.6
Leak investigation & rectification RS-WPF-LEK General 240 hr 132 55% $40,320 $22,176 132 of 240
Leak investigation & rectification RS-WPF-LEK · VAR-046-01 General 60 hr 51.6 86% $10,080 $8,669 51.6 of 60
CC-07 Rectification & defects Fastener replacement, sheet repairs and defects liability work.
$74,672 of $110,024 · 68%
TaskSub-jobContractDone%ValueEarnedHours
Replace corroded fasteners RS-REC-FAS General 4,800 ea 3,456 72% $59,520 $42,854 259.2 of 360
Replace individual damaged sheet RS-REC-SHT General 118 ea 74.34 63% $50,504 $31,818 111.5 of 177