VAR-031-02 Demo Security escort standby, 11 days
Accounting connected Wed 5 Aug 2026
VAR-031-02 Approved PRJ-2025-031

Variation 2, Security escort standby, 11 days

Damascus Barracks B004: Cladding Rectification · Department of Defence, Estate & Infrastructure · their reference DEF-VO-1131

Raised 24 Nov 2025 by Cameron Doyle · approved 16 Dec 2025 by Maj. Ellen Straub

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-PRE-SUP Site supervision, leading hand $1,248.00/day 11 $13,728.00 $11,385.00 17%
RS-LAB-STD Cladding installer, ordinary hours $114.00/hr 484 $55,176.00 $45,496.00 18%
Total, ex GST $68,904.00 $56,881.00 17%
GST $6,890.40
Total, inc GST $75,794.40

Why it was raised

Escorted access required for the eastern zone; crew productivity halved.

Position

Value, ex GST
$68,904.00
Cost to deliver
$56,881.00
Margin
17.4%
Physically built
100%
Value already on the ground
$68,904.00
Work commenced
Yes, under site instruction

Contract

Contract no.
DEF-EI-DAM-B004-9921
Head contractor
Department of Defence, Estate & Infrastructure
Approver
Maj. Ellen Straub
Payment terms
30 days

Trail

  1. Raised 24 Nov 2025 by Cameron DoylePriced off the project schedule of rates
  2. Lodged with Department of Defence, Estate & InfrastructureTheir reference DEF-VO-1131
  3. Approved 16 Dec 2025Maj. Ellen Straub · added to the contract sum and the open claim