Variation 2, Security escort standby, 11 days
Damascus Barracks B004: Cladding Rectification · Department of Defence, Estate & Infrastructure · their reference DEF-VO-1131
Raised 24 Nov 2025 by Cameron Doyle · approved 16 Dec 2025 by Maj. Ellen Straub
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-PRE-SUP Site supervision, leading hand | $1,248.00/day | 11 | $13,728.00 | $11,385.00 | 17% |
| RS-LAB-STD Cladding installer, ordinary hours | $114.00/hr | 484 | $55,176.00 | $45,496.00 | 18% |
| Total, ex GST | $68,904.00 | $56,881.00 | 17% | ||
| GST | $6,890.40 | ||||
| Total, inc GST | $75,794.40 | ||||
Why it was raised
Escorted access required for the eastern zone; crew productivity halved.
Position
- Value, ex GST
- $68,904.00
- Cost to deliver
- $56,881.00
- Margin
- 17.4%
- Physically built
- 100%
- Value already on the ground
- $68,904.00
- Work commenced
- Yes, under site instruction
Contract
- Project
- PRJ-2025-031
- Contract no.
- DEF-EI-DAM-B004-9921
- Head contractor
- Department of Defence, Estate & Infrastructure
- Approver
- Maj. Ellen Straub
- Payment terms
- 30 days
Trail
- Raised 24 Nov 2025 by Cameron DoylePriced off the project schedule of rates
- Lodged with Department of Defence, Estate & InfrastructureTheir reference DEF-VO-1131
- Approved 16 Dec 2025Maj. Ellen Straub · added to the contract sum and the open claim