QClad
QClad
VAR-045-02 Demo Spider lift extended hire, 3 weeks
Accounting connected Wed 5 Aug 2026
VAR-045-02 Submitted Crew already on it PRJ-2026-045

Variation 2, Spider lift extended hire, 3 weeks

M&A Apartments Stage 3: Facade Cladding · M&A Developments · their reference MAA-VO-0038

Raised 23 Jul 2026 by Cameron Doyle

Effect of approval

These lines join PRJ-2026-045's schedule of rates. With 60% of the work already in place, the value of work in place moves with the contract sum, the open progress claim measures the difference, the job's margin recalculates, and an acknowledgement is issued to the head contractor.

Contract sum

$1,090,514 → $1,125,914

Work in place

$564,473 → $585,713

Next claim

$0 → $21,240

Margin on PRJ-2026-045

9.9% → 10.2%

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-HGT-SPI Spider lift hire & operator, 28m $2,360.00/day 15 $35,400.00 $28,500.00 19%
Total, ex GST $35,400.00 $28,500.00 19%
GST $3,540.00
Total, inc GST $38,940.00

Why it was raised

Programme slip on the preceding trade left the lift on site three weeks longer.

Position

Value, ex GST
$35,400.00
Cost to deliver
$28,500.00
Margin
19.5%
Physically built
60%
Value already on the ground
$21,240.00
Work commenced
Yes, under site instruction

Contract

Contract no.
MAA-S3-CL-2026-0088
Head contractor
M&A Developments
Approver
Jordan Ellul
Payment terms
30 days

Trail

  1. Raised 23 Jul 2026 by Cameron DoylePriced off the project schedule of rates
  2. Lodged with M&A DevelopmentsTheir reference MAA-VO-0038