Schedule Demo 15 live jobs · 26 weeks
Accounting connected Thu 13 Aug 2026

Jobs

Schedule

The programme across the next six months and the crew allocation behind it. Every bar comes off the contract dates on the job, so moving a finish date moves the schedule rather than a second copy of it.

Live jobs

15

$34.5M of contracts

Starting inside 60 days

2

need crew and material

Finishing inside 60 days

3

crew comes free

On site without a crew

4

run on subcontract labour

Programme

Week commencing 10 Aug 2026 to 8 Feb 2027. The dark line is today.

On siteAwardedPractical completionDefects liabilityOn hold
Aug
Sept
Oct
Nov
Dec
Jan
Feb
Today
QJ2006 PROJECT CERES - UREA SHEDS Saipem Clough Joint Venture · Crew 3, FIFO West · 21/7
45% · $7.50M
QJ2039 Groote Island: Mobile Plant Workshop Re-roof Groote Eylandt Mining Company · Crew 4, FIFO North · 21/7
56% · $3.08M
QJ2046 Downer Rail Maryborough: Periodic Roofing Works 2026 Downer Rail
60% · $807k
QJ2041 QRSAUP: Brisbane Rail Stations Roofing & Cladding Laing O'Rourke Australia · Crew 1, Rail
61% · $4.09M
QJ2045 M&A Apartments Stage 3: Facade Cladding M&A Developments · subcontract labour
52% · $1.09M
QJ2047 Mountain Creek SHS: Hall Re-roof & Cladding Mountain Creek State High School, Dept of Education · subcontract labour
48% · $967k
QJ2044 BMA Saraji Workshop Upgrade: Cladding BHP Mitsubishi Alliance · Crew 2, Bowen Basin
71% · $2.53M
QJ2038 Boyne Smelters Stockpile Shed: Re-clad & Acoustics Rio Tinto Aluminium · subcontract labour
77% · $2.65M
QJ2049 Bengalla VDC Re-roof Stage 2 Bengalla Mining Company
1% · $1.78M
QJ2050 QCLNG Train 2: Acoustic Enclosure Refit Australia Pacific LNG
0% · $1.16M
QJ2042 Village Building: Fyshwick Warehouse Re-roof Village Building Co.
2% · $827k
QJ1936 Mt Thorley Warkworth Mine Workshop: Roofing & Cladding Yancoal Australia
100% · $2.72M
QJ1939 McNab: Yatala Cold Store Insulated Panel McNab Constructions
100% · $1.99M
QJ1931 Damascus Barracks B004: Cladding Rectification Department of Defence, Estate & Infrastructure
100% · $1.49M
QJ1934 Williamtown RAAF: NACC Hangar Cladding Renewal Department of Defence, Estate & Infrastructure
100% · $1.80M

Crew allocation

Where each crew is, on what roster, and how many flights that costs.

CrewLeading handRosterJobSiteContractCompleteFlights bookedRuns to
Crew 1, Rail Blake Tuiala 5 on, 2 off QJ2041 Banyo, Buranda, Morningside & Lindum stations $4,093,279 61% - 5 Dec 2026
Crew 2, Bowen Basin Mitch Ravenscroft 14 on, 7 off QJ2044 Saraji Mine, Dysart $2,533,376 71% 3 3 Oct 2026
Crew 3, FIFO West Zeb Marchetti 21 on, 7 off QJ2006 Ceres urea plant, Karratha $7,497,478 45% 15 3 Apr 2027
Crew 4, FIFO North Dom Falzon 21 on, 7 off QJ2039 Groote Eylandt, Alyangula NT $3,076,024 56% 21 26 Dec 2026

Swings, fly-in fly-out

Eight weeks, 46 people. A booked flight is a travel day off the travel register; everything past the last booking is the crew's own cycle projected forward.

On site Travelling Home Flight booked
People on the ground
Mon 10
Mon 17
Mon 24
Mon 31
Mon 7
Mon 14
Mon 21
Mon 28
Crew 1, Rail 5 on, 2 off QJ2041 0 flights booked in the window
Blake Tuiala Leading Hand
40 days on
Ryan Petrie Roof Plumber
40 days on
Josh Mardin Roof Plumber
40 days on
Dane Kelso Cladding Installer
40 days on
Tyrone Baker Cladding Installer
40 days on
Isaac Vella Rope Access Tech
40 days on
Nick Harrow Cladding Installer
40 days on
Liam O'Shea Apprentice, 3rd yr
40 days on
Kade Whitmore Cladding Installer
40 days on
Shaun Ferris EWP Operator
40 days on
Beau Lansdown Labourer
40 days on
Corey Iona Cladding Installer
40 days on
Crew 2, Bowen Basin 14 on, 7 off QJ2044 3 flights booked in the window
Mitch Ravenscroft Leading Hand
37 days on
Trent Osborne Roof Plumber
37 days on
Damien Yorke Cladding Installer
37 days on
Brody Chan Cladding Installer
37 days on
Angus Petersen Rope Access Tech
37 days on
Wade Tolhurst Sheeting Hand
37 days on
Jesse Mallard Cladding Installer
37 days on
Ashton Reilly Apprentice, 2nd yr
37 days on
Kirk Danaher EWP Operator
37 days on
Nathan Prowse Labourer
37 days on
Rhys Callaghan Cladding Installer
37 days on
Crew 3, FIFO West 21 on, 7 off QJ2006 11 flights booked in the window
Zeb Marchetti Leading Hand
42 days on
Callum Byrne Roof Plumber
42 days on
Deacon Whitely Acoustic Installer
42 days on
Hamish Ngata Acoustic Installer
42 days on
Levi Sandford Cladding Installer
42 days on
Owen Krasnov Sheeting Hand
42 days on
Brett Hallam Rope Access Tech
42 days on
Fletcher Doig Cladding Installer
42 days on
Sione Fatu Labourer
38 days on
Kyle Anderton Apprentice, 1st yr
38 days on
Bailey Rutherford Cladding Installer
38 days on
Crew 4, FIFO North 21 on, 7 off QJ2039 7 flights booked in the window
Dom Falzon Leading Hand
41 days on
Jarrah Winton Roof Plumber
41 days on
Ellis Braithwaite Cladding Installer
41 days on
Tom Gillard Cladding Installer
41 days on
Reece Salvatore Sheeting Hand
41 days on
Marlon Deverell EWP Operator
38 days on
Xavier Pauling Cladding Installer
38 days on
Heath Corrigan Labourer
38 days on
Jai Sutherland Apprentice, 3rd yr
38 days on
Lachlan Ferreira Cladding Installer
42 days on
Riley Cusack Roof Plumber
42 days on
Ned Blackwood Rope Access Tech
42 days on

This is a pay input as much as a plan. Travel time is paid from an hour before departure to thirty minutes after landing, the living-away allowance runs on days away, and both come off these rows straight into the pay run.

Broken down per job

Each job's cost centres, with what is complete and what the hours have run to. This is the detail underneath every bar above.

QJ2006 PROJECT CERES - UREA SHEDS 24 Feb 2026 to 3 Apr 2027 · Ceres urea plant, Karratha
45% complete · $7,497,478
CC-01 52%

Preliminaries & establishment

2,953 of 5,395.4 hours

CC-02 47%

Roofing

4,099.8 of 8,294.9 hours

CC-03 39%

Wall cladding

2,369.1 of 5,919.6 hours

CC-05 51%

Height access & safety systems

1,326.3 of 2,632.8 hours

CC-06 42%

Weatherproofing

641.9 of 1,437.6 hours

CC-08 44%

Direct labour & plant

0 of 0 hours

QJ2039 Groote Island: Mobile Plant Workshop Re-roof 21 Apr 2026 to 26 Dec 2026 · Groote Eylandt, Alyangula NT
56% complete · $3,076,024
CC-01 64%

Preliminaries & establishment

1,756.3 of 2,917.8 hours

CC-02 55%

Roofing

2,690.8 of 4,851.7 hours

CC-03 49%

Wall cladding

457.8 of 945.6 hours

CC-05 57%

Height access & safety systems

914.7 of 1,637.6 hours

CC-06 46%

Weatherproofing

217.1 of 484 hours

CC-08 58%

Direct labour & plant

0 of 0 hours

QJ2046 Downer Rail Maryborough: Periodic Roofing Works 2026 10 Feb 2026 to 26 Dec 2026 · Downer Rail, Maryborough
60% complete · $807,398
CC-01 58%

Preliminaries & establishment

569.6 of 1,008 hours

CC-02 61%

Roofing

642.6 of 1,054.9 hours

CC-03 52%

Wall cladding

73.3 of 142.8 hours

CC-05 59%

Height access & safety systems

433.8 of 740 hours

CC-06 56%

Weatherproofing

251.7 of 442.6 hours

CC-07 68%

Rectification & defects

355.9 of 537 hours

QJ2041 QRSAUP: Brisbane Rail Stations Roofing & Cladding 16 Dec 2025 to 5 Dec 2026 · Banyo, Buranda, Morningside & Lindum stations
61% complete · $4,093,279
CC-01 64%

Preliminaries & establishment

4,960.2 of 7,614.8 hours

CC-02 63%

Roofing

2,960.4 of 4,542.3 hours

CC-03 52%

Wall cladding

1,318 of 2,461.7 hours

CC-05 65%

Height access & safety systems

1,086.8 of 1,695.2 hours

CC-06 53%

Weatherproofing

508.2 of 923.8 hours

QJ2045 M&A Apartments Stage 3: Facade Cladding 26 May 2026 to 7 Nov 2026 · Maroochydore
52% complete · $1,090,514
CC-01 66%

Preliminaries & establishment

732.7 of 1,184.4 hours

CC-03 45%

Wall cladding

784 of 1,677.4 hours

CC-05 63%

Height access & safety systems

296.4 of 460 hours

CC-06 41%

Weatherproofing

190 of 436.8 hours

QJ2047 Mountain Creek SHS: Hall Re-roof & Cladding 7 Jul 2026 to 10 Oct 2026 · Mountain Creek, Sunshine Coast
48% complete · $967,046
CC-01 53%

Preliminaries & establishment

495.1 of 998.4 hours

CC-02 46%

Roofing

1,014.1 of 2,083.8 hours

CC-03 29%

Wall cladding

55.2 of 192 hours

CC-05 78%

Height access & safety systems

120.8 of 160.9 hours

CC-06 32%

Weatherproofing

95.6 of 302.2 hours

QJ2044 BMA Saraji Workshop Upgrade: Cladding 24 Mar 2026 to 3 Oct 2026 · Saraji Mine, Dysart
71% complete · $2,533,376
CC-01 70%

Preliminaries & establishment

1,049.4 of 1,549 hours

CC-02 70%

Roofing

1,852.2 of 2,597.2 hours

CC-03 72%

Wall cladding

2,405.4 of 3,281.9 hours

CC-05 71%

Height access & safety systems

649 of 923.6 hours

CC-06 60%

Weatherproofing

257.2 of 436 hours

CC-08 67%

Direct labour & plant

0 of 0 hours

QJ2038 Boyne Smelters Stockpile Shed: Re-clad & Acoustics 17 Feb 2026 to 5 Sep 2026 · Boyne Island, Gladstone
77% complete · $2,650,824
CC-01 79%

Preliminaries & establishment

1,165.1 of 1,457 hours

CC-02 91%

Roofing

515.5 of 564 hours

CC-03 87%

Wall cladding

2,460.4 of 2,761.4 hours

CC-04 67%

Acoustics

1,969.5 of 2,907.7 hours

CC-05 84%

Height access & safety systems

1,147.6 of 1,369.6 hours

CC-06 68%

Weatherproofing

511.3 of 712.8 hours