VAR-006-02 Demo Cyclone tie-down upgrade, both sheds
Accounting connected Thu 13 Aug 2026
VAR-006-02 Approved QJ2006

Variation 2, Cyclone tie-down upgrade, both sheds

PROJECT CERES - UREA SHEDS · Saipem Clough Joint Venture · their reference SCJV-VO-0246

Raised 3 Jun 2026 by Marcus Deng · approved 23 Jun 2026 by Dean Marchetti

Scope

Priced off the pricing schedule the contract is measured against.

RateRate, ex GSTQtyValueCostMargin
RS-ROF-SAF Safety mesh, install to purlins $24.80/m² 2,180 $54,064.00 $43,730.80 19%
RS-CLD-FLA Custom flashings, supply and install $114.00/lm 480 $54,720.00 $44,400.00 19%
RS-WPF-SEA Sealant to laps, penetrations & flashings $34.80/lm 940 $32,712.00 $25,972.20 21%
Total, ex GST $141,496.00 $114,103.00 19%
GST $14,149.60
Total, inc GST $155,645.60

Why it was raised

Region D wind classification confirmed after award. Fastener pattern and clip spacing both change, which is a quantity change rather than a rate change.

Position

Value, ex GST
$141,496.00
Cost to deliver
$114,103.00
Margin
19.4%
Physically built
86%
Value already on the ground
$121,686.56
Work commenced
Yes, under site instruction

Contract

Contract no.
SCJV-CER-SC-1180
Head contractor
Saipem Clough Joint Venture
Approver
Dean Marchetti
Payment terms
45 days EOM
Open claim
PC-2026-0196

Trail

  1. Raised 3 Jun 2026 by Marcus DengPriced off the job's schedule of rates
  2. Lodged with Saipem Clough Joint VentureTheir reference SCJV-VO-0246
  3. Approved 23 Jun 2026Dean Marchetti · added to the contract sum and the open claim