Variation 2, Cyclone tie-down upgrade, both sheds
PROJECT CERES - UREA SHEDS · Saipem Clough Joint Venture · their reference SCJV-VO-0246
Raised 3 Jun 2026 by Marcus Deng · approved 23 Jun 2026 by Dean Marchetti
Scope
Priced off the pricing schedule the contract is measured against.
| Rate | Rate, ex GST | Qty | Value | Cost | Margin |
|---|---|---|---|---|---|
| RS-ROF-SAF Safety mesh, install to purlins | $24.80/m² | 2,180 | $54,064.00 | $43,730.80 | 19% |
| RS-CLD-FLA Custom flashings, supply and install | $114.00/lm | 480 | $54,720.00 | $44,400.00 | 19% |
| RS-WPF-SEA Sealant to laps, penetrations & flashings | $34.80/lm | 940 | $32,712.00 | $25,972.20 | 21% |
| Total, ex GST | $141,496.00 | $114,103.00 | 19% | ||
| GST | $14,149.60 | ||||
| Total, inc GST | $155,645.60 | ||||
Why it was raised
Region D wind classification confirmed after award. Fastener pattern and clip spacing both change, which is a quantity change rather than a rate change.
Position
- Value, ex GST
- $141,496.00
- Cost to deliver
- $114,103.00
- Margin
- 19.4%
- Physically built
- 86%
- Value already on the ground
- $121,686.56
- Work commenced
- Yes, under site instruction
Contract
- Job
- QJ2006
- Contract no.
- SCJV-CER-SC-1180
- Head contractor
- Saipem Clough Joint Venture
- Approver
- Dean Marchetti
- Payment terms
- 45 days EOM
- Open claim
- PC-2026-0196
Trail
- Raised 3 Jun 2026 by Marcus DengPriced off the job's schedule of rates
- Lodged with Saipem Clough Joint VentureTheir reference SCJV-VO-0246
- Approved 23 Jun 2026Dean Marchetti · added to the contract sum and the open claim