$72.6M

ex GST, current option

Won out of these

5

83% of the decided ones

Rates in the history

51

priced at least once

RS-PRE-SUP CC-01 Preliminaries & establishment

Site supervision, leading hand

Pricing schedule

Schedule rate

$1,248.00 / day

what the pricing schedule says

Priced on

29

5 of them won

Average priced

$1,264.00

+1.3% against schedule

Average when won

$1,248.00

+0.0% against schedule

EstimateClientSiteIssuedQuantityPriced atAgainst scheduleOutcome
Q32419 Stage 9 wall repair Village Roadshow Theme Parks Oxenford 7 Aug 2026 28 day $1,480.00 +18.6% Estimating - Submitted
Q32104 Downer Rail Maryborough: Periodic Works 2027 Downer Rail Maryborough 6 Aug 2026 104 day $1,248.00 list Estimating - In Progress
Q32456 Install only of Acoustic panel Cairns Rosefield Group Cairns 5 Aug 2026 34 day $1,248.00 list Estimating - Pending
Q32415 C19512 Female Ablution Block Groote Eylandt Mining Company Groote Eylandt, NT 2 Aug 2026 24 day $1,248.00 list Estimating - Submitted
Q32638 4x warehouse sheds Brittabull Construction Yeppoon 1 Aug 2026 96 day $1,248.00 list Estimating - In Progress
Q32131 Herston Health Precinct, Plantroom Acoustic Enclosures Hutchinson Builders Herston, Brisbane 1 Aug 2026 74 day $1,248.00 list Estimating - In Progress
Q32400 Mooloolah Valley Distribution Reservoir Dornway Civil Mooloolah Valley 20 Jul 2026 62 day $1,248.00 list Estimating - Pending
Q32441 Hastings Deering Hastings Deering (Australia) Mackay 16 Jul 2026 78 day $1,248.00 list Contract Review
Q32127 Springfield Central Retail, Roof Renewal ADCO Constructions Springfield Central 10 Jul 2026 56 day $1,248.00 list Estimating - Submitted
Q32592 Logan Hyperdome ADCO Constructions Loganholme 8 Jul 2026 118 day $1,480.00 +18.6% Estimating - Pending
Q32125 Wacol Distribution Centre, Cladding & Roofing Walz Group Wacol 4 Jul 2026 64 day $1,248.00 list Estimating - Submitted
Q32588 Coolum Beach Surf Club, roof renewal Mountain Creek State High School, Dept of Education Coolum Beach 30 Jun 2026 32 day $1,248.00 list Contract Review
QPL2376 CONFIDENTIAL - Project Braemer OPB Contractors Undisclosed, QLD 10 Jun 2026 940 day $1,248.00 list Estimating - In Progress
Q32358 Groote Island Groote Eylandt Mining Company Groote Eylandt, NT 7 Jun 2026 268 day $1,248.00 list Estimating - Pending
Q32122 Bengalla VDC Re-roof Stage 2 Bengalla Mining Company Bengalla Mine, Muswellbrook 6 Jun 2026 104 day $1,248.00 list Won
Q27686 Bengalla CHPP Family Constructions Bengalla Mine, Muswellbrook 5 Jun 2026 218 day $1,248.00 list Estimating - Submitted
Q32582 Groote Island Gemco MWS Re-roof Groote Eylandt Mining Company Groote Eylandt, NT 26 May 2026 186 day $1,248.00 list Estimating - In Progress
Q32364 Groote Island, Flo Jo's Groote Eylandt Mining Company Groote Eylandt, NT 14 May 2026 124 day $1,248.00 list Estimating - Submitted
Q32119 Northshore Hamilton: Commercial Roof Package McNab Constructions Hamilton, Brisbane 22 Apr 2026 48 day $1,248.00 list Lost
Q32118 Mountain Creek SHS, Hall Re-roof Mountain Creek State High School, Dept of Education Mountain Creek 9 Apr 2026 68 day $1,248.00 list Won
Q32235 The Mine, Burnett Highway Morgan Projects Burnett Highway 28 Feb 2026 186 day $1,248.00 list Contract Review
Q32116 M&A Apartments Stage 3: Facade Cladding M&A Developments Maroochydore 27 Feb 2026 88 day $1,248.00 list Won
Q32916 Hillgrove Mine MACA Interquip Hillgrove Mine, Armidale NSW 27 Jan 2026 148 day $1,248.00 list Estimating - Pending
T-2025-0092 Saraji Workshop Upgrade: Cladding BHP Mitsubishi Alliance Saraji Mine, Dysart 23 Dec 2025 126 day $1,248.00 list Won
Q22087 Mineral Sands Plant Ausenco Services Capel, WA 18 Nov 2025 168 day $1,248.00 list Estimating - Submitted
T-2025-0088 Boyne Smelters Stockpile Shed: Re-clad & Acoustics Rio Tinto Aluminium Boyne Island 14 Nov 2025 118 day $1,248.00 list Won
Q32096 Caloundra Sth West Primary School, Stage 2 Hutchinson Builders Caloundra South 28 Oct 2025 86 day $1,248.00 list Estimating - Submitted
Q27503 Processing Building Townsville Sedgman Pty Ltd Townsville 12 Sep 2024 118 day $1,248.00 list Estimating - Submitted
Q27693 Ravensworth Coal Glencore Coal Assets Australia Ravensworth, NSW 18 Jul 2024 96 day $1,248.00 list Estimating - Submitted

A rate priced above the schedule is a loaded rate: difficult access, a shutdown, freight, or a client QClad have been burnt by. Priced below is a sharpened one. Either way it is on the record, so the next estimator can see what was done and why rather than starting from the list price.

Matches

Newest first. Each row shows which of its priced lines matched.

Q32419 Estimating - Submitted

Stage 9 wall repair

Village Roadshow Theme Parks · Oxenford · issued 7 Aug 2026 · Priya Raghavan

Strip and replace damaged wall sheeting to the Stage 9 back-of-house elevation, renew flashings and cappings and reseal all penetrations. Park operating, so work is out of hours.

28 day at $1,480.00 = $41,440

$217,346

11 lines

21%
Q32104 Estimating - In Progress

Downer Rail Maryborough: Periodic Works 2027

Downer Rail · Maryborough · issued 6 Aug 2026 · Priya Raghavan

Renewal of the standing schedule of rates for periodic roofing, leak rectification and sheet replacement across the Maryborough facility for calendar 2027.

104 day at $1,248.00 = $129,792

$851,584

10 lines

15%
Q32456 Estimating - Pending 10/4

Install only of Acoustic panel Cairns

Rosefield Group · Cairns · issued 5 Aug 2026 · Priya Raghavan

Install only of client-supplied acoustic absorption panel and perforated liner tray to the plantroom walls and ceiling, including isophonic mounts and post-installation verification test.

34 day at $1,248.00 = $42,432

$330,538

11 lines

19%
Q32415 Estimating - Submitted

C19512 Female Ablution Block

Groote Eylandt Mining Company · Groote Eylandt, NT · issued 2 Aug 2026 · Priya Raghavan

Roof and wall cladding to a new female ablution block, including insulation, flashings, rainwater goods and weatherproofing.

24 day at $1,248.00 = $29,952

$202,150

12 lines

18%
Q32638 Estimating - In Progress

4x warehouse sheds

Brittabull Construction · Yeppoon · issued 1 Aug 2026 · Priya Raghavan

Roof and wall cladding to four new warehouse sheds: TRIMDEK roof, CUSTOM ORB wall, insulation, safety mesh, flashings, cappings, rainwater goods and roof anchors to each.

96 day at $1,248.00 = $119,808

$2,047,008

17 lines

18%
Q32131 Estimating - In Progress

Herston Health Precinct, Plantroom Acoustic Enclosures

Hutchinson Builders · Herston, Brisbane · issued 1 Aug 2026 · Dylan Fraser

Supply and install acoustic enclosures, absorption panel, liner tray and isophonic mounts to four rooftop plantrooms, with independent verification testing to 38 dB(A) at the boundary.

74 day at $1,248.00 = $92,352

$1,054,494

11 lines

19%
Q32400 Estimating - Pending

Mooloolah Valley Distribution Reservoir

Dornway Civil · Mooloolah Valley · issued 20 Jul 2026 · Dylan Fraser

Strip and renew the reservoir roof in KLIP-LOK 700, replace corroded purlins on a provisional quantity, renew safety mesh, ridge and rainwater goods, and install an anchor and static line system for future access.

62 day at $1,248.00 = $77,376

$724,376

15 lines

17%
Q32441 Contract Review

Hastings Deering

Hastings Deering (Australia) · Mackay · issued 16 Jul 2026 · Priya Raghavan

Strip and replace the Wheel Ends workshop roof in KLIP-LOK 700, renew safety mesh and roof lighting, replace box gutters and downpipes, and install a permanent anchor and static line system.

78 day at $1,248.00 = $97,344

$1,084,248

17 lines

17%
Q32127 Estimating - Submitted

Springfield Central Retail, Roof Renewal

ADCO Constructions · Springfield Central · issued 10 Jul 2026 · Priya Raghavan

Strip and re-sheet the retail roof in KLIP-LOK 406, new blanket insulation, safety mesh, box gutters and roof lighting.

56 day at $1,248.00 = $69,888

$816,296

10 lines

18%
Q32592 Estimating - Pending

Logan Hyperdome

ADCO Constructions · Loganholme · issued 8 Jul 2026 · Priya Raghavan

Strip and re-sheet the northern retail wing in KLIP-LOK 406, renew box gutters and rainwater goods, install a permanent anchor and static line system, and weatherproof all penetrations. Trading centre, so all work is out of hours.

118 day at $1,480.00 = $174,640

$1,852,362

17 lines

18%
Q32125 Estimating - Submitted

Wacol Distribution Centre, Cladding & Roofing

Walz Group · Wacol · issued 4 Jul 2026 · Priya Raghavan

New KLIP-LOK 700 wall cladding and TRIMDEK roof sheeting to the distribution centre, flashings, personnel doors and sealant.

64 day at $1,248.00 = $79,872

$1,460,526

10 lines

19%
Q32588 Contract Review Insurance

Coolum Beach Surf Club, roof renewal

Mountain Creek State High School, Dept of Education · Coolum Beach · issued 30 Jun 2026 · Priya Raghavan

Strip and renew the eastern pavilion roof in KLIP-LOK 700 with insulation, safety mesh, ridge, box gutter and downpipes. Salt-air specification throughout.

32 day at $1,248.00 = $39,936

$304,506

13 lines

17%
QPL2376 Estimating - In Progress Confidential 14/7

CONFIDENTIAL - Project Braemer

OPB Contractors · Undisclosed, QLD · issued 10 Jun 2026 · Dylan Fraser

Supply and install Kingspan KS1000 RW insulated panel to the process buildings, cold stores and control rooms of an energy hub development, with EquiDeck insulated roof panel, full weatherproofing and permanent access systems throughout.

940 day at $1,248.00 = $1,173,120

$27,891,784

18 lines

17%
Q32358 Estimating - Pending 21/7

Groote Island

Groote Eylandt Mining Company · Groote Eylandt, NT · issued 7 Jun 2026 · Dylan Fraser

A bundled price across four structures on Groote: the heavy vehicle wash bay, the reagent store, the crib and change facility and the conveyor transfer house. Roof, wall, safety systems and weatherproofing to each.

268 day at $1,248.00 = $334,464

$4,440,878

23 lines

20%
Q32122 Won

Bengalla VDC Re-roof Stage 2

Bengalla Mining Company · Bengalla Mine, Muswellbrook · issued 6 Jun 2026 · Dylan Fraser

Strip and re-sheet the VDC roof in Stramit Speed Deck Ultra over new purlins, with safety mesh, blanket insulation, box gutters and a certified static line system.

104 day at $1,248.00 = $129,792

$1,765,226

16 lines

17%
Q27686 Estimating - Submitted 14/7

Bengalla CHPP

Family Constructions · Bengalla Mine, Muswellbrook · issued 5 Jun 2026 · Dylan Fraser

Full re-roof of the coal preparation plant over live process equipment: strip, purlin renewal on a provisional quantity, KLIP-LOK 700, insulation, safety mesh, ridge ventilators and a permanent static line system.

218 day at $1,248.00 = $272,064

$2,796,934

22 lines

19%
Q32582 Estimating - In Progress 21/7

Groote Island Gemco MWS Re-roof

Groote Eylandt Mining Company · Groote Eylandt, NT · issued 26 May 2026 · Dylan Fraser

Second stage re-roof over the mobile plant workshop: strip, purlin renewal on a measured quantity, KLIP-LOK 700, insulation, safety mesh, roof lighting and full rainwater goods, over a live workshop.

186 day at $1,248.00 = $232,128

$2,989,072

21 lines

20%
Q32364 Estimating - Submitted 21/7

Groote Island, Flo Jo's

Groote Eylandt Mining Company · Groote Eylandt, NT · issued 14 May 2026 · Dylan Fraser

Replace corroded structural elements and purlins and re-roof the Flo Jo's accommodation and messing structures, including safety mesh, rainwater goods and a permanent access system.

124 day at $1,248.00 = $154,752

$1,626,630

19 lines

19%
Q32119 Lost

Northshore Hamilton: Commercial Roof Package

McNab Constructions · Hamilton, Brisbane · issued 22 Apr 2026 · Priya Raghavan

TRIMDEK roof sheeting, insulation, safety mesh, box gutters and roof lighting to the commercial building.

48 day at $1,248.00 = $59,904

$581,852

9 lines

17%
Q32118 Won

Mountain Creek SHS, Hall Re-roof

Mountain Creek State High School, Dept of Education · Mountain Creek · issued 9 Apr 2026 · Priya Raghavan

Strip and re-sheet the hall roof in KLIP-LOK 406 with insulation, safety mesh, new gutters and downpipes, plus edge protection for the duration.

68 day at $1,248.00 = $84,864

$945,534

17 lines

17%
Q32235 Contract Review 14/7

The Mine, Burnett Highway

Morgan Projects · Burnett Highway · issued 28 Feb 2026 · Dylan Fraser

Roof and wall cladding to the H1 extra buildings: workshop, wash bay, store and crib. Insulated panel to the crib, sheet elsewhere, with permanent access systems throughout.

186 day at $1,248.00 = $232,128

$3,051,040

22 lines

19%
Q32116 Won

M&A Apartments Stage 3: Facade Cladding

M&A Developments · Maroochydore · issued 27 Feb 2026 · Dylan Fraser

Fielders Finesse architectural panel to the street elevations, KingKlip to the return walls, cappings, membrane and sealant.

88 day at $1,248.00 = $109,824

$1,063,286

12 lines

13%
Q32916 Estimating - Pending 14/7

Hillgrove Mine

MACA Interquip · Hillgrove Mine, Armidale NSW · issued 27 Jan 2026 · Dylan Fraser

Roof and wall cladding to the concentrate filter extension and the tails filter building, including insulated panel to the filter room, safety mesh, anchor and static line systems and full weatherproofing.

148 day at $1,248.00 = $184,704

$2,698,446

21 lines

19%

Saraji Workshop Upgrade: Cladding

BHP Mitsubishi Alliance · Saraji Mine, Dysart · issued 23 Dec 2025 · Dylan Fraser

Strip and replace roof sheeting and wall cladding to the heavy workshop, purlin renewal, louvres, personnel doors and a certified anchor system.

126 day at $1,248.00 = $157,248

$2,470,624

21 lines

19%
Q22087 Estimating - Submitted 14/7

Mineral Sands Plant

Ausenco Services · Capel, WA · issued 18 Nov 2025 · Dylan Fraser

Cladding and acoustic treatment to the mineral sands plant: insulated panel to the process building, mass-loaded barrier and absorption panel to the screening tower, roof sheeting throughout and a verification test at the boundary.

168 day at $1,248.00 = $209,664

$2,570,588

19 lines

18%

Boyne Smelters Stockpile Shed: Re-clad & Acoustics

Rio Tinto Aluminium · Boyne Island · issued 14 Nov 2025 · Dylan Fraser

Re-clad the stockpile shed and install an acoustic enclosure to the transfer tower, verified by independent sound test.

118 day at $1,248.00 = $147,264

$2,542,100

19 lines

15%
Q32096 Estimating - Submitted

Caloundra Sth West Primary School, Stage 2

Hutchinson Builders · Caloundra South · issued 28 Oct 2025 · Priya Raghavan

Roof and wall cladding to Blocks C and D: KLIP-LOK 406 roof, Fielders Finesse architectural cladding to the street elevations, CUSTOM ORB elsewhere, insulation, safety mesh, rainwater goods and permanent roof anchors.

86 day at $1,248.00 = $107,328

$1,496,856

19 lines

18%
Q27503 Estimating - Submitted

Processing Building Townsville

Sedgman Pty Ltd · Townsville · issued 12 Sep 2024 · Priya Raghavan

Budget pricing only for the roof and wall cladding to a new processing building, for Sedgman's feasibility study. Rates current at the date of issue.

118 day at $1,248.00 = $147,264

$1,347,684

10 lines

18%
Q27693 Estimating - Submitted 14/7

Ravensworth Coal

Glencore Coal Assets Australia · Ravensworth, NSW · issued 18 Jul 2024 · Dylan Fraser

Strip and replace corroded wall sheeting and girts to the CHPP and the reclaim tunnel headhouse, including flashings, cappings and weatherproofing.

96 day at $1,248.00 = $119,808

$1,366,084